Consequential REC changes for BSC CP1532
Summary
_
Latest update and next planned activity
Date of latest update
Latest Update
_
Impacts Overview
Priority and rationale
High
Priority last updated on 29 May 2026
Solution development
Problem Statement
BSC CP1532 proposed updates to the Change of Supply (CoS) timescales within BSC Procedures BSCP502, BSCP504 and BSCP514, to align the Half-Hourly and Non-Half Hourly Supplier Agent Appointment and de-Appointment timescales and to facilitate the achievement of the Faster Switching programme objectives. BSC CP1532 was approved on 01 September 2021 by the Supplier Volume Allocation Group (SVG). Following the SVG’s decision to approve, BSCP514 moved to the Retail Energy Code (REC) following the implementation of P420 ‘Retail Code Consolidation Significant Code Review’. A REC Change Proposal is therefore required to deliver the full solution.
Proposed solution summary
- As an electricity Consumer I want my new Energy Supplier to set up my account and appoint their agents appropriately, so I receive timely and accurate bills.
- As a Market Participant, I need to understand any changes to Market Messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
- As an Energy Supplier, I want to be able to Appoint and De-appoint Agents more quickly, to minimise risks to my settlement performance and ability to produce accurate and timely consumer bills when the new switching arrangements go-live.
No documents available.
Change Plan
Initial Assessment Report and Change Proposal Plan approved
Completed
Start:
26 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Preliminary Change Report issued
Completed
Start:
21 Dec 2021Due:
28 Jan 2022Completion:
28 Jan 2022Preliminary Change Report approval
Completed
Start:
28 Jan 2022Due:
09 Feb 2022Completion:
09 Feb 2022Consultation starts
Completed
Start:
09 Feb 2022Due:
14 Feb 2022Completion:
11 Feb 2022Consultation ends
Completed
Start:
14 Feb 2022Due:
04 Mar 2022Completion:
04 Mar 2022Final Change Report Issued
Completed
Start:
04 Mar 2022Due:
11 Mar 2022Completion:
11 Mar 2022Responsible Committee decision (ex-Committee)
Completed
Start:
11 Mar 2022Due:
23 Mar 2022Completion:
22 Mar 2022Original submission
Change details
- - -
26 Nov 2021
Change details
Consequential REC changes for BSC CP1532
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
No
-
-
-
No details provided
-