MM00093

Confirmation of Energisation/De-Energisation of Prepayment Meter

Local Catalogue Reference
D0179
Message Version
1
Description
Confirmation is being given that the energisation status of a prepayment meter has been changed and readings and settings are being provided.
Notes
Though Tariff Code is defined within the structure as being optional it should be included in the Flow when the change of energisation status relates to either a Token Meter or Smart Card Meter.
Scenario Variants
Variant ID Name Source Target Owner Actions
Variant ID SV00556 Name Confirmation of Energisation/De-Energisation of Prepayment Meter Source Electricity Smart Meter Equipment Manager Target Electricity Supplier Owner Retail Energy Code Company Change selection
Structure
SV00556
Flow structure for SV00556
ID Name Range Level Required
368 MPAN Cores Range: 1-* L1 Mandatory
MPAN Core Mandatory
Site Visit Check Code Optional
Additional Information Optional
Failure Reason Code Optional
Tariff Code
Conditions: Tariff Code

Tariff Code is Mandatory within a message generated for a Token Meter or a Smart Card Meter, or Optional for any other meter type.

369 Meters Details per MPAN Core Range: 1-* L2 Mandatory
Meter ID Mandatory
Energisation Status Mandatory
Prepayment Meter Shutdown Status Mandatory
Reason for Request Mandatory
Date of Action Mandatory
Credit Balance Mandatory
Total Credit Accepted Optional
Total Tokens Inserted Optional
Emergency Credit Status Optional
Total Debt Outstanding Optional
Debt Recovery Rate Optional
Standing Charge Mandatory
370 Register Detail per Meter Range: 1-* L3 Mandatory
Meter Register Id Mandatory
Register Reading Mandatory
Prepayment Unit Rate Mandatory