Issue Review
Summary
Currently within Schedule 23 a Registration can only be undertaken on RMPs with an Operational or Dormant RMP Status, and not Terminated. Terminated is a status that the RMP is set to when the Meter Point Status is no longer operational or the site is isolated. It is right that these sites are not able to be Registered as there is a risk that Suppliers could inadvertently Register such Meter Points. We do have instances where such sites are stranded in defunct Supplier portfolios - and the Supplier no longer has the capability to take the relevant action to Deactivate the Registrations. This may because the operational staff have left and the business is in administration.

Latest update and next planned activity

Date of latest update
Latest Update
27/02/2025 - Change is now not being merged into any other changes and will proceed as a standalone change. A potential solution has been identified, but will be discussed for potential cross code impacts

Impacts Overview

Impacted Consumers
Gas
Impacted REC Parties and Market Participants
Energy Supplier Shipper Other
Impacted REC Documents
Schedule 23 - Registration Services
Impacted REC Services
Central Switching Service (CSS)
Other Industry Codes impacted
Uniform Network Code (UNC) Independent Gas Transporters (IGT) Uniform Network Code (UNC)
Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

No documents available.

Change Plan

Discussed at Technical Change Workshop

Completed

Start:

Due:

Completion:

25 Feb 2025

Original submission

Change details

David Addison - Xoserve
21 Oct 2024

Change details

Stranded RMPs in Defunct Suppliers
Currently within Schedule 23 a Registration can only be undertaken on RMPs with an Operational or Dormant RMP Status, and not Terminated. Terminated is a status that the RMP is set to when the Meter Point Status is no longer operational or the site is isolated. It is right that these sites are not able to be Registered as there is a risk that Suppliers could inadvertently Register such Meter Points. We do have instances where such sites are stranded in defunct Supplier portfolios - and the Supplier no longer has the capability to take the relevant action to Deactivate the Registrations. This may because the operational staff have left and the business is in administration.
A Supplier cannot have any remaining Meter Points in their portfolio for them to fully exit the market. There is a risk that Suppliers will remain indefinitely in the market without intervention from another party. Xoserve - acting as the CDSP - raised a derogation to support any parties who had not undertaken relevant entry activities to be registered as CSS Users as they were planning to exit the market.
the derogation has proven very effective, but the CDSP has needed to amend the Supply Meter Point Status to Live to force the RMP Status to Operational to allow the SoLR (or acquiring Supplier) to Register the Supply Point, then Deactivate it. We agree with the current rules that Terminated RMPs should not be subject to Registration due to the risk of Erroneous Transfers. We think that this should be an exception process, and that this should be something that the CSS should be administering. We do acknowledge that as the GRDA (and therefore the CDSP) we require a specific notification of the Deactivation of the site to remove this from Settlement systems. As such, we do consider that one option that could be considered is to continue the existing derogation until a solution is defined. One solution could be continued CDSP amendment of the MP status, but we think that logically the exception process should be managed by the party responsible for Registration - i.e. CSS.
We remind parties that CDSP would be unwilling to accept a 'change of Supplier' identity solution without a defined Registration or Deactivation event.

Impacts

Gas
Billing accuracy
-
Schedule 23 - Registration Services
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Central Switching Service (CSS)
-
Energy Suppliers, Shippers
This impacts GRDA systems.
Uniform Network Code (UNC), Independent Gas Transporters (IGT) Uniform Network Code (UNC)
At this time this change proposal does NOT impact any elements of the UNC / IGT UNC, but certain solution options could impact these Codes.
No
No details provided

Priority & timing

No
-
No
No
No details provided
-

Activity

Status has been changed to Issue Review.
james.hardy has been allocated as Lead Analyst.