Performance Assurance Report Catalogue Updates (MHHS)

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This change seeks to update the Performance Assurance Reporting Catalogue (PARC) to capture data items required to continue to appropriately monitor Retail Risks under Market-wide Half Hourly Settlement (MHHS) industry arrangements. Some housekeeping changes, for the PARC, have also been included in this change.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.

Impacts Overview

Priority and rationale

Priority last updated on 29 May 2026

Solution development

Problem Statement
The PARC currently does not capture all the data items required to support the monitoring of Retail Risks following Market-wide Half Hourly Settlement go-live. An update to the PARC is required to include the data items that will ensure the Code Manager can provide the assurance the industry requires during transition and under the new MHHS arrangements.

No documents available.

Change Plan

Proposal Plan approved

Completed

Start:

08 Aug 2024

Due:

03 Sep 2024

Completion:

03 Sep 2024

Party impact assessment completed

Completed

Start:

03 Sep 2024

Due:

04 Oct 2024

Completion:

04 Oct 2024

Change Report approved for Consultation

Completed

Start:

04 Oct 2024

Due:

25 Mar 2025

Completion:

25 Mar 2025

Consultation completed

Completed

Start:

25 Mar 2025

Due:

15 Apr 2025

Completion:

15 Apr 2025

RECPAB Voting

In Progress

Start:

15 Apr 2025

Due:

29 Apr 2025

Completion:

Original submission

Change details

- - -
8 Aug 2024

Change details

Performance Assurance Report Catalogue Updates (MHHS)
-
-
-
-

Impacts

No details provided
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Implementation Date has been updated to 27 Jun 2025.
harriet.truss has been allocated as Lead Analyst.
beth.brown, awaghorn have been allocated as SME.