House Keeping Amendment to the PARC
Final Change Report Issued
Start:
07 Mar 2024Due:
14 Mar 2024Completion:
14 Mar 2024Responsible Committee Decision
Start:
14 Mar 2024Due:
26 Mar 2024Completion:
26 Mar 202428 March 2024
DCC Service Level Agreements for the Switching Incentive Regime (Alternative)
08 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want the CRS Provider to provide an effective service so that my Switch is not delayed.
- As the REC Code Manager, I want to ensure the CRS Provider has appropriate SLAs set, which incentivises the effective functioning of the Switching Service.
- As the CRS Provider, I want to ensure that the appropriate SLAs are in place to incentivise the effective functioning of the Switching Service and if these SLAs are not met by the CRS Provider, the commercial impact is proportionate to the detriment experienced by CSS Users and Consumers.
Performance Assurance Report Catalogue V5.1
PRELIMINARY CHANGE REPORT AND CONSULTATION ISSUED
Start:
24 Nov 2023Due:
05 Jan 2024Completion:
05 Jan 2024CONSULTATION CLOSES
Start:
05 Jan 2024Due:
26 Jan 2024Completion:
26 Jan 2024FINAL CHANGE REPORT ISSUED
Start:
26 Jan 2024Due:
16 Feb 2024Completion:
16 Feb 2024RESPONSIBLE COMMITTEE DECISION
Start:
16 Feb 2024Due:
27 Feb 2024Completion:
28 March 2024
- As a Consumer, I want parties who handle my energy account information to be held to high standards, so that I have confidence in their management of my information.
- As a REC Party and/or Service Provider, I want the performance assurances standards to which I am held to be regularly reviewed, so that I have confidence in monitoring activities.
DCC Service Level Agreements for the Switching Incentive Regime
Solution Development
Start:
01 Feb 2023Due:
05 Oct 2023Completion:
05 Oct 2023Service Provider Impact Assessment
Start:
05 Oct 2023Due:
20 Nov 2023Completion:
13 Nov 2023Party Impact Assessment
Start:
20 Nov 2023Due:
03 Jan 2024Completion:
10 Nov 2023Preliminary Change Report issued
Start:
03 Jan 2024Due:
20 Feb 2024Completion:
16 Feb 2024Preliminary Change Report - Committee Review
Start:
20 Feb 2024Due:
27 Feb 2024Completion:
27 Feb 2024Consultation close
Start:
01 Mar 2024Due:
04 Apr 2024Completion:
04 Apr 2024Final Change Report issued
Start:
04 Apr 2024Due:
23 Apr 2024Completion:
19 Apr 2024Responsible Committee Decision
Start:
23 Apr 2024Due:
30 Apr 2024Completion:
30 Apr 2024Sent to Authority for Determination
Start:
30 Apr 2024Due:
01 May 2024Completion:
Consultation published
Start:
27 Feb 2024Due:
01 Mar 2024Completion:
01 Mar 2024- As a Consumer, I want the CRS Provider to provide an effective service so that my Switch is not delayed.
- As the REC Code Manager, I want to ensure the CRS Provider has appropriate SLAs set, which incentivises the effective functioning of the Switching Service.
- As the CRS Provider, I want to ensure that the appropriate SLAs are in place to incentivise the effective functioning of the Switching Service and if these SLAs are not met by the CRS Provider, the commercial impact is proportionate to the detriment experienced by CSS Users and Consumers.
Amendments to Sample Access Agreement
PARTY IMPACT ASSESSMENT
Start:
02 Sep 2022Due:
24 May 2024Completion:
24 May 2024PRELIMINARY CHANGE REPORT ISSUED
Start:
24 May 2024Due:
18 Jul 2024Completion:
18 Jul 2024RESPONSIBLE COMMITTEE REVIEW
Start:
18 Jul 2024Due:
30 Jul 2024Completion:
30 Jul 2024CONSULTATION ISSUED
Start:
30 Jul 2024Due:
02 Aug 2024Completion:
01 Aug 2024FINAL CHANGE REPORT ISSUED
Start:
02 Aug 2024Due:
12 Sep 2024Completion:
12 Sep 2024RESPONSIBLE COMMITTEE DECISION
Start:
12 Sep 2024Due:
24 Sep 2024Completion:
24 Sep 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want systems containing my information to be correctly assured, so that my personal information is kept safe and services I expect to be able to use are not disrupted.
