Prepayment Credit Balance Transfer Process
Initial Analysis
Start:
10 Mar 2022Due:
30 Jun 2022Completion:
Present updated Change Proposal Plan to Change Panel
Start:
30 Jun 2022Due:
19 Jul 2022Completion:
Solution Development Complete
Start:
30 Jan 2023Due:
29 Feb 2024Completion:
29 Feb 2024Present Updated Change Proposal Plan to Change Panel
Start:
19 Jul 2022Due:
08 Nov 2022Completion:
Present Updated Plan to Change Panel
Start:
08 Nov 2022Due:
17 Jan 2023Completion:
17 Jan 2023Service Provider Impact Assessment
Start:
17 Jan 2023Due:
30 Jan 2023Completion:
30 Jan 2023Market Stabilisation Charge – Administration
Party Impact Assessment initiated
Start:
22 Feb 2022Due:
08 Apr 2022Completion:
08 Apr 2022Party Impact Assessment completed
Start:
08 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Preliminary Change Report issued
Start:
29 Apr 2022Due:
06 May 2022Completion:
06 May 2022Issued to Responsible Committee for review (ex-Committee)
Start:
06 May 2022Due:
10 May 2022Completion:
10 May 2022Consultation initiated
Start:
10 May 2022Due:
13 May 2022Completion:
13 May 2022Consultation completed
Start:
13 May 2022Due:
01 Jun 2022Completion:
01 Jun 2022Final Change Report issued
Start:
01 Jun 2022Due:
10 Jun 2022Completion:
10 Jun 2022Responsible Committee Decision (ex-Committee)
Start:
10 Jun 2022Due:
14 Jun 2022Completion:
14 Jun 2022Authority Determination
Start:
14 Jun 2022Due:
24 Jun 2022Completion:
27 Jun 202230 June 2022
- As a Domestic Consumer, I want to be able to choose my Energy Supplier and a tariff from a range of competitive options, so that I can take advantage of cheaper deals as they become available.
- As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
- As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
- As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send my invoices/credit notes, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I make to RECCo or at an appropriate time for my organisation. As a Domestic Supplier, I want to understand how I could dispute an invoice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly
Market Stabilisation Charge
Preliminary Change Report issued
Start:
21 Feb 2022Due:
04 Mar 2022Completion:
04 Mar 2022Consultation issued (5 WD)
Start:
04 Mar 2022Due:
04 Mar 2022Completion:
04 Mar 2022Final Change Report issued
Start:
04 Mar 2022Due:
18 Mar 2022Completion:
18 Mar 2022Responsible Committee decision (ex-Committee)
Start:
18 Mar 2022Due:
23 Mar 2022Completion:
23 Mar 2022Authority determination
Start:
23 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 202214 April 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)
Solution Analysis and Development
Start:
03 Feb 2022Due:
09 May 2022Completion:
09 May 2022Service Provider Impact Assessment Issued
Start:
09 May 2022Due:
13 May 2022Completion:
13 May 2022Party Impact Assessment Issued
Start:
13 May 2022Due:
13 May 2022Completion:
13 May 2022Preliminary Change Report Issued
Start:
29 Jun 2022Due:
29 Jul 2022Completion:
29 Jul 2022Consultation Issued
Start:
29 Jul 2022Due:
05 Aug 2022Completion:
05 Aug 2022Final Change Report Issued
Start:
05 Aug 2022Due:
08 Nov 2022Completion:
08 Nov 2022Additional Impact Assessment Issued
Start:
13 May 2022Due:
29 Jun 2022Completion:
29 Jun 2022Responsible Committee Decision (Deferred from 20/09/22)
Start:
08 Nov 2022Due:
15 Nov 2022Completion:
15 Nov 202230 June 2023
- As an impacted Market Participant, I want to ensure good quality underlying data is available to support the transition to HH Settlements to avoid additional time and effort being spent fixing data quality issues during the migration period.
- As the MHHS Programme, I want Registration Data Items to be available ahead of the MHHS migration to enable data cleanse activity to be completed to address data quality issues.
