Changes to Supply Number Format for MHHS

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
The Electricity Supply License requires Suppliers to provide the Supply Number to each Consumer on every bill, or at least once per year where no bill has been sent. The Supply Number format is prescribed by the REC and is detailed in the Energy Market Data Specification. The MHHS design is changing the data associated with each individual metering point, including those data items currently displayed within the Supply Number top line. To support Electricity Supplier implementation of the MHHS arrangements, a clearly defined solution is required setting out a revised approach to populating the Supply Number on Consumer’s bills and statements.

Latest update and next planned activity

Date of latest update
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.

Impacts Overview

Priority and rationale
High

Priority last updated on 29 May 2026

Solution development

Problem Statement
The Market-wide Half Hourly Settlement design is impacting the Data Items that are used in the top line of the Supply Number, which Energy Suppliers are obliged to provide to Consumers at least once a year under their Licence. A revised definition of the Supply Number format is required so that Electricity Suppliers have a clear understanding of the approach to populating the Supply Number for metering points that have migrated to the new MHHS arrangements.
Proposed solution summary
  1. As an electricity Consumer I want to be able to provide my prospective Energy Supplier with the necessary information for them to provide a suitable tariff. As a Non-Domestic Consumer, I want to have the necessary information that will allow me to access tariff information, specific to my business, to help me manage my energy. As an electricity Consumer, I want to have access to the data that will help me appoint my own Metering Equipment Manager (MEM) where permitted.
  2. As a Supplier, I want to know how to populate and format the Supply Number, so that I can meet my obligations to include it in Consumer bills or statements. As a Third Party Intermediary (TPI), I want Consumers to be able to provide me with the right information to provide appropriate quotes.
  3. As an independent Distribution Network Operator, I want to be able to identify and use the DUoS Tariff Id so that I can provide transparency on charging that is being applied to my customers. As the Electricity Enquiry Service (EES) Provider, I want to know how to populate the Supply Number so that I can make it available on the EES

No documents available.

Change Plan

Solution development completed

Completed

Start:

05 Dec 2022

Due:

31 Mar 2023

Completion:

31 Mar 2023

Party Impact Assessment issued

Completed

Start:

31 Mar 2023

Due:

06 Apr 2023

Completion:

06 Apr 2023

Party Impact Assessment closed

Completed

Start:

06 Apr 2023

Due:

02 May 2023

Completion:

02 May 2023

Preliminary Change Report issued

Completed

Start:

02 May 2023

Due:

25 May 2023

Completion:

26 May 2023

REC Change Panel review of PCR

Completed

Start:

25 May 2023

Due:

06 Jun 2023

Completion:

06 Jun 2023

Consultation issued

Completed

Start:

06 Jun 2023

Due:

09 Jun 2023

Completion:

09 Jun 2023

Consultation closed

Completed

Start:

09 Jun 2023

Due:

30 Jun 2023

Completion:

30 Jun 2023

Final Change Report issued

Completed

Start:

30 Jun 2023

Due:

21 Jul 2023

Completion:

20 Jul 2023

REC Change Panel decision

Completed

Start:

21 Jul 2023

Due:

01 Aug 2023

Completion:

01 Aug 2023

Authority Determination requested

Completed

Start:

01 Aug 2023

Due:

03 Aug 2023

Completion:

02 Aug 2023

Original submission

Change details

- - -
5 Dec 2022

Change details

Changes to Supply Number Format for MHHS
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Proposed solution summary changed to As an electricity Consumer I want to be able to provide my prospective Energy Supplier with the necessary information for them to provide a suitable tariff. As a Non-Domestic Consumer, I want to have the necessar…
Show more
Implementation Date has been updated to MHHS Programme Milestone M8 (Code changes delivered).
harriet.truss has been allocated as Lead Analyst.