MHHS Incremental Changes for go live

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This Issue looks to assess and confirm the scope to be taken forward into the Change Proposal that will deliver critical updates to the REC MHHS Code Drafting. Any potential scope items that have material impacts over and above the approved MHHS design will be considered as having unacceptable risk to the intended Change Proposal and will not be included in the confirmed scope.

Latest update and next planned activity

Date of latest update
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.

Impacts Overview

Priority and rationale

Priority last updated on 29 May 2026

Solution development

Problem Statement
It is critical to the implementation of MHHS that design changes approved by the MHHS Programme are reflected in the REC MHHS Code Drafting. The REC MHHS Code Drafting was approved by the Authority, to meet MHHS Programme Milestone M7, through R0209 and incremental changes that were not included under that Change Proposal, now need to be taken through REC change governance as captured under the R0209 RAID, Risk R001 and Assumptions A005 and A006.

No documents available.

Change Plan

Change Proposal Plan approved

Completed

Start:

30 Jan 2025

Due:

04 Mar 2025

Completion:

04 Mar 2025

Issue scope developed and presented at Change Issues Group meetings (06 March, 03 April, 01 May)

Completed

Start:

04 Mar 2025

Due:

01 May 2025

Completion:

01 May 2025

Solution and legal drafting presented to Code Drafting Working Group

Completed

Start:

01 May 2025

Due:

13 May 2025

Completion:

13 May 2025

Solution and legal drafting endorsed by Cross Code Advisory Group

Completed

Start:

13 May 2025

Due:

28 May 2025

Completion:

28 May 2025

Ofgem direction received

Completed

Start:

28 May 2025

Due:

04 Jun 2025

Completion:

04 Jun 2025

Consultation published

Completed

Start:

04 Jun 2025

Due:

17 Jun 2025

Completion:

17 Jun 2025

Change Report (Consultation) approved at Change Panel

Completed

Start:

17 Jun 2025

Due:

17 Jun 2025

Completion:

17 Jun 2025

REC Change Panel vote on Code Manager's recommendation

Completed

Start:

17 Jun 2025

Due:

15 Jul 2025

Completion:

15 Jul 2025

Authority referral sent

Completed

Start:

15 Jul 2025

Due:

17 Jul 2025

Completion:

16 Jul 2025

Authority decision published

In Progress

Start:

17 Jul 2025

Due:

05 Sep 2025

Completion:

Original submission

Change details

- - -
30 Jan 2025

Change details

MHHS Incremental Changes for go live
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Implementation Date has been updated to MHHS Programme Milestone M8 (Code changes delivered).
harriet.truss has been allocated as Lead Analyst.
Orphaned SME: Lead Technical Analyst, vaishnsharma have been allocated as SME.