Service Provider Performance Charges (DCC)
Preliminary Change Report and Consultation Issued
Start:
04 Jan 2022Due:
15 Nov 2022Completion:
15 Nov 2022Final Change Report Issued
Start:
15 Nov 2022Due:
09 Dec 2022Completion:
09 Dec 2022Responsible Committee Decision
Start:
09 Dec 2022Due:
20 Dec 2022Completion:
20 Dec 2022Send to Authority for Decision
Start:
20 Dec 2022Due:
21 Dec 2022Completion:
21 Dec 202201 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As the REC Code Manager, I want to ensure that REC Service Providers achieve their Service Level Agreements (SLAs) defined in REC Service Definitions, so that impacts to the REC Code Manager, REC Parties and other Service Providers, as a consequence of Service Provider underperformance, are minimised and the change process delivers to time and cost.
- As a Service Provider, I want clarity on when and how Performance Charges will be used as part of the Performance Assurance Techniques, so that I’m clear on what service levels I need to meet and the consequences of not delivering against these.
ETTOS Report Dissemination
Initial Assessment Report published
Start:
29 Nov 2021Due:
03 Dec 2021Completion:
03 Dec 2021Change Panel review
Start:
03 Dec 2021Due:
07 Dec 2021Completion:
07 Dec 2021Preliminary Change Report issued
Start:
07 Dec 2021Due:
13 Dec 2021Completion:
13 Dec 2021Change Panel review
Start:
13 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 2021Consultation starts
Start:
21 Dec 2021Due:
22 Dec 2021Completion:
21 Dec 2021Consultation ends
Start:
22 Dec 2021Due:
12 Jan 2022Completion:
12 Jan 2022Final Change Report issued
Start:
12 Jan 2022Due:
14 Jan 2022Completion:
14 Jan 2022Change Panel decision
Start:
14 Jan 2022Due:
18 Jan 2022Completion:
18 Jan 202231 January 2022
- As a Consumer, I want my Energy Supplier to receive and act upon energy theft tip-offs, to ensure the safety and security of my energy supply.
- As an ETTOS Recipient, I need to be aware of changes to the way I will receive and send tip-off information, so I can engage in the process and plan any required changes to my processes.
- As an ETTOS Recipient, I need to receive my ETTOS Service Data in a timely manner, so that I am able to act on tip-offs, to reduce risks for consumers and my business.
Consequential REC changes for BSC CP1532
Initial Assessment Report and Change Proposal Plan approved
Start:
26 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Preliminary Change Report issued
Start:
21 Dec 2021Due:
28 Jan 2022Completion:
28 Jan 2022Preliminary Change Report approval
Start:
28 Jan 2022Due:
09 Feb 2022Completion:
09 Feb 2022Consultation starts
Start:
09 Feb 2022Due:
14 Feb 2022Completion:
11 Feb 2022Consultation ends
Start:
14 Feb 2022Due:
04 Mar 2022Completion:
04 Mar 2022Final Change Report Issued
Start:
04 Mar 2022Due:
11 Mar 2022Completion:
11 Mar 2022Responsible Committee decision (ex-Committee)
Start:
11 Mar 2022Due:
23 Mar 2022Completion:
22 Mar 202230 June 2022
- As an electricity Consumer I want my new Energy Supplier to set up my account and appoint their agents appropriately, so I receive timely and accurate bills.
- As a Market Participant, I need to understand any changes to Market Messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
- As an Energy Supplier, I want to be able to Appoint and De-appoint Agents more quickly, to minimise risks to my settlement performance and ability to produce accurate and timely consumer bills when the new switching arrangements go-live.
