Market-wide Half-Hourly Settlement Implementation

Date of latest update
Type
Change
ID
R0003
Change Category
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Abid Sheikh
Change Plan

Initial Assessment Report published

Completed

Start:

01 Sep 2021

Due:

03 Sep 2021

Completion:

03 Sep 2021

Change Panel review

Completed

Start:

03 Sep 2021

Due:

07 Sep 2021

Completion:

07 Sep 2021

Preliminary Change Report published

Completed

Start:

07 Sep 2021

Due:

09 Sep 2021

Completion:

09 Sep 2021

Consultation start

Completed

Start:

09 Sep 2021

Due:

14 Sep 2021

Completion:

14 Sep 2021

Consultation end

Completed

Start:

14 Sep 2021

Due:

20 Sep 2021

Completion:

20 Sep 2021

Final Change Report published

Completed

Start:

20 Sep 2021

Due:

24 Sep 2021

Completion:

24 Sep 2021

Change Panel decision

Completed

Start:

24 Sep 2021

Due:

05 Oct 2021

Completion:

05 Oct 2021
Status
Implementation Date
Status Live
EMAR Version 04.11.2021_live
Included changes Affected REC Items
R0001 Amendment to DCC Service Flag (DI51130) Data Item

Documents

Name Version Last updated Actions
241.04 KB
Version 1.3 - 29 May 2026 XLSX - 241.04 KB
1.3 29 May 2026
455.42 KB
Version 1.3 - 29 May 2026 XLSX - 455.42 KB
1.3 29 May 2026
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As the Senior Responsible Owner for the Market-wide Half-Hourly Settlement programme, I need assurance that all programme participants will deliver the required changes in accordance with programme plan, so Market-wide Half-Hourly settlement can be introduced and implemented successfully.
Proposed Solution Document
Document title
R0003 - Red-lined amendments to Main Body
Archive
Off
Document title
Link to EMAR - Change Set (Clean)
Archive
Off
Problem Statement
The successfully introduction of Market-wide Half-Hourly Settlement (MHHS) requires changes to made to the systems and processes governed by other codes outside of the BSC, including the REC. Elexon as the Senior Responsible Owner (SRO) and Ofgem as the Programme Sponsor for the MHHS programme need assurance that all programme participants will support the implementation of the programme and deliver against the approved timetable. While there is a general ‘duty to cooperate’ with Significant Code Reviews that exists for licenced parties, there is no explicit legal requirement for RECCo (as a non-BSC Party) to support this and no contractual recourse if its duties are not met.
Letter from the Authority to the REC Code Manager - Authority Led Modification Proposal
Initial Assessment Report v1.0 (Approved)
Change Proposal Plan v1.0 (Approved)
R0003 - Preliminary Change Report v1.0 (Approved)
R0003 - Final Change Report v1.0 (Pre-Vote)
R0003 - Final Change Report v2.0 (Post-Vote)
R0003 - Authority Decision
Company Name
-
Review status
Review required

Review of Data Specification Category in REC Baseline Statement

Date of latest update
Type
Change
ID
R0002
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Jonathan Hawkins
Change Plan

Initial Assessment Report published

Completed

Start:

01 Sep 2021

Due:

03 Sep 2021

Completion:

02 Sep 2021

Change Panel review

Completed

Start:

03 Sep 2021

Due:

07 Sep 2021

Completion:

07 Sep 2021

Preliminary Change Report published

Completed

Start:

07 Sep 2021

Due:

09 Sep 2021

Completion:

09 Sep 2021

Consultation start

Completed

Start:

09 Sep 2021

Due:

14 Sep 2021

Completion:

14 Sep 2021

Consultation end

Completed

Start:

14 Sep 2021

Due:

20 Sep 2021

Completion:

20 Sep 2021

Final Change Report published

Completed

Start:

20 Sep 2021

Due:

24 Sep 2021

Completion:

24 Sep 2021

Change Panel decision

Completed

Start:

24 Sep 2021

Due:

05 Oct 2021

Completion:

05 Oct 2021
Status
Implementation Date
Status Live
EMAR Version 04.11.2021_live
Included changes Affected REC Items
R0001 Amendment to DCC Service Flag (DI51130) Data Item

