Revision to the Consolidated Metering Code of Practice (CoMCoP)

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
Following the implementation of the Consolidated Metering Code of Practice (CoMCoP) a number of issues have been identified by RECCo, The Code Manager and REC Parties, stating that REC Parties are unable to meet their obligations as currently presented in the CoMCoP. The Code Manager has reviewed these and determined changes are required.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.

Impacts Overview

Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
MEMs are struggling to successfully pass their CoMCoP audits and be compliant, due to inconsistencies and lack of clarity in the document. There has been concern expressed by MEMs, that when contracting with Energy Suppliers, they are proclaiming themselves compliant with the CoMCoP when this may or may not be true.
Proposed solution summary
  1. As a Consumer, I trust my Energy Supplier and their associated agents to have a robust metering framework to ensure the safety and accuracy of my meter.
  2. As an Energy Supplier, MEM or DNO, I need clear and correct documentation so I can identify the obligations I need to meet within my role and satisfy my audit criteria.
  3. As an Energy Supplier, I need to know that any MEM or DNO I work with is compliant to ensure the best practice for my customers.
  4. As the Metering Scheme Auditor, I need clear and correct documentation to ensure I can fulfil my role and provide confidence that REC Parties are meeting their obligations.

No documents available.

Change Plan

Extension to Plan V2.0 approved at Change Panel

Completed

Start:

Due:

Completion:

04 Feb 2025

Original submission

Change details

- - -
3 Nov 2023

Change details

Revision to the Consolidated Metering Code of Practice (CoMCoP)
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Proposed solution summary changed to As a Consumer, I trust my Energy Supplier and their associated agents to have a robust metering framework to ensure the safety and accuracy of my meter.As an Energy Supplier, MEM or DNO, I need clear and correct…
Show more
Status has been changed to Implemented.
Implementation Date has been updated to 07 Nov 2025.
caroline.milner, djrodgers have been allocated as SME.