New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)
Summary
This change seeks to deliver a recommendation from the Market-Wide Half Hourly Settlement Programme’s (MHHSP’s) Code Change and Development Group (CCDG), to introduce Registration Service Data Items that will be needed for MHHS, into the existing Supplier Meter Registration Service (SMRS) systems, before MHHS migration commences in October 2024.
Latest update and next planned activity
Date of latest update
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Impacts Overview
Priority and rationale
High
Priority last updated on 29 May 2026
Solution development
Problem Statement
There are Registration Service Data Items that are critical to the MHHS rules and processes. The MHHS Programme is concerned that starting migration in October 2024 with poor underlying data quality would lead to avoidable time and effort being spent fixing issues during the 12-month migration period. To facilitate MHHS Programme data cleanse activity, prior to the transition to Half Hourly Settlement, Registration Service Data Items need to be introduced into the existing Supplier Meter Registration Service (SMRS) system and displayed in EES.
Proposed solution summary
- As an impacted Market Participant, I want to ensure good quality underlying data is available to support the transition to HH Settlements to avoid additional time and effort being spent fixing data quality issues during the migration period.
- As the MHHS Programme, I want Registration Data Items to be available ahead of the MHHS migration to enable data cleanse activity to be completed to address data quality issues.
No documents available.
Change Plan
Solution Analysis and Development
Completed
Start:
03 Feb 2022Due:
09 May 2022Completion:
09 May 2022Service Provider Impact Assessment Issued
Completed
Start:
09 May 2022Due:
13 May 2022Completion:
13 May 2022Party Impact Assessment Issued
Completed
Start:
13 May 2022Due:
13 May 2022Completion:
13 May 2022Preliminary Change Report Issued
Completed
Start:
29 Jun 2022Due:
29 Jul 2022Completion:
29 Jul 2022Consultation Issued
Completed
Start:
29 Jul 2022Due:
05 Aug 2022Completion:
05 Aug 2022Final Change Report Issued
Completed
Start:
05 Aug 2022Due:
08 Nov 2022Completion:
08 Nov 2022Additional Impact Assessment Issued
Completed
Start:
13 May 2022Due:
29 Jun 2022Completion:
29 Jun 2022Responsible Committee Decision (Deferred from 20/09/22)
Completed
Start:
08 Nov 2022Due:
15 Nov 2022Completion:
15 Nov 2022Original submission
Change details
- - -
3 Feb 2022
Change details
New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
No
-
-
-
No details provided
-