Missing Meter Technical Details

  • 1
    Withdrawn
Step 1 of 1
Withdrawn
Summary
When a Switch occurs, with a concurrent change of Metering Equipment Manager (MEM), and the Meter Technical Details (MTD) are not received by the Gaining Supplier’s MEM, they are unable to provide them to the Gaining Supplier. Lack of MTDS can impact Consumers, Suppliers, and other industry Parties. The Change Proposer has highlighted that there is currently no defined escalation process available to Suppliers, enabling them to chase for missing MTDs following a Switch.

Latest update and next planned activity

Date of latest update
Latest Update
08/07/2024 - R0006 has been withdrawn as the issue has been addressed under R0121 - SDEP Review Improvements - Process Types.

Impacts Overview

Impacted Consumers
Electricity Domestic Non-Domestic
Impacted REC Parties and Market Participants
Energy Supplier Data Collector
Impacted REC Documents
Schedule 14 - Metering Operations Schedule 17 - Secure Data Exchange
Impacted REC Services
Secure Data Exchange Service (SDES)
Priority and rationale
Standard

Priority last updated on 29 May 2026

Solution development

Problem Statement
On a CoS the new MEM and Supplier need to receive the MTDs from the previous MEM to complete the setup of the customer’s account and billing records. Where MTD are not sent there is no dispute or escalation process to resolve this. This prevents the new Supplier from setting up the customer’s account and issuing a timely and accurate bill.
Proposed solution summary
  1. As a Consumer: I want my new Supplier to set up my account in a timely manner, ensuring that I receive timely and accurate bills. I want to my meter to be read regularly to ensure I receive accurate bills I want to receive my final invoice from my old Supplier in a timely manner
  2. As a Losing Supplier I want to agree a closing meter reading to allow me to produce a final invoice and collect any outstanding payments
  3. As a Gaining Supplier I want to set up the energy account correctly for the consumer, receive an opening reading and produce a timely first invoice As a Gaining Supplier’s MEM I want to receive the MTD to enable me to update my data and trigger the necessary Market Messages to the new Supplier, new DC and DNO As a new Data Collector I want to receive the MTD to enable me to set up the correct meter reading schedule and collect meter readings.

No documents available.

Change Plan

Initial Assessment Report published

Completed

Start:

08 Sep 2021

Due:

12 Oct 2021

Completion:

12 Oct 2021

Change Panel review

Completed

Start:

12 Oct 2021

Due:

19 Oct 2021

Completion:

19 Oct 2021

Updated Change Proposal Plan presented to Change Panel

Completed

Start:

19 Oct 2021

Due:

04 Oct 2022

Completion:

04 Oct 2022

Solution Development

Completed

Start:

04 Oct 2022

Due:

05 Oct 2022

Completion:

08 Jan 2023

Updated plan Presented to Change Panel

Completed

Start:

05 Oct 2022

Due:

06 Dec 2022

Completion:

06 Dec 2022

Service Provider Impact Assessment

Missing Meter Technical Details > Change Plan

Start:

06 Dec 2022

Due:

09 Jan 2023

Completion:

Party Impact Assessment

Completed

Start:

09 Jan 2023

Due:

03 Feb 2023

Completion:

24 Feb 2023

Preliminary Change Report Issued

Missing Meter Technical Details > Change Plan

Start:

03 Feb 2023

Due:

28 Apr 2023

Completion:

Responsible Committee Review

Missing Meter Technical Details > Change Plan

Start:

28 Apr 2023

Due:

10 May 2023

Completion:

Consultation Issued

Missing Meter Technical Details > Change Plan

Start:

10 May 2023

Due:

12 May 2023

Completion:

Final Change Report Issued

Missing Meter Technical Details > Change Plan

Start:

12 May 2023

Due:

30 Jun 2023

Completion:

Responsible Committee Decision

Missing Meter Technical Details > Change Plan

Start:

30 Jun 2023

Due:

12 Jul 2023

Completion:

Original submission

Change details

Diane Lyon - ScottishPower
8 Sep 2021

Change details

New SDEP Process Type
We receive a number of queries from gaining suppliers chasing our MTDs. There is no industry process for this – as it stands it stops with the MOPs requesting the MTDs from the old MOP. We believe there is a gap that needs to be resolved.
There’s a clear customer impact as the gaining DC can’t issue the D0086 so neither supplier can resolve their billing.
Proposed solutions would be Our high level suggestions are: • Update metering schedule to include escalations, potentially using SDEP • Create a new supplier schedule for supplier hub issues, including MTDs and MRH, using SDEP to send the queries.
-

Impacts

Electricity, Domestic Prepayment, Domestic Credit, Microbusiness
Billing accuracy, Trust and confidence
-
Schedule 14 - Metering Operations, Schedule 17 - Secure Data Exchange
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Secure Data Exchange Service
-
Energy Suppliers, Data Collectors
-
No details provided
-
No
No details provided

Priority & timing

No
-
-
No.
No details provided
-

Activity

Proposed solution summary changed to As a Consumer: I want my new Supplier to set up my account in a timely manner, ensuring that I receive timely and accurate bills. I want to my meter to be read regularly to ensure I receive accurate bills I want…
Show more
beth.brown has been allocated as SME.