Market-wide Half-Hourly Settlement Implementation
Summary
_
Latest update and next planned activity
Date of latest update
Latest Update
_
Impacts Overview
Priority and rationale
High
Priority last updated on 29 May 2026
Solution development
Problem Statement
The successfully introduction of Market-wide Half-Hourly Settlement (MHHS) requires changes to made to the systems and processes governed by other codes outside of the BSC, including the REC. Elexon as the Senior Responsible Owner (SRO) and Ofgem as the Programme Sponsor for the MHHS programme need assurance that all programme participants will support the implementation of the programme and deliver against the approved timetable. While there is a general ‘duty to cooperate’ with Significant Code Reviews that exists for licenced parties, there is no explicit legal requirement for RECCo (as a non-BSC Party) to support this and no contractual recourse if its duties are not met.
Proposed solution summary
- As the Senior Responsible Owner for the Market-wide Half-Hourly Settlement programme, I need assurance that all programme participants will deliver the required changes in accordance with programme plan, so Market-wide Half-Hourly settlement can be introduced and implemented successfully.
No documents available.
Change Plan
Initial Assessment Report published
Completed
Start:
01 Sep 2021Due:
03 Sep 2021Completion:
03 Sep 2021Change Panel review
Completed
Start:
03 Sep 2021Due:
07 Sep 2021Completion:
07 Sep 2021Preliminary Change Report published
Completed
Start:
07 Sep 2021Due:
09 Sep 2021Completion:
09 Sep 2021Consultation start
Completed
Start:
09 Sep 2021Due:
14 Sep 2021Completion:
14 Sep 2021Consultation end
Completed
Start:
14 Sep 2021Due:
20 Sep 2021Completion:
20 Sep 2021Final Change Report published
Completed
Start:
20 Sep 2021Due:
24 Sep 2021Completion:
24 Sep 2021Change Panel decision
Completed
Start:
24 Sep 2021Due:
05 Oct 2021Completion:
05 Oct 2021Original submission
Change details
- - -
1 Sep 2021
Change details
Market-wide Half-Hourly Settlement Implementation
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
Yes
-
-
-
No details provided
-