CSS Switch Synchronisation to ERDA at SecuredActive
Summary
_
Latest update and next planned activity
Date of latest update
Latest Update
_
Impacts Overview
Priority and rationale
Standard
Priority last updated on 29 May 2026
Solution development
Problem Statement
Due to the high volume and timing of Registration messages being sent by the CSS, some messages are at risk of being received by REC Parties and Service Providers out of sequence. When messages have been received out of sequence, there is a risk that the information maintained in MPRS, including Registration Status, will be incorrect and will not match that held in the Registration Service. This in turn means MPRS updates to Parties could be triggered in error.
Proposed solution summary
- As a Consumer I want the Switch process to work effectively so that I can switch Electricity Supplier without delay or issues As a Consumer I want the Switch process to work effectively so that if my Switch needs to be cancelled it is done so without delay or issues
- As an Energy Supplier I want the Switch systems and process to operate effectively so that appointment Market Messages will be sent to my agents at the appropriate time so that there is no disruption to the Consumer switching experience
- As the ERDS Provider I only want to receive the first Pending message and then the Secured Active confirmation message, in order that there is no risk of processing CSS messages out of sequence which could impact a timely Switch for electricity Consumers As the CSS Provider I want the messages I send to MPRS to be processed effectively so that there is no disruption to the Switch process and Consumers’ Switches can be confirmed or cancelled as required
No documents available.
Change Plan
Solution analysis and development
Completed
Start:
17 Oct 2022Due:
31 Oct 2022Completion:
31 Oct 2022Change Proposal Plan presented to Change Panel for re-baselining
Completed
Start:
31 Oct 2022Due:
01 Nov 2022Completion:
26 Oct 2022Service Provider Impact Assessment period started
Completed
Start:
04 Apr 2022Due:
17 Oct 2022Completion:
17 Oct 2022Service Provider Impact Assessment period ended
Completed
Start:
16 Nov 2022Due:
18 Jan 2023Completion:
08 Nov 2022Change Proposal Withdrawn
Completed
Start:
01 Nov 2022Due:
16 Nov 2022Completion:
16 Nov 2022Original submission
Change details
- - -
4 Apr 2022
Change details
CSS Switch Synchronisation to ERDA at SecuredActive
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
No
-
-
-
No details provided
-