Improvements to the Theft Detection Incentive Scheme (TDIS)

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This Change proposes that not only Confirmed Energy Thefts are incentivised within the Theft Detection Incentive Scheme (TDIS) but also Energy Theft Desktop and Site Visit Investigations.

Latest update and next planned activity

Date of latest update
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.

Impacts Overview

Priority and rationale

Priority last updated on 29 May 2026

Solution development

Problem Statement
Suppliers are not currently meeting their TDIS Theft targets within each TDIS Reporting Year because there may be financial disincentives to undertake investigations where there is no assurance that such investigations would convert into a Confirmed Energy Theft.

No documents available.

Change Plan

Party Impact Assessment Closure

Completed

Start:

20 May 2024

Due:

04 Oct 2024

Completion:

04 Oct 2024

Consultation

In Progress

Start:

04 Oct 2024

Due:

18 Oct 2024

Completion:

18 Oct 2024

Consultation Closure

Not Started

Start:

18 Oct 2024

Due:

08 Nov 2024

Completion:

Responsible Committee Decision

Not Started

Start:

08 Nov 2024

Due:

03 Dec 2024

Completion:

Send to Authority

Not Started

Start:

03 Dec 2024

Due:

04 Dec 2024

Completion:

Original submission

Change details

- - -
20 May 2024

Change details

Improvements to the Theft Detection Incentive Scheme (TDIS)
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

florentina.monea has been allocated as Lead Analyst.
rosalind.timperley, awaghorn have been allocated as SME.