Data Specification Update for Refresh Functionality

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This change has been raised to update the Data Specification and to align it with the changes made during implementation of change proposal ‘R0067 – Introduction of CSS Refresh Functionality’.

Latest update and next planned activity

Date of latest update
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.

Impacts Overview

Impacted Consumers
Electricity Gas
Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
Following implementation of R0067, a small number of Market Messages and Data Items need to be appropriately reflected within the Data Specification.
Proposed solution summary
  1. As a Market Participant, I need to understand any changes to Market Messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.

No documents available.

Change Plan

Preliminary Change Report Published

Completed

Start:

21 Aug 2023

Due:

16 May 2024

Completion:

16 May 2024

Consultation Issued

Completed

Start:

16 May 2024

Due:

16 May 2024

Completion:

16 May 2024

Final Change Report Issued

Data Specification Update for Refresh Functionality > Change Plan

Start:

16 May 2024

Due:

19 Jun 2024

Completion:

Responsible Committee Decision

Data Specification Update for Refresh Functionality > Change Plan

Start:

19 Jun 2024

Due:

26 Jun 2024

Completion:

Original submission

Change details

Michael Taylor - Code Manager
21 Aug 2023

Change details

Data Specification Update for Refresh Functionality
The Data Specification will require updating to bring it in line with the technical changes that will be implemented as part of Change Proposal R0067.
No impact, administration change only. Technical artifacts will be made available within the Physical Interface Document on R0067 implementation (6 December 2023). Change Proposal R0067 impacted parties (GRDA/CSS Provider) are currently working from detailed design documents, as such updating the Data Specification is to ensure completeness and has no impact.
Update the Data Specification at the earliest opportunity.
N/A

Impacts

Electricity, Gas
Other (please provide details in Additional information box below)
No impact, Data Specification requires updating for completeness.
No details provided
-
No details provided
-
No details provided
-
Data Item Catalogue, Market Message Catalogue
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No
No details provided

Priority & timing

No
-
Has to align with a Data Specification release.
No.
No details provided
-

Activity

Implementation Date has been updated to 23 Aug 2024.