Housekeeping February 2025

Date of latest update
Type
Change
ID
R0239
Change Path
Priority
Urgent
No
Latest Update
Housekeeping Change implemented on the 28 February 2025.
Summary
The code manager has identified a number of non-material clarifications, typographical errors and changes needed to REC products.
Proposer
Holly Law
Status
Implementation Date
Status Live
EMAR Version 28.02.2025_live
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
holly.law
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0239 Legal text.zip
Archive
Off
Problem Statement
This Housekeeping Change Proposal seeks to make typographical and formatting corrections that have been identified and improve consistency across the REC.
R0239 Housekeeping Change Report
Company Name
-
Review status
Review required

Erroneous Switch Review: CSS Solution

Date of latest update
Type
Issue
ID
I0237
Change Category
Change Path
Priority
Urgent
No
Latest Update
26/06/2026 On 25 June 2026, the REC Change Panel approved this extension to plan.
Summary
The current solution for Erroneous Switch (ES) resolution is failing some Consumers, there are gaps in the process and several areas that could be considered for improvement. It has been a number of years since the process has been reviewed end to end. Since then, Faster Switching has been introduced and MHHS is on the horizon.
Proposer
Carl Carl Dennis
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0237 Erroneous Switch Draft Guidance Document V0.2
Archive
Off
Problem Statement
ES obligations are a key Consumer-impacting process which facilitate the quick resolution of Consumer detriment as efficiently as possible and requires an end-to-end review.
SME
SME Role
Lead Technical Analyst
SME User
vaishnsharma@deloitte.co.uk
Change proposal Form
I0237 - Change Report (Proposal plan) Approved 17.06.2025
I0237 Change Proposal Re Plan V2.0
I0237 Extension to Plan V1.0 Approved 25.06.2026
Company Name
-
Review status
Review required

REC Party Auto de-accession proposal

Date of latest update
Type
Change
ID
R0236
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
Update the REC to allow the option of any Party who has not proceeded to pursue Certification within 12 months of accession, and has not contacted the REC Code Manager in at least 6 months to indicate they wish to do so/remain acceded, to be removed without further contact or confirmation with that Party.
Proposer
Rebecca Griffiths
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

04 Mar 2025
Status
Implementation Date
Status Live
EMAR Version 27.06.2025_live
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0236 - Legal Drafting v0.1
Archive
Off
Problem Statement
There are many Parties who have acceded to the REC but not Qualified within 12 months of accession, and who have not contacted the Code Manager within 6 months. This may cause confusion for Parties in knowing which other organisations have Qualified for roles under the REC.
SME
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0236 - Submission Form v1.0 - REC Party Auto de-accession proposal.docx
I0236 Change Report (Proposal Plan) v1.0 Approved 04.03.25
I0236 Consolidated Impact Assessment Responses v1.0
R0236 - Change Report (For Consultation) V1.0 (09.04.2025)
R0236 Consolidated Consultation Responses v1.0
R0236 Change Report (Final Recommendation) V1.0 Approved 03.06.25
Company Name
-
Review status
Review required

Missing Scenario Variants in D0179

Date of latest update
Type
Change
ID
R0235
Change Category
Change Path
Priority
Urgent
No
Latest Update
01/07/2025 - On 01 July 2025, the REC Change Panel voted to reject R0235 and approve R0235A, in line with the Code Manager's recommendation. The appeal window has closed.
Summary
Within MHHS SIT there is a scenario where the LDSO generates a D0139 to the MS for a PPM but the requirement is for the MS to generate a D0179. There is a gap in the D0179 data required and that provided on the D0139. 21.5.1 & 21.5.6 under Schedule 14 states that where the DNO changes the energisation status, within 3 WD of changing the energisation status the DNO will send the D0139 or the D0179(21.5.6) to the MS and then the MS will generate the D0179 to the Supplier(21.5.6). Currently, the LDSO only generates the D0179 to the Supplier but not to the MOP and the only change under MHHS is to add the new variant MSS.
Proposer
Patricia Parker
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

04 Mar 2025

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

06 Mar 2025

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

01 May 2025

Presented at REC Change Panel

Completed

Start:

