New value for Site Visit Check Code (J0024)

  • 1
    Rejected
Step 1 of 1
Rejected
Summary
The Change introduces a change to the MM00036/(D0139), to introduce a new Site Visit Check Code to reflect site specific capacity charges being levied by the Distribution Network Operators (DNOs) on Suppliers for their Consumers.

Latest update and next planned activity

Date of latest update
Latest Update
12/10/2023 - Change Proposal has been rejected, as the change needs to be raised under the Balancing & Settlement Code - as the impacted Data Item is a BSC owned Data Item, and is not able to be amended by a REC Change.

Impacts Overview

Priority and rationale
High

Priority last updated on 29 May 2026

Solution development

Problem Statement
DNOs need to be able to communicate to Suppliers that they will charge site-specific DUoS for de-energised sites where there is an ongoing need for the connection to be maintained.
Proposed solution summary
  1. As a Consumer, I need my Supplier to be aware of any charges that will be applied by the DNO for the provision of the connection while the site is De-energised.
  2. As a Supplier I need to know if charges are expected to be levied by the DNO for retained capacity for De-energised Metering Points, so that I can pass the costs on to my Consumer.

No documents available.

Change Plan

Impact Assessment Report Published

Completed

Start:

14 Aug 2023

Due:

25 Aug 2023

Completion:

25 Aug 2023

Original submission

Change details

- - -
14 Aug 2023

Change details

New value for Site Visit Check Code (J0024)
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

Yes
-
-
-
No details provided
-

Activity

Proposed solution summary changed to As a Consumer, I need my Supplier to be aware of any charges that will be applied by the DNO for the provision of the connection while the site is De-energised.As a Supplier I need to know if charges are expected…
Show more
colette.baldwin has been allocated as Lead Analyst.