Summary
DCUSA change DCP467 has been raised to propose that Category A and B defects reported currently using the Asset Condition Report (D0135) or phone call to the DNO, should instead be reported via an online reporting tool where the DNO has one available. This is expected to have impacts to the REC.

Latest update and next planned activity

Date of latest update
Latest Update
08/07/2026 - the Metering Expert Panel approved the Update to Plan.

Impacts Overview

Impacted REC Parties and Market Participants
Distribution Network Operator Electricity Metering Operative Energy Supplier Meter Operator Agent
Other Industry Codes impacted
Distribution Connection and Use of System Agreement (DCUSA)
Priority and rationale
Standard

Priority last updated on 17 Sep 2026

Solution development

Problem Statement
Where DNOs have enhanced reporting tools for Category A or Category B situations, it is not mandatory for Parties to submit reports using this method. This may lead to a detrimental Consumer experience, as it is limited what information can be provided over the telephone or via Market Message (e.g. it is not possible to provide photographs of the situation).

No documents available.

There is currently no Change Plan.

Original submission

Change details

- - -
20 Jan 2026

Change details

REC Change to Align with DCP467 Asset Condition Reporting
DCUSA change DCP467 has been raised to propose that for Category A and B defects reported currently using the Asset Condition Report (D0135) or phone call to the DNO, should instead be reported via an online reporting tool where the DNO has one available. This is expected to have impacts to the REC.
This is expected to have impacts to the REC, to the Service Termination Issue Reporting (STIR) Guidance document and potentially to the D0135 or D0126 data flows which are both owned by the REC.

If only the STIR Guidance document is impacted, this still needs to be processed a full Change Proposal rather than a Category 3 CP due to there being a change in obligations.
To be determined, this is currently being discussed under DCUSA work groups.
-

Impacts

No details provided
On site experience, Security of supply
-
No details provided
-
No details provided
-
No details provided
-
Market Message Catalogue
-
No details provided
-
No details provided
-
Distribution Network Operators, Electricity Metering Operative, Energy Suppliers, Meter Operator Agent
-
Distribution Connection and Use of System Agreement (DCUSA)
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
On site experience, Security of supply

Activity