Amendment to Multiplication Factor Enumerations to Support Hydrogen Trials
Summary
The H100 hydrogen gas trial involves the supply of hydrogen gas to households in place of natural gas. The quantity of gas supplies needs to be billed in a way that is comparable to standard gas supply. To facilitate the trial, a multiplication factor enumeration value must be established within the Data Specification that can replicate hydrogen’s calorific value, therefore allowing accurate billing.
Latest update and next planned activity
Date of latest update
Latest Update
28/06/2024 - Change implemented as part of the June 2024 REC Release
Impacts Overview
Priority and rationale
Standard
Priority last updated on 29 May 2026
Solution development
Problem Statement
In order for the H100 gas trial to be successful, a billable value for hydrogen gas needs to be accurately calculated from supplied physical volumes. To do this, relevant Data Items (relating to the calculation of billable gas volumes) within the Data Specification need to be updated to allow a new value for the multiplication factor. This change seeks to introduce a new enumeration value for the multiplication factor needed to facilitate the addition of this new value.
Proposed solution summary
- As a Consumer taking part in the H100 trial, I want to be charged based on the amount of gas I consume, such that I am not charged more than I would have been, had I consumed the equivalent energy from natural gas.
- As a Gas Supplier, I want to ensure H100 trial Consumers, are not charged more than they would have been, had they consumed the equivalent energy from natural gas. 2- As a Gas Transporter, I want to accurately know how much hydrogen gas is being offtaken, so that I can support Suppliers. 3- As the Central Data Service Provider (CDSP), I want Market Messages relating to meter asset information to be accurate, so that I am better able to support dependant REC Parties. 4- As a Meter Equipment Manager (MEM), I want my metering assets compatible with the H100 trial to be underpinned by accurate Market Messages, so that I able to manage these meters correctly.
No documents available.
Change Plan
SERVICE PROVIDER IMPACT ASSESSMENT ISSUED
Completed
Start:
11 Aug 2023Due:
27 Nov 2023Completion:
27 Nov 2023PARTY IMPACT ASSESSMENT ISSUED
Completed
Start:
27 Nov 2023Due:
01 Dec 2023Completion:
01 Dec 2023PRELIMINARY CHANGE REPORT PUBLISHED
Completed
Start:
01 Dec 2023Due:
19 Jan 2024Completion:
19 Jan 2024CONSULTATION ISSUED
Completed
Start:
19 Jan 2024Due:
19 Jan 2024Completion:
19 Jan 2024FINAL CHANGE REPORT PUBLISHED
Completed
Start:
19 Jan 2024Due:
20 Feb 2024Completion:
16 Feb 2024RESPONSIBLE COMMITTEE DECISION
Completed
Start:
20 Feb 2024Due:
28 Feb 2024Completion:
28 Feb 2024Original submission
Change details
- - -
11 Aug 2023
Change details
Amendment to Multiplication Factor Enumerations to Support Hydrogen Trials
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
No
-
-
-
No details provided
-