Documents

Name Version Last updated Actions
241.04 KB
Version 1.3 - 29 May 2026 XLSX - 241.04 KB
1.3 29 May 2026
455.42 KB
Version 1.3 - 29 May 2026 XLSX - 455.42 KB
1.3 29 May 2026
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a market participant, I need to understand any changes to market messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
  2. As the REC Code Manager, I need to ensure that proposals to amend the Data Specification are subject to appropriate scrutiny and impact assessment, so that impacted stakeholders can appropriately engage with the proposal and understand the impacts to their business.
Proposed Solution Document
Document title
Changes to REC Baseline Statement
Archive
Off
Problem Statement
The Data Specification was not included in the Switching Programme Change Requests that gave effect to REC V2.0. Therefore, the Data Specification was not formally designated as part of REC V2.0 and has temporarily been added to the REC Baseline Statement as a Category 3 product. This means that changes to the Data Specification, including changes to Market Messages and Data Items used by market participants to interface with other businesses and service providers, are not subject to the process set out in the REC Change Management Schedule. Changes to these artefacts can have significant impacts to the systems and processes of market participants and service providers. These changes should follow a robust and thorough assessment to ensure these impacts are identified and considered, and the most appropriate solution is considered. The Category 3 change process is not appropriate for this, as changes to Category 3 products should not cause a material impact to parties and stakeholders.
Initial Assessment Report V1.0 (Approved)
Change Proposal Plan V1.0 (Approved)
R0002 - Preliminary Change Report v1.0 (Approved)
R0002 - Final Change Report v1.0 (Pre-Vote)
R0002 - Final Change Report v2.0 (Post-Vote)
Company Name
-
Review status
Review required

Amendment to DCC Service Flag (DI51130) Data Item

Date of latest update
Type
Change
ID
R0001
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Jonathan Hawkins
Change Plan

Initial Assessment Report published

Completed

Start:

01 Sep 2021

Due:

03 Sep 2021

Completion:

02 Sep 2021

Change Panel review

Completed

Start:

03 Sep 2021

Due:

07 Sep 2021

Completion:

07 Sep 2021

Preliminary Change Report published

Completed

Start:

07 Sep 2021

Due:

09 Sep 2021

Completion:

09 Sep 2021

Consultation start

Completed

Start:

09 Sep 2021

Due:

14 Sep 2021

Completion:

14 Sep 2021

Consultation end

Completed

Start:

14 Sep 2021

Due:

20 Sep 2021

Completion:

20 Sep 2021

Final Change Report published

Completed

Start:

20 Sep 2021

Due:

24 Sep 2021

Completion:

24 Sep 2021

Change Panel decision

Completed

Start:

24 Sep 2021

Due:

05 Oct 2021

Completion:

05 Oct 2021
Status
Implementation Date
Status Live
EMAR Version 04.11.2021_live
Included changes Affected REC Items
R0001 Amendment to DCC Service Flag (DI51130) Data Item

Documents

Name Version Last updated Actions
241.04 KB
Version 1.3 - 29 May 2026 XLSX - 241.04 KB
1.3 29 May 2026
455.42 KB
Version 1.3 - 29 May 2026 XLSX - 455.42 KB
1.3 29 May 2026
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As an Energy Consumer, I want my Energy Supplier to know the status of my smart meter, so they can bill me accurately using remote smart data.
  2. As an Energy Supplier, I need to establish whether there is a smart meter I can communicate with in the DCC network, so I can complete the correct process for customers switching supplier.
  3. As a Distribution Network Operator, I need to establish whether there is a smart meter I can communicate with in the DCC network, so I know whether to respond to smart meter alerts.
Proposed Solution Document
Document title
Amendments to DCC Service Flag Data Item - Legal Text
Archive
Off
Document title
Link to EMAR - Change Set (Clean)
Archive
Off
Problem Statement
SEC Modification Proposal 077 proposes to update the values, and business rules, of the DCC Service Flag Data Item. This will allow users to use the Data Item as originally intended, to establish whether there is an active smart meter in the DCC network that they can communicate with at a premises. This modification has been approved for implementation on 4th November 2021 by the SEC, and a consequential change is required to the Data Specification to reflect this.
SEC MP077 - Modification Report v1.0.pdf
SEC MP077 Legal Text v1.0 (1).pdf
Initial Assessment Report V1.0 (Approved)
Change Proposal Plan V1.0 (Approved)
R0001 - Preliminary Change Report v1.0 (Approved)
R0001 - Final Change Report v1.0 (Pre-Vote)
R0001 - Final Change Report v2.0 (Post-Vote)
Company Name
-
Review status
Review required