Change Process Improvements following Code Manager review

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This Change Proposal has been raised to make the required changes to Schedule1 and Schedule 5, to enable process enhancements to be made to support Change Process Improvements project.

Latest update and next planned activity

Date of latest update
Latest Update
19/07/24 - This change was implemented on the 19 July 2024.

Impacts Overview

Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
Feedback gathered has highlighted issues with the current process including speed of the process, engagement, and inefficiencies. Amendments are required to Schedule 1 and Schedule 5, that will support the provision of a suite of enhancements to the Change Process.
Proposed solution summary
  1. As a Consumer, I want REC issues and changes that impact Consumers to be developed with Parties and Market Participants input, with minimal delay or hassle, so that I can benefit from positive Consumer outcomes at the earliest opportunity.
  2. As a REC Party or Market Participant, I want to participate effectively and efficiently in the REC Change Process including the development and progression of industry issues, to shape and develop solutions.

No documents available.

Change Plan

Preliminary Change Reports Published

Completed

Start:

25 Apr 2024

Due:

17 May 2024

Completion:

17 May 2024

Consultation Published

Completed

Start:

17 May 2024

Due:

17 May 2024

Completion:

17 May 2024

Final Change Report Published

Completed

Start:

17 May 2024

Due:

07 Jun 2024

Completion:

25 Jun 2024

Responsible Committee Decison

Completed

Start:

07 Jun 2024

Due:

18 Jun 2024

Completion:

02 Jul 2024

Original submission

Change details

- - -
25 Apr 2024

Change details

Change Process Improvements following Code Manager review
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

Yes
-
-
-
No details provided
-

Activity

Proposed solution summary changed to As a Consumer, I want REC issues and changes that impact Consumers to be developed with Parties and Market Participants input, with minimal delay or hassle, so that I can benefit from positive Consumer outcomes a…
Show more
Implementation Date has been updated to 19 Jul 2024.