Due:

Completion:

20 May 2025
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 27.02.2026_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0235 D0179 Missing Scenario Variants
Archive
Off
Document title
R0235 Data Specification V0.2
Archive
Off
Problem Statement
DNOs and MOAs cannot fulfil their full obligations listed in Schedule 14 Metering Operations as there missing Scenario Variants in the Data Specification preventing them from sending the D0179 to all required Parties.
Stages Selection
I0235 Change Proposal Form
I0235 Change Report (Proposal Plan) V1.0 Approved 04.03.25
I0235 Consolidated Impact Assessment Responses V1.0
R0235 and R0235A Change Report (For Consultation) V1.1
R0235 and R0235A Consolidated Consultation Responses PUBLIC V1.0
R0235 and R0235A Change Report (Final Recommendation) V2.0 (Approved) 01.07.2025
Company Name
-
Review status
Review required

Introduction of an energy theft Referral Assessment Service under the REC

Date of latest update
Type
Change
ID
R0234
Change Category
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
Energy theft is a significant issue, costing consumers between £457 million and £760 million annually (based on Autumn 2024 retail prices). Energy theft also poses safety risks, particularly due to tampered meters, which have caused fatal incidents. Whilst existing measures under the REC, such as the Energy Theft Tip-Off Service (ETTOS) and Theft Detection Incentive Scheme (TDIS) seek to provide information on likely instances of energy theft and the incentives to investigate them, there are currently insufficient enforcement mechanisms and coordination with law enforcement agencies. In particular, there are challenges due to limited police engagement and inconsistent prosecutions, contributing to a low deterrent.
Proposer
theft
Change Plan

Change Report (Proposal Plan) at Change Panel

Introduction of an energy theft Referral Assessment Service under the REC > Change Plan

Start:

29 Jan 2025

Due:

04 Feb 2025

Completion:

04 Feb 2025

Presentation to TIG

Completed

Start:

13 Jan 2025

Due:

29 Jan 2025

Completion:

29 Jan 2025

Change Proposal Updated Plan (Extension) at Change Panel

Introduction of an energy theft Referral Assessment Service under the REC > Change Plan

Start:

04 Feb 2025

Due:

18 Feb 2025

Completion:

18 Feb 2025

Final solution presented to TIG

Completed

Start:

18 Feb 2025

Due:

26 Feb 2025

Completion:

26 Feb 2025
Status
Implementation Date
Status Live
EMAR Version 27.06.2025_live
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0234 - Legal Drafting
Archive
Off
Document title
R0234 - ETU and RAS Case Acceptance Criteria
Archive
Off
Document title
R0234 - Referral information and evidentiary requirements
Archive
Off
Document title
RAS and ETU Referral Information and Evidentiary Requirements
Archive
Off
Problem Statement
The introduction of the ETU provides the mechanism to prosecute and add a significant deterrent previously missing from the theft landscape. To ensure an effective operation of this unit, the referrals should include standardised data by introducing the Referral Assessment Service (RAS). RAS will assess, triage and co-ordinate theft referrals received from industry parties.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
Change Proposal Form - Referral Assessment Service.docx
Energy Theft Unit - Business Case November 2024
I0234 - Change Report (Updated Plan) Approved 18.02.2025
R0234 Change Report (Party Impact Assessment)
R0234 Consolidated Impact Assessment Responses NON-CONFIDENTIAL
R0234 Change Report (Consultation)
R0234 Consolidated Consultation Responses NON-CONFIDEANTIAL (14/05/2025)
R0234 Change Report (Final Recommendation) Post-vote
R0234 Decision Letter
Company Name
-
Review status
Review required

Introduction of an Energy Theft Unit (ETU) under the REC

Date of latest update
Type
Change
ID
R0233
Change Category
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
Energy theft is a significant issue, costing consumers between £457 million and £760 million annually (based on Autumn 2024 retail prices). Energy theft also poses safety risks, particularly due to tampered meters, which have caused fatal incidents. Whilst existing measures under the REC, such as the Energy Theft Tip-Off Service (ETTOS) and Theft Detection Incentive Scheme (TDIS) seek to provide information on likely instances of energy theft and the incentives to investigate them, there are currently insufficient enforcement mechanisms and coordination with law enforcement agencies. In particular, there are challenges due to limited police engagement and inconsistent prosecutions, contributing to a low deterrent.
Proposer
theft
Change Plan

