Micro-business Smart Meter Installation Reports

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
_

Latest update and next planned activity

Date of latest update
Latest Update
_

Impacts Overview

Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
Energy Suppliers do not currently have the ability to assess their Micro-Business Smart Meter installation performance relative to other Energy Suppliers through Consumer Survey Reports, therefore may not take any appropriate action to address any areas of underperformance or respond to trends in Consumer feedback, wider than their own Consumer base. This could affect the Smart Meter installation service received by Micro-Business Consumers.
Proposed solution summary
  1. As a Micro-Business Consumer, I want my Energy Supplier to complete my Smart Meter installation in line with, or above, the standards of service provided by other Energy Suppliers, so that the installation of the Smart Meter has minimal disruption to my business.
  2. As an Energy Supplier to Micro-Business Consumers, I want access to Consumer feedback from across the industry, to enable me to assess my performance relative to other Micro-Business Energy Suppliers and identify areas of under or over performance, enabling me to take appropriate actions to increase or maintain my performance.

No documents available.

Change Plan

Legal text drafting initiated

Completed

Start:

07 Feb 2022

Due:

02 May 2022

Completion:

02 May 2022

Legal text drafting completed

Completed

Start:

02 May 2022

Due:

16 May 2022

Completion:

16 May 2022

Service Provider IA completed

Completed

Start:

16 May 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Preliminary Change Report issued

Completed

Start:

14 Jun 2022

Due:

01 Jul 2022

Completion:

01 Jul 2022

Consultation completed

Completed

Start:

01 Jul 2022

Due:

22 Jul 2022

Completion:

22 Jul 2022

Final Change Report issued

Completed

Start:

22 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022

Responsible Committee Decision

Completed

Start:

05 Aug 2022

Due:

16 Aug 2022

Completion:

16 Aug 2022

Original submission

Change details

- - -
7 Feb 2022

Change details

Micro-business Smart Meter Installation Reports
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Proposed solution summary changed to As a Micro-Business Consumer, I want my Energy Supplier to complete my Smart Meter installation in line with, or above, the standards of service provided by other Energy Suppliers, so that the installation of the…
Show more
Implementation Date has been updated to 04 Nov 2022.
colette.baldwin has been allocated as Lead Analyst.