Combined progression of Change Proposals R0058, R0104 and R0129

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This change seeks to efficiently address the issues raised under the following Change Proposals. R0058 – REC Services Procurement Clarification R0104 – Clarifying Requirement for Continuous Billing Following an Erroneous Switch R0129 – Clarifying Event of Default Requirements These Change Proposals have been identified by the Code Manager as requiring non-contentious, clarificatory and non-material alterations to the REC Legal Text only.

Latest update and next planned activity

Date of latest update
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release

Impacts Overview

Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
Three Change Proposals have been placed on hold due to having a low priority status. These proposals have been identified as having fully formed solutions, which are non-contentious and can be quickly implemented. This change seeks to address these Change Proposals so that they can be addressed, and their benefits realised.
Proposed solution summary
  1. As a Market Participant, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.

No documents available.

Change Plan

Preliminary Change Report published

Completed

Start:

04 Aug 2023

Due:

01 Sep 2023

Completion:

01 Sep 2023

Consultation close

Completed

Start:

01 Sep 2023

Due:

15 Sep 2023

Completion:

15 Sep 2023

Final Change Report published

Completed

Start:

15 Sep 2023

Due:

22 Sep 2023

Completion:

22 Sep 2023

Responsible Committee decision

Not Started

Start:

22 Sep 2023

Due:

03 Oct 2023

Completion:

Original submission

Change details

- - -
4 Aug 2023

Change details

Combined progression of Change Proposals R0058, R0104 and R0129
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Implementation Date has been updated to 03 Nov 2023.