Schedule 14 - Metering Operations Footnote Review
Summary
The footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant. This Change Proposal looks to correct issues within the footnotes and move them into the legal text to prevent this from happening when future Change Proposals impacting this schedule are implemented.
Latest update and next planned activity
Date of latest update
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Impacts Overview
Impacted Consumers
Electricity
Gas
Domestic
Non-Domestic
Impacted REC Documents
Schedule 14 - Metering Operations
Priority and rationale
High
Priority last updated on 29 May 2026
Solution development
Problem Statement
REC parties are unable to ensure their processes and procedures correctly reflect their obligations as the footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant.
No documents available.
Change Plan
Change Proposal Plan and Impact Assessment Report issued
Completed
Start:
06 Jun 2024Due:
18 Jun 2024Completion:
18 Jun 2024Preliminary Change Report issued
Completed
Start:
18 Jun 2024Due:
19 Jun 2024Completion:
19 Jun 2024Consultation issued
Completed
Start:
19 Jun 2024Due:
19 Jun 2024Completion:
19 Jun 2024Consultation Close
Completed
Start:
19 Jun 2024Due:
10 Jul 2024Completion:
10 Jul 2024Final Change Report Issued
Completed
Start:
10 Jul 2024Due:
11 Jul 2024Completion:
11 Jul 2024Responsible Committee Decision
Completed
Start:
11 Jul 2024Due:
19 Jul 2024Completion:
19 Jul 2024Appeal Window Closure
Not Started
Start:
19 Jul 2024Due:
02 Aug 2024Completion:
Original submission
Change details
Holly Law - Code Manager
6 Jun 2024
Change details
Schedule 14- Metering Operations Footnote Review
The footnotes within Schedule 14- Metering Operations are not in the correct order, have been removed incorrectly or are irrelevant.
Because of the ordering issue, the volume of footnotes and how they are referenced in tables, guidance on processes that need to be followed are not correct and difficult to follow.
The footnotes need to be reviewed so they are correct and referenced in the right places within process tables and are easier to follow.
-
Impacts
Electricity, Gas, Domestic Prepayment, Domestic Credit, Small and Medium Enterprise (SME), Industrial and Commercial (I&C), Other (please specify in the Additional information box below)
Trust and confidence
-
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No
No details provided
Priority & timing
No
-
Yes- needs to be approved before the end of July so can be included MHHS drafting.
-
No details provided
-