Implementation of Ofgem-led code modification prioritisation within the REC

Date of latest update
Type
Change
ID
R0304
Change Category
Change Path
Urgent
No
Latest Update
This change Proposal has been approved for implementation on the date as directed by the Authority.
Summary
Ofgem has consulted on, and is progressing towards a decision on, the introduction of a harmonised code modification prioritisation framework across all industry codes, under its transitional powers in Schedule 12 to the Energy Act 2023. This Issue is being raised to provide the formal REC change vehicle through which Ofgem’s prioritisation reforms can be tracked, developed and implemented in the REC, once the Authority has published its decision and statutory modification notice.
Proposer
Ann Perry
Change report - Final Change Report

Comments deadline
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
holly.law
Date of Update to Priority
Solution Development
Problem Statement
In the absence of REC changes, the REC would not align with Ofgem’s harmonised approach to code modification prioritisation, creating inconsistency with other industry codes and undermining the objectives of Energy code reform.
I0304 submission form
I0304 Change Report (Proposal Plan) V1.0
New Priority Status
Company Name
-
Review status
Review required

Review of Schedule 1 Interpretations and Definitions

Date of latest update
Type
Change
ID
R0291
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
During the quality checks of REC Schedules for MHHS, several capitalised terms throughout schedules were identified with no entry in Schedule 1. It has also been identified that there are definitions that link to Schedules (such as 2, 20 and 21) which are no longer live REC Schedules. The Code Manager has reviewed these and determined some changes are required to Schedule 1.
Proposer
Caroline Freimuller
Change Report - Draft Change Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Live
EMAR Version 26.06.2026_live
Included changes Affected REC Items
R0103 Central provision of DCC Technical Contacts for requesting test certificates
  • Schedule 25 - Central Switching Service
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0291 REC Main Body draft V0.1
Archive
Off
Document title
R0291 Schedule 1 draft V0.1
Archive
Off
Document title
R0291 Schedule 25 (CSS) draft V0.1
Archive
Off
Document title
R0291 Schedule 1 draft V0.2
Archive
Off
Document title
R0291 REC Main Body draft V0.1
Archive
Off
Document title
R0291 Schedule 25 (CSS) draft V0.1
Archive
Off
Problem Statement
Without clear definitions of all defined terms within the REC, there may be confusion for REC Parties and other industry participants who use REC documents.
I0291 submission form
I0291 Change Report (Proposal Plan) V1.0
R0291 Change Report (For Consultation) V1.0
R0291 Consolidated Consultation Responses v1.0
R0291 Change Report (Final Recommendation) V1.1 approved 21.04.26
Company Name
-
Review status
Review required

Annual Address Management Plan Updates

Date of latest update
Type
Change
ID
R0283
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
Address management is the responsibility of DCC, with support from REC Parties. There has been progress resolving address data issues, but there is no mechanism to clearly establish code level targets for address improvement, or overall market performance.
Proposer
anton.moden
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

21 Oct 2025
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 27.02.2026_live
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0283 Legal Text For Consultation
Archive
Off
Problem Statement
The REC Address Management Service is the responsibility of DCC, with support from REC Parties. There has been progress resolving address data issues, but there is no mechanism to clearly establish code level targets for address improvement, or overall market performance.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0283 submission form
R0283 Change Report (Proposal Plan) v1.0 approved 21/10/2025
R0283 Change Report (For Consultation) v1.0
R0283 Consolidated Consultation Responses v1.0
R0283 - Change Report (Final Recommendation) Approved 16.12.25 v1.0
Company Name
-
Review status
Review required

Establishing the Safe Isolation Provider (SIP) as a Standalone REC Party

Date of latest update
Type
Issue
ID
I0278
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - An Update to Plan has been approved by the Change Panel on 21 July 2026.
Summary
This proposal recommends the formal recognition of the Safe Isolation Provider (SIP) as a standalone Party under the Retail Energy Code (REC). This aligns with the direction set out in Ofgem’s recently published Strategic Direction Statement (SDS), which explicitly calls for the establishment of SIPs as a standalone Party role. The aim is to address the growing scale of unregulated SIP activity, mitigate associated consumer safety risks, and ensure the metering industry is equipped to support the UK’s Net Zero ambitions. By enabling easier access to certified SIPs, this change will enhance consumer protection, accelerate low-carbon technology deployment, and improve operational efficiency across the energy sector.
Proposer
Rebecca Griffiths
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
The current SIP framework poses several risks: - Consumers, MEMs and unaccredited practitioners’ safety. Unaccredited and unregulated isolation work increases the risk of unsafe installations and potential harm to Consumers. NAPIT highlighted to RECCo and DESNZ that 17 and 13 unregulated practitioners respectively died in 2023 and in 2024 due to unsafe isolation. With the right Party undertaking this work, there would also be less safety issues for the Consumer at their premises; - Inequity. Independent Installers face longer wait times compared to supplier-led installations, creating a two-tier system; - Low competitive market. Currently prospective Parties can be put off from applying to be a SIP as it appears they would need full MEM Accreditation which is often too far outside their current business operating model. Providing SIPs with their own pathway and requirements could result in more Parties becoming SIPs and therefore giving Consumers more choice in their provider; and - Decarbonisation delays. The inability to scale SIP capacity undermines the timely deployment of LZCTs, threatening Net Zero targets.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0278 submission form
I0278 Change Report (Proposal Plan) V1.0 (Pre-Approval) 09.10.2025
I0278_Change Report (Extension to Plan) v1.0 (Pre-Approval) 12.01.2026
I0278_Change Report (Extension to Plan) v2.0 (Pre-Approval) 13.07.2026
I0278_Change Report (Extension to Plan) v2.1 (Approved) 21.07.26
I0278_Consolidated Information Request DNO Responses
I0278_Consolidated Information Request MEM-SIP Responses PUBLIC
I0278_Consolidated Information Request RPA Responses
Company Name
-
Review status
Review required

Clarification of SIP Qualification Requirements

Date of latest update
Type
Change
ID
R0270
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
REC Schedules 1, 14, and 15 all note that in order to Qualify as a Safe Isolation Provider (SIP), the Party needs to be a Qualified Meter Operator Agent (MOA). It has since been determined that Qualified Electricity Metering Operatives (EMOs) should also be able to Qualify as SIPs.
Proposer
Daniel Rodgers
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Live
EMAR Version 27.02.2026_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0270 draft legal text
Archive
Off
Problem Statement
Requiring SIPs to be fully Qualified MOAs may be hindering smaller Parties who wish to be SIPs from Qualifying under the REC. This in turn may be reducing the number of Qualified SIPs in the market for Consumers to choose from or causing Consumers inadvertently to contract with people who are not Qualified SIPs to carry out SIP Works.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0270 Submission Form
I0270 Change Report (Proposal Plan) V1.0 approved 18.11.25
R0270 Change Report (For Consultation) V1.1 approved 10.12.25
R0270 Consolidated Consultation Responses V1.0
R0270 Change Report (Final Recommendation) V1.0 approved 11.02.26
Company Name
-
Review status
Review required