On-site Aggregation as a method to facilitate Third Party Access - BSC P455
Summary
Following a modification proposal to the Balancing and Settlement Code (BSC) to allow on-site aggregation as a method for third party access on private networks, the Code Manager is required to amend the REC to place a requirement on the Meter Equipment Managers (MEMs) appointed by the boundary points Electricity Supplier, to rectify any faults found with the submeters used in the on-site aggregation methodology.
Latest update and next planned activity
Date of latest update
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Impacts Overview
Priority and rationale
Standard
Priority last updated on 29 May 2026
Solution development
Problem Statement
Under the proposed solution for BSC Modification P455, Consumers will require a Market Participant to oversee the maintenance of their sub-meter, including installations and rectification of metering faults. To ensure this, the REC will need to place a requirement on the MEMs appointed by the boundary point Electricity Supplier to rectify any faults found with the sub-meters used in the On-Site Aggregation.
Proposed solution summary
- The BSC Modification P455 Modification proposes to place a requirement on the SVA MOA (MEMs) appointed by the Boundary Point Supplier to rectify any faults found with the sub meters used in the On-Site Aggregation methodology; and to produce and submit the On-Site Aggregation Form to the HHDC. As MEMs (SVA MOAs) are governed under the Retail Energy Code (REC), R0150 is the REC's subsequent change to propose this.
No documents available.
Change Plan
Preliminary Change Report and Consultation Issued
Completed
Start:
15 Jan 2024Due:
22 Mar 2024Completion:
22 Mar 2024Party Impact Assessment
Completed
Start:
30 Oct 2023Due:
15 Jan 2024Completion:
15 Jan 2024Final Change Report Issued
Completed
Start:
22 Mar 2024Due:
26 Apr 2024Completion:
25 Apr 2024Responsible Committee Decision
Completed
Start:
26 Apr 2024Due:
08 May 2024Completion:
08 May 2024Original submission
Change details
- - -
30 Oct 2023
Change details
On-site Aggregation as a method to facilitate Third Party Access - BSC P455
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
No
-
-
-
No details provided
-