Remote communication obligations for electricity Advanced Meters
Initial Assessment Report published
Start:
17 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Analysis and Solution development activity
Start:
21 Dec 2021Due:
27 Feb 2022Completion:
25 Feb 2022Party Impact Assessment completion
Start:
27 Feb 2022Due:
21 Mar 2022Completion:
21 Mar 2022Preliminary Change Report issued
Start:
07 Apr 2022Due:
27 May 2022Completion:
27 May 2022Consultation starts
Start:
27 May 2022Due:
10 Jun 2022Completion:
10 Jun 2022Consultation ends
Start:
10 Jun 2022Due:
01 Jul 2022Completion:
01 Jul 2022Final Change Report issued
Start:
01 Jul 2022Due:
29 Jul 2022Completion:
28 Jul 2022Metering Expert Panel decision
Start:
29 Jul 2022Due:
10 Aug 2022Completion:
10 Aug 2022Service Provider Impact Assessment issued
Start:
21 Mar 2022Due:
07 Apr 2022Completion:
07 Apr 2022Send back solution refinement completed
Start:
10 Aug 2022Due:
13 Jan 2023Completion:
13 Jan 2023Consultation issued
Start:
13 Jan 2023Due:
20 Jan 2023Completion:
20 Jan 2023Update provided to Change Panel
Start:
20 Jan 2023Due:
07 Feb 2023Completion:
07 Feb 2023Final Change Report issued
Start:
07 Feb 2023Due:
14 Feb 2023Completion:
14 Feb 2023Responsible Committee decision
Start:
14 Feb 2023Due:
21 Feb 2023Completion:
21 Feb 2023Authority Determination requested
Start:
21 Feb 2023Due:
28 Feb 2023Completion:
24 Mar 202330 June 2023
- As an electricity consumer with an Advanced Meter, I want my usage data to be accessed remotely from my meter, to reduce the need for on-site visits and ensure that I receive timely and accurate bills.
- As the Market-wide Half Hourly Settlement (MHHS) Programme I want to see an effective, early migration of NHH settled Advanced Meters to HH settled, to reduce the risk of missed migration deadlines and ensuring sufficient time to resolve ‘problem’ sites ahead of the MHHS migration deadline.
- As an Energy Supplier I want to obtain usage remotely, reducing the need for on-site metering reading activity, enabling me to settle and bill accurately. As a Metering Equipment Manager (MEM), I need to understand any changes to obligations that may impact my business, so I can engage in the change process and plan any required changes to my systems, processes and organisation.
Housekeeping amendments to REC V2
Initial Assessment Report published
Start:
04 Oct 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
22 Oct 2021Completion:
22 Oct 2021Change Panel review
Start:
22 Oct 2021Due:
16 Nov 2021Completion:
16 Nov 2021Consultation starts
Start:
16 Nov 2021Due:
17 Nov 2021Completion:
17 Nov 2021Consultation ends
Start:
17 Nov 2021Due:
08 Dec 2021Completion:
08 Dec 2021Final Change Report issued
Start:
08 Dec 2021Due:
10 Dec 2021Completion:
10 Dec 2021Change Panel decision
Start:
10 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 202131 January 2022
- As an Energy Consumer, I need Energy Companies to operate consistent processes, to ensure my energy supply is managed efficiently and to retain my trust in the functioning of the energy market.
- As a REC Party, I need the REC to provide a consistent baseline, so I can operate in an interoperable way with other Market Participants.
Consequential New and Amended Market Messages for BSC Modification P375
Initial Assessment Report published
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
01 Nov 2021Completion:
29 Oct 2021Technical Expert Panel review
Start:
01 Nov 2021Due:
08 Nov 2021Completion:
08 Nov 2021Consultation starts
Start:
08 Nov 2021Due:
15 Nov 2021Completion:
12 Nov 2021Consultation ends
Start:
15 Nov 2021Due:
06 Dec 2021Completion:
06 Dec 2021Final Change Report issued
Start:
06 Dec 2021Due:
10 Dec 2021Completion:
10 Dec 2021Technical Expert Panel decision
Start:
10 Dec 2021Due:
22 Dec 2021Completion:
22 Dec 202130 June 2022
- As a Consumer I want to be able to access aggregation services so that I can take full advantage of commercial opportunities for my onsite generation or demand reduction.
- As Market Participant, I need to understand any changes to Market Messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
- As an Asset Metering Virtual Lead Party, I need to be recognised as a valid Market Data Service, so that I can appoint BSC Qualified Agents and fulfil relevant metering operations and data collection activities for Asset Metering.