Prepayment Unallocatable Transactions

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
_

Latest update and next planned activity

Date of latest update
Latest Update
_

Impacts Overview

Impacted Consumers
Electricity Gas Domestic
Impacted REC Parties and Market Participants
Energy Supplier
Impacted REC Documents
Schedule 11 - Prepayment Arrangements
Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
The process for the allocation and payment of Unallocatable Transactions, set out in the Prepayment Arrangements Schedule, does not currently take into account Energy Suppliers that have exited the market or that do not have a contract with the PPMIP. This prevents the PPMIP from being able to release payments to Energy Suppliers, as the process doesn’t allow for all funds to be accounted for in the calculation.
Proposed solution summary
  1. As a PPMIP, I want to receive accurate market share data to allow me to complete the Unallocatable Prepayment Allocation Run in a timely manner.
  2. As an Energy Supplier, I want the calculation of Unallocatable Transactions to be carried out accurately and efficiently so that I receive payments allocated to my organisation.

No documents available.

Change Plan

Preliminary Change Report Issued

Completed

Start:

15 Dec 2021

Due:

04 Mar 2022

Completion:

04 Mar 2022

Responsible Committee Decision

Completed

Start:

08 Apr 2022

Due:

19 Apr 2022

Completion:

19 Apr 2022

Consultation Period Start

Completed

Start:

19 Apr 2022

Due:

22 Apr 2022

Completion:

22 Apr 2022

Consultation Period End

Completed

Start:

22 Apr 2022

Due:

16 May 2022

Completion:

16 May 2022

Final Change Report Issued

Completed

Start:

16 May 2022

Due:

27 May 2022

Completion:

27 May 2022

Responsible Committee Decision

Completed

Start:

27 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Appeal Window Closure

Completed

Start:

07 Jun 2022

Due:

22 Jun 2022

Completion:

22 Jun 2022

Legal Review / Preliminary Change Report Revision

Completed

Start:

04 Mar 2022

Due:

15 Mar 2022

Completion:

15 Mar 2022

Revised Preliminary Change Report Issued

Completed

Start:

15 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Original submission

Change details

Jonathan Holland - -
15 Dec 2021

Change details

Prepayment Unallocated Transactions
Each July the Code Manager, the Central Data Service Provider (CDSP) and the Prepayment Meter Infrastructure Provider (PPMIP) reconcile any unallocated Prepayment payments from the Backstop date, in accordance with Schedule 11 – Prepayment Arrangements.

If an Energy Supplier does not have a valid contact with the PPMIP or is no longer an active Energy Supplier, then they should be excluded from the allocation of payments.

When an Energy Supplier exits the market, these need to be removed from calculations and validation steps to ensure the correct payment values are calculated based on market share.
The calculation and validation steps, currently documented in Schedule 11 – Prepayment Arrangements, do not take into account any suppliers that exit the Energy market after July each year.
Not having this ability to remove these newly exited Energy Suppliers may result in inaccurate payment amounts being paid and further re-work needed by the PPMIP.
Additional validation steps added to the defined unallocated payment calculation methodology, to remove Energy Suppliers that exit the market from the calculation. This will ensure accuracy of the final payment amounts to the remaking active Energy Suppliers.
-

Impacts

Electricity, Gas, Domestic Prepayment
Other (please provide details in Additional information box below)
Although this issue predominately impacts gas, electricity process will be within scope of this Change Proposal.

There is no direct consumer impact.
Schedule 11 - Prepayment Arrangements
Schedule 11 – Prepayment Arrangements
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Energy Suppliers
-
No details provided
-
No
No details provided

Priority & timing

No
-
The next Unallocated Prepayment reconciliation process is due to take place in July 2022. Therefore, this Change Proposal would need to be implemented prior to then.
-
No details provided
-

Activity

Proposed solution summary changed to As a PPMIP, I want to receive accurate market share data to allow me to complete the Unallocatable Prepayment Allocation Run in a timely manner.As an Energy Supplier, I want the calculation of Unallocatable Trans…
Show more
Implementation Date has been updated to 30 Jun 2022.
jonathan.holland has been allocated as Lead Analyst.
rosalind.timperley has been allocated as SME.