Schedule 14 review – DNOs do not remove Metering Assets

  • 1
    Issue Withdrawn
Step 1 of 1
Issue Withdrawn
Summary
As part of the REC Code drafting for MHHS, an issue has been identified with the current drafting of Metering Operations Schedule. This sets out the processes for the removal of a meter (and metering assets) by the DNOs. DNOs would only remove CTs and VTs and not the actual meters. The text should be reviewed and revised to reflect what happens and what activity DNOs complete.

Latest update and next planned activity

Date of latest update
Latest Update
18/12/2025 - the Code Manager has withdrawn this Issue following discussions at the Metering Expert Panel on 10 December 2025, where Panel members advised there were a small number of niche scenarios where a DNO may remove a Metering Asset (e.g. emergencies). On this basis, the Code Manager believes it appropriate this remains within Schedule 14. If you wish to adopt this REC Issue, please contact the Code Manager by COB 07 January 2026.

Impacts Overview

Impacted REC Parties and Market Participants
Distribution Network Operator
Impacted REC Documents
Schedule 14 - Metering Operations
Priority and rationale

Priority last updated on 29 May 2026

Solution development

No documents available.

Change Plan

Change Proposal approved

Completed

Start:

28 Oct 2025

Due:

24 Jan 2026

Completion:

24 Jan 2026

Test

In Progress

Start:

24 Jan 2026

Due:

24 Mar 2026

Completion:

Original submission

Change details

- - -
28 Oct 2025

Change details

Schedule 14 review – DNOs do not remove Metering Assets
As part of the REC Code drafting for MHHS, an issue has been identified with the current drafting of Metering Operations Schedule. This sets out the processes for the removal of a meter (and metering assets) by the DNOs. DNOs would only remove CTs and VTs and not the actual meters. The text should be reviewed and revised to reflect what happens and what activity DNOs complete.
Schedule 14 being inaccurate could lead to confusion around the obligations and processes required of REC Parties.
A review of Schedule 14 to ensure this process is accurate and reflects the obligations and processes of DNO Parties.
n/a

Impacts

No details provided
On site experience, Safety
-
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Distribution Network Operators
-
No details provided
-
-
No details provided

Priority & timing

Yes
-
-
-
No details provided
On site experience, Safety

Activity

Status has been changed to Withdrawn.
Status has been changed to Issue Withdrawn.
Status has been changed to Issue Review.