Central provision of DCC Technical Contacts for requesting test certificates
Impact Assessment period - start date
Start:
23 Mar 2023Due:
19 May 2023Completion:
19 May 2023Impact Assessment period - end date
Start:
19 May 2023Due:
28 Jul 2023Completion:
28 Jul 2023Preliminary Change Report issued and consultation started
Start:
28 Jul 2023Due:
11 Aug 2023Completion:
11 Aug 2023Consultation end date
Start:
11 Aug 2023Due:
04 Sep 2023Completion:
04 Sep 2023Final Change Report issued
Start:
04 Sep 2023Due:
15 Sep 2023Completion:
08 Sep 2023Responsible Committee decision
Start:
15 Sep 2023Due:
22 Sep 2023Completion:
19 Sep 202323 February 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As the SO, I want sufficient simulators to be available in the test environments, so that I can test changes to CSS systems for all necessary scenarios
- As a CSS User, I want changes to the CSS systems to be robustly tested, so that implemented changes align to their design and deliver the planned benefits
- As a CSS User, I want to be able to manage my Technical Contacts, so that I am in control of my responsibilities under the REC
Revision of the approved solution for R0032
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Service Provider Impact Assessment Complete
Start:
31 Mar 2023Due:
11 Apr 2023Completion:
11 Apr 2023Party Impact Assessment Completed
Start:
11 Apr 2023Due:
11 Apr 2023Completion:
11 Apr 2023Preliminary Change Report Published for Consultation
Start:
11 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation Start
Start:
14 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation End
Start:
14 Apr 2023Due:
21 Apr 2023Completion:
21 Apr 2023Final Change Report Published
Start:
21 Apr 2023Due:
24 Apr 2023Completion:
24 Apr 2023Responsible Committee Discussion
Start:
24 Apr 2023Due:
26 Apr 2023Completion:
Appeal Window Closure
Start:
26 Apr 2023Due:
12 May 2023Completion:
30 June 2023
- As an impacted Market Participant, I want to have clarity on version of the Market Message and the population of Data Items within the Data Specification, so that my internal systems can be correctly configured to send and receive Data Items within Market Messages.
Revision of the Implementation Date and approved solution for R0021
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Responsible Committee Review Completed
Start:
31 Mar 2023Due:
27 Apr 2023Completion:
27 Apr 2023Consultation Started
Start:
27 Apr 2023Due:
28 Apr 2023Completion:
28 Apr 2023Consultation Ended
Start:
28 Apr 2023Due:
16 May 2023Completion:
16 May 2023Final Change Report Issued
Start:
16 May 2023Due:
19 May 2023Completion:
19 May 2023Responsible Committee Recommendation
Start:
19 May 2023Due:
26 May 2023Completion:
26 May 202330 June 2023
- As a premise owner I want to be able to contract with a Safe Isolator Provider (SIP), and for the SIP to be able to provide the service in a fully compliant manner.
- As a REC MEM who wants to operate as SIP, I need clarity on the solution and Market Message requirements when I provide Safe Isolation Works to Premise Owners. As a Registered Supplier, I need clarity on the solution and Market Message requirements when my consumers have Safe Isolation Works completed at their Premise Owners by SIPs.
- As a Distribution Network Operator, I need clarity on the solution and Market Message requirements when my connected parties have Safe Isolation Works completed at their Premise Owners by SIPs.
Update to Error Handling Documents
Optional fuzzy searching in EES
Service Provider Impact Assessment window start
Start:
07 Mar 2023Due:
09 Oct 2023Completion:
09 Oct 2023Service Provider Impact Assessment window close
Start:
09 Oct 2023Due:
27 Dec 2023Completion:
24 Nov 2024Party Impact Assessment start
Start:
27 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As an organisation providing switching services, I want Consumers to be able to search addresses efficiently.
Consequential Change for CSS Smart Meter Data Retriever Appointments
Service Provider Impact Assessment started
Start:
20 Feb 2023Due:
22 Mar 2023Completion:
22 Mar 2023Service Provider Impact Assessment completed
Start:
22 Mar 2023Due:
03 May 2023Completion:
03 May 2023Preliminary Change Report and Consultation issued
Start:
03 May 2023Due:
19 May 2023Completion:
19 May 2023Consultation closed
Start:
19 May 2023Due:
05 Jun 2023Completion:
05 Jun 2023Final Change Report issued
Start:
05 Jun 2023Due:
21 Jun 2023Completion:
15 Jun 2023Responsible Committee decision
Start:
21 Jun 2023Due:
28 Jun 2023Completion:
04 Jul 2023Appeal Window opens
Start:
28 Jun 2023Due:
04 Jul 2023Completion:
04 Jul 2023Appeal Window closes
Start:
04 Jul 2023Due:
18 Jul 2023Completion:
18 Jul 2023MHHS Programme Milestone M8 (Code changes delivered)
- As the CSS Provider, I want to be able to identify which appointment messages received from ERDS require a response, so that I can confirm whether the appointment was successfully made in SMDSP
- As the ERDS Provider, I want to be able to indicate which appointment messages I need to receive a response for, so that I can understand which appointments have been successful in the SMDSP
- As an Electricity Supplier, I want Supplier appointments in the ERDS to match those held in SMDSP
CSS Message Regeneration Functionality
Update to Plan approved at Change Panel
Start:
Due:
Completion:
21 Oct 202505 November 2027
Changes to allow DNOs to reinstate disconnected MPANs
- As a Consumer, I do not want the erroneous disconnection of my MPAN to affect the continuity of my supply contract and billing arrangements.
- As a DNO, I want to be able to reverse erroneous disconnections with no lasting effect so that I don’t need to create a new MPAN to resolve the issue, thereby avoiding DUoS payment collection issues. 2 - As a Supplier, I want to be able to reverse erroneous disconnections with no lasting effect so that I can correctly bill my consumers. 3 - As the CSS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate. 4 - As MPRS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate.
Clarify obligations on gas meter exchanges that occur close to CoS
Solution Development & Analysis
Start:
17 Feb 2023Due:
29 Mar 2024Completion:
27 Mar 2024Party Impact Assessment Due
Start:
29 Mar 2024Due:
19 Apr 2024Completion:
19 Apr 2024Preliminary Change Report Issued
Start:
19 Apr 2024Due:
26 Apr 2024Completion:
26 Apr 2024Responsible Committee Review
Start:
26 Apr 2024Due:
08 May 2024Completion:
08 May 2024Consultation Closes
Start:
08 May 2024Due:
31 May 2024Completion:
31 May 2024Final Change Report Issued
Start:
31 May 2024Due:
05 Jun 2024Completion:
05 Jun 2024Responsible Committee Decision
Start:
05 Jun 2024Due:
12 Jun 2024Completion:
12 Jun 2024Appeal Window Closure
Start:
12 Jun 2024Due:
26 Jun 2024Completion:
08 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want my Supplier to have accurate information about my meter, so that I do not experience billing problems following a Switch.
- As a MEM, I want to clearly understand my obligations relating to data transfer during a Switch, so that records of work I carry out are accurately recorded. 2 - As a Registered Supplier, I want metering data on my portfolio of Registrable Measurement Points to be accurate, so that Consumers do not experience billing problems or have a negative switch experience. 3 - As the CDSP, I want Change of Metering Asset data communicated with me to be timely and accurate, so that I am better able to fulfil my role and support REC Parties.