Amendments to Sample Access Agreement
Summary
A number of Non-Party REC Service Users have entered into an Access Agreement with RECCo under the Code’s Qualification and Maintenance Schedule, to obtain access to the CSS and become a CSS User. These Access Agreements are based on the Sample Access Agreement appended to Schedule 9 to the Code, which DCC believes should have been revised to address issues they have identified.
Latest update and next planned activity
Date of latest update
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Impacts Overview
Priority and rationale
Standard
Priority last updated on 29 May 2026
Solution development
Problem Statement
The CRS Provider has raised that the Sample Access Agreement appended to Schedule 9 – Qualification and Maintenance does not provide adequate protections to Non-Party REC Service Users or the CRS Provider regarding liabilities or data security.
Proposed solution summary
- As a Consumer, I want systems containing my information to be correctly assured, so that my personal information is kept safe and services I expect to be able to use are not disrupted.
- As a Non-Party REC Service User, I want the Access Agreement I sign before I can access services from the CRS Provider to give me the same protections as other service users, so I am protected from loss and liability caused by another service user, or the service itself.
- As the CRS Provider, I want Non-Party REC Service Users to be held to the same provisions as other CSS Users, so I am protected from loss and liability caused by them.
- As a CSS User, I want Non-Party REC Service Users to be held to the same
No documents available.
Change Plan
PARTY IMPACT ASSESSMENT
Completed
Start:
02 Sep 2022Due:
24 May 2024Completion:
24 May 2024PRELIMINARY CHANGE REPORT ISSUED
Completed
Start:
24 May 2024Due:
18 Jul 2024Completion:
18 Jul 2024RESPONSIBLE COMMITTEE REVIEW
Completed
Start:
18 Jul 2024Due:
30 Jul 2024Completion:
30 Jul 2024CONSULTATION ISSUED
Completed
Start:
30 Jul 2024Due:
02 Aug 2024Completion:
01 Aug 2024FINAL CHANGE REPORT ISSUED
Completed
Start:
02 Aug 2024Due:
12 Sep 2024Completion:
12 Sep 2024RESPONSIBLE COMMITTEE DECISION
Completed
Start:
12 Sep 2024Due:
24 Sep 2024Completion:
24 Sep 2024Original submission
Change details
- - -
2 Sep 2022
Change details
Amendments to Sample Access Agreement
-
-
-
-
Impacts
No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided
Priority & timing
No
-
-
-
No details provided
-