Change Report (Proposal Plan) at Change Panel

Introduction of an Energy Theft Unit (ETU) under the REC > Change Plan

Start:

29 Jan 2025

Due:

04 Feb 2025

Completion:

04 Feb 2025

Presentation to TIG

Completed

Start:

13 Jan 2025

Due:

29 Jan 2025

Completion:

29 Jan 2025

Change Report (Consultation) to Change Panel

Introduction of an Energy Theft Unit (ETU) under the REC > Change Plan

Start:

04 Feb 2025

Due:

18 Mar 2025

Completion:

18 Mar 2025

Change Report (Final) for Change Panel

In Progress

Start:

18 Mar 2025

Due:

06 May 2025

Completion:

06 May 2025
Status
Implementation Date
Status Live
EMAR Version 27.06.2025_live
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0233 - Legal drafting (28/02/2025)
Archive
Off
Problem Statement
Whilst existing measures under the REC, such as the Energy Theft Tip-Off Service (ETTOS) and Theft Detection Incentive Scheme (TDIS) seek to provide information on likely instances of Energy Theft and the incentives to investigate them, there are currently insufficient enforcement mechanisms and coordination with law enforcement agencies. Energy theft is an illegal activity where criminal charges are being given if perpetrators are being prosecuted. However, these are rarely happening due to limited police engagement and inconsistent prosecutions. This means offenders may re-offend given the low deterrent.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
Change Proposal Form - Energy Theft Unit.docx
Energy Theft Unit - Business Case November 2024
I0233 - Change Report (Proposal Plan) (Approved) 04/02/2025
R0233 Change Report (Consultation)
R0233 Consolidated Consultation Responses NON-CONFIDENTIAL
R0233 Change Report (Final Recommendation) Post-vote (07/05/2025)
R0233 Decision Letter
Company Name
-
Review status
Review required

Non-Domestic Change of Occupier SDEP Screens (R0155 Solution)

Date of latest update
Type
Change
ID
R0232
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
This Issue has been raised to develop the dedicated Non-Domestic Change of Occupier SDEP screens that were not possible as part of R0155 – Change of Occupier: Evidentiary Standards and Timescales. Should this Issue progress with a developed solution, the new dedicated Non-Domestic Change of Occupier screens would replace the temporary work around provided as a temporary workaround in the R0155 solution.
Proposer
lorna.mallon_sYHth
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 07.11.2025_live
Included changes Affected REC Items
R0003 Market-wide Half-Hourly Settlement Implementation
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
James Hardy
Date of Update to Priority
Solution Development
Proposed solution summary
  1. The solution will be developed through the Change Issues Group. Attendees will be invited to discuss and determine the requirements for the dedicated Non-Domestic Change of Occupier SDEP screens (a separate screen will be required for both Gas and Electricity). The solution will also require reporting for Performance Assurance and will include a plan for queries raised at cut over and data retention obligations. To help drive those discussions a starting point could be as follows: • Meter Point X Number (MPxN) • Multi MPxN flag – i.e. are there more than one • Date of CoO • Number of attachments • Accept evidence - Y / N – only available to the receiving supplier • Additional info – must be populated if N Auto populate: • Date of creation, date of response. • The Service Level Agreement (SLA) is 10 Working Days so it will need the RAG status based on that. Escalations screens – as per the standard REC escalations – including MPxN, date of creation and number of attachments. As part of any solution, the Code Manager will also update the non-mandatory Non-Domestic Change of Occupier Guidance Document to include further details on the newly dedicated SDEP screens, as well as further training material for Energy Suppliers.
Problem Statement
Due to the MHHS Code Freeze, newly dedicated Non-Domestic Change of Occupier SDEP screens could not be implemented as part of the R0155 solution and instead the use of re-purposed, existing screens was proposed as a temporary workaround. Energy Suppliers were clear in their responses to the R0155 impact assessment and consultation that using a temporary work around (with the temporary solution being the use of existing screens PT0056 and PT0067) would create additional workload and risk and that newly dedicated SDEP screens for Non-Domestic Change of Occupiers would still be required.
SME
SME Role
Lead Technical Analyst
I0232 - Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) - Issue form
I0232 - Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) - Change Report (Proposal Plan) V2.0 (17.06.2025)
I0232 - Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) - Change Report (Impact Assessment) 13.03.2025
R0232 - Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) - Change Report (For Consultation) 05.08.2025
I0232 - Consolidated Impact Assessment Responses (Non-Confidential) 08.04.2025
R0232 - Non-Confidential Consolidated Consultation Responses (02.09.2025)
R0232 - Change Report (Final Recommendation) V2.0 (Approved) 16.09.2025
SDEP User Training Deck v2.0
I0232 - Extension to Plan V1.0 (06.06.2025) Approved
Company Name
-
Review status
Review required