- As a Non-Party REC Service User, I want the Access Agreement I sign before I can access services from the CRS Provider to give me the same protections as other service users, so I am protected from loss and liability caused by another service user, or the service itself.
- As the CRS Provider, I want Non-Party REC Service Users to be held to the same provisions as other CSS Users, so I am protected from loss and liability caused by them.
- As a CSS User, I want Non-Party REC Service Users to be held to the same
Maintenance of Qualification Schedule Change
Solution Development
Start:
05 Aug 2022Due:
01 Mar 2023Completion:
01 Mar 2023Impact Assessment Start
Start:
01 Mar 2023Due:
10 Mar 2023Completion:
10 Mar 2023Impact Assessment End
Start:
10 Mar 2023Due:
24 Mar 2023Completion:
24 Mar 2023Preliminary Change Report Issued
Start:
24 Mar 2023Due:
14 Apr 2023Completion:
14 Apr 2023Responsible Committee Review
Start:
14 Apr 2023Due:
25 Apr 2023Completion:
25 Apr 2023Consultation Start
Start:
25 Apr 2023Due:
28 Apr 2023Completion:
28 Apr 2023Consultation End
Start:
28 Apr 2023Due:
22 May 2023Completion:
22 May 2023Final Change Report Issued
Start:
22 May 2023Due:
16 Jun 2023Completion:
15 Jun 2023Responsible Committee Decision
Start:
16 Jun 2023Due:
27 Jun 2023Completion:
27 Jun 2023Appeal Window Closure
Start:
27 Jun 2023Due:
11 Jul 2023Completion:
03 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0104 | Clarifying requirement for continuous billing following an Erroneous Switch |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 08 Jun 2026 | ||
| 1.0 | 08 Jun 2026 |
- As an Energy Supplier, DNO, GT, MEM and REC Service User, I want to understand precisely what obligations apply to me under the Schedule 9 – Qualification and Maintenance, so that I can provide the required information to the Code Manager in a timely manner and be compliant.
- As the REC Code Manager, I want REC Parties and REC Service Users to have a clear understanding of the information they need to submit relating to the maintenance of their qualification, so that necessary information can be submitted for review and consideration in the most efficient way.
Performance Assurance Report Catalogue Changes as a consequence of REC V3.0
Impact Assessments completed
Start:
23 Mar 2022Due:
16 May 2022Completion:
16 May 2022Preliminary Change Report published
Start:
16 May 2022Due:
31 May 2022Completion:
31 May 2022Consultation started
Start:
31 May 2022Due:
31 May 2022Completion:
31 May 2022Consultation completed
Start:
31 May 2022Due:
16 Jun 2022Completion:
16 Jun 2022Final Change Report published
Start:
16 Jun 2022Due:
21 Jun 2022Completion:
21 Jun 2022Responsible Committee decision
Start:
21 Jun 2022Due:
28 Jun 2022Completion:
28 Jun 202218 July 2022
- As the Code Manager I need to receive the necessary data to complete the required Performance Assurance activities post REC V3.0
- As a REC Service Provider, I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0
- As a Supplier I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0. As a MEM I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0.
Service Provider Performance Charges (DCC)
Preliminary Change Report and Consultation Issued
Start:
04 Jan 2022Due:
15 Nov 2022Completion:
15 Nov 2022Final Change Report Issued
Start:
15 Nov 2022Due:
09 Dec 2022Completion:
09 Dec 2022Responsible Committee Decision
Start:
09 Dec 2022Due:
20 Dec 2022Completion:
20 Dec 2022Send to Authority for Decision
Start:
20 Dec 2022Due:
21 Dec 2022Completion:
21 Dec 202201 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As the REC Code Manager, I want to ensure that REC Service Providers achieve their Service Level Agreements (SLAs) defined in REC Service Definitions, so that impacts to the REC Code Manager, REC Parties and other Service Providers, as a consequence of Service Provider underperformance, are minimised and the change process delivers to time and cost.