Domestic Elective HH Switching

Date of latest update
Type
Change
ID
R0227
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
This change aims to remove unnecessary blocks to Consumer Switching, where a Domestic Consumer is registered as elective Half Hourly (HH) with the Losing Supplier, but the Gaining Supplier does not offer this.
Proposer
angela.joyce
Status
Implementation Date
Status Live
EMAR Version 07.11.2025_live
Included changes Affected REC Items
R0003 Market-wide Half-Hourly Settlement Implementation
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0227 - Proposed Legal Text (IA) - Schedule 23 - Registration Services.doc
Archive
Off
Document title
I0227 Schedule 23 pre MHHS version
Archive
Off
Document title
I0227 Schedule 23 post MHHS version
Archive
Off
Problem Statement
There are issues when a Domestic Consumer intends to Switch Suppliers, but their MPAN is registered as elective HH with their current Supplier, and this is not offered by the Gaining Supplier. This can cause delays with Switching for Consumers.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Issues Proposal Form - Attachment 1. Electralink Post.docx
Issue Proposal form
I0227 - Change Report (Proposal Plan - Approved) v1.0 04.02.2025
I0227 - Consolidated Party Impact Assessment Responses (Non-Confidential) 11.04.2025
I0227 Extension to Plan V1.0 Approved 15.04.2025
R0227 Change Report (For Consultation) V1.0
R0227 Consolidated Consultation Responses v1.0
R0227 Change Report (Final Recommendation) V1.0 Approved 17.06.25
Company Name
-
Review status
Review required

In-year CRS budget amendment

Date of latest update
Type
Change
ID
R0226
Urgent
No
Latest Update
21/01/25 - Change Panel approved final recommendation for immediate implementation.
Summary
DCC has identified that the CRS budget for the current Financial Year (2024-2025) can be reduced, and as per the Code, a REC Change Proposal must be raised for the agreed budget to be amended.
Proposer
Bradley Baker
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
holly.law
Date of Update to Priority
Solution Development
Change Proposal Form
R0226 Change Report - Final Recommendation approved.
Company Name
-
Review status
Review required

Clarification on TDIS portfolio transfers on sale

Date of latest update
Type
Change
ID
R0225
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
The current wording of the Energy Theft Reduction Schedule has wording on the transfer of theft targets on portfolio sale, however which sales would qualify is ambiguous.
Proposer
Anton Moden
Change Plan

Change Plan at Change Panel

Clarification on TDIS portfolio transfers on sale > Change Plan

Start:

27 Nov 2024

Due:

21 Jan 2025

Completion:

21 Jan 2025

Change Report (Consultation) to Change Panel

In Progress

Start:

21 Jan 2025

Due:

04 Feb 2025

Completion:

Status
Implementation Date
Status Live
EMAR Version 27.06.2025_live
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0225 - Legal Drafting
Archive
Off
Document title
Schedule 7 Energy Theft Reduction (based on v3.0) Legal Drafting
Archive
Off
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Change/ Issue form
I0225 - Change Report - Proposal Plan (Approved 21/01/2025)
R0225 Change Report (Consultation)
R0225 Consolidated Consultation Responses
R0225 Change Report (Final) Post-vote
Company Name
-
Review status
Review required