Post-MHHS Full Transition Complete (M15) REC updates

Date of latest update
Type
Issue
ID
I0325
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - On 21 July 2026, the REC Change Panel voted to approve the Change Report (Proposal Plan) for I0325.
Summary
The REC was updated, primarily through R0209 and R0241, to add requirements that support the transition to, and enduring operation of the MHHS arrangements. As part of the transition, each impacted Metering Point will be migrated using processes defined in Codes, including the REC. Once this migration activity is complete, the legacy and transitional arrangements will become redundant and should be removed from the REC to support its efficient operation
Proposer
Jonny Moore
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
Retention of redundant obligations within the REC would make it more complex to navigate for Market Participants and could cause confusion on the obligations that are in effect to support the efficient operation of the Great British Energy retail market. It is also worth noting that until Ofgem formally closes the MHHS Significant Code Review (SCR), this REC Issue could potentially impact that SCR.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0325 submission form
I0325 Scope list
Company Name
-
Review status
Review required

Review of export meter work arrangements

Date of latest update
Type
Issue
ID
I0312
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
28/05/2026 The Code Manager has set up an I0312 Working Group to engage with Industry Parties on solution development. The next session will be held on Wednesday, 03 June 2026. To register your interest, please email change.management@recmanager.co.uk
Summary
The REC Metering Operations Schedule has limited distinction between the activities for import and export metering. These provisions were not specifically developed to support a market with high volumes of small-scale microgeneration with shared metering assets for import and export.
Proposer
Jon Hawkins
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
There is a lack of distinction within REC Schedule 14 – Metering Operations between activities for Import and Export Metering, and how to manage work arrangements where is a shared Metering Asset between Import and Export Suppliers.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0312 submission form
I0312 Change Report (Proposal Plan) v1.0 Approved 21.04.26
Company Name
-
Review status
Review required

CoMCoP 2-year Audit Cycles

Date of latest update
Type
Change
ID
R0311
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
Renewal audits under the Consolidated Metering Code of Practice (CoMCoP) are consistently delivered on a 2 year cycle and include both a desktop audit and a site audit. However, Schedule 15 currently does not explicitly define this.
Proposer
David Haddock
Change Report - Initial Assessment and Change Plan Report
Change report - Final Change Report
Impacted REC Documents
Status
Implementation Date
Status Live
EMAR Version 26.06.2026_live
Included changes Affected REC Items
R0103 Central provision of DCC Technical Contacts for requesting test certificates
  • Schedule 25 - Central Switching Service
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. An update to the REC Schedule 15 - Metering Accreditation
Proposed Solution Document
Document title
R0311_Draft legal text (For Final Recommendation)
Archive
Off
Problem Statement
The current lack of explicit wording in the Metering Accreditation Schedule of both a desktop and site audits that need to be completed one year after the initial accreditation, and then every two years for renewals introduces ambiguity for future audit delivery undertaken under CoMCoP as it creates a gap between operational practice and the codified baseline. This could potentially lead to inconsistent approaches by Parties, which in turn could reduce the consistency, predictability, and effectiveness of the industry’s audit and assurance framework.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0311 submission form
Draft legal text (On submission)
R0311 Draft legal text (For Consultation)
R0311_Change Report (Final Recommendation)_v1.1 (13 May 2026)
Company Name
-
Review status
Review required

REC Change to Align with DCP467 Asset Condition Reporting

Date of latest update
Type
Change
ID
R0306
Change Category
Change Path
Priority
Urgent
No
Latest Update
08/07/2026 - the Metering Expert Panel approved the Update to Plan.
Summary
DCUSA change DCP467 has been raised to propose that Category A and B defects reported currently using the Asset Condition Report (D0135) or phone call to the DNO, should instead be reported via an online reporting tool where the DNO has one available. This is expected to have impacts to the REC.
Proposer
Caroline Freimuller
Status
Implementation Date
Status Live
EMAR Version 06.11.2026_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0306 STIRG Guidance Document draft V0.1
Archive
Off
Document title
I0306 Data Spec changes v0.1
Archive
Off
Document title
R0306 STIRG Guidance Document draft V0.2
Archive
Off
Document title
R0306 Data Spec changes V0.2
Archive
Off
Problem Statement
Where DNOs have enhanced reporting tools for Category A or Category B situations, it is not mandatory for Parties to submit reports using this method. This may lead to a detrimental Consumer experience, as it is limited what information can be provided over the telephone or via Market Message (e.g. it is not possible to provide photographs of the situation).
I0306 submission form
I0306 Change Report (Proposal Plan) V1.0 approved 03.02.26
I0306 Consolidated Impact Assessment Responses V1.0
R0306 Change Report (For Consultation) V1.1
R0306 Consolidated Consultation Responses v1.1 PUBLIC
R0306 Change Proposal Re-Plan v1.0 approved 08.07.26
Company Name
-
Review status
Review required

Updates to Schedule 14 Measurement Transformers Commissioning Timescales

Date of latest update
Type
Change
ID
R0284
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
12/08/2026 - the Metering Expert Panel approved the Change Report (Final Recommendation) V1.2. This Change Proposal will be implemented on 26 June 2027. If you wish to appeal this decision, this must be received by COB 28 August 2026.
Summary
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
Proposer
Caroline Freimuller
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Change Report - Draft Change Report
Impacted REC Documents
Status
Implementation Date
Status Live
EMAR Version 25.06.2027_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0284 Schedule 14 Metering Operations draft V0.2
Archive
Off
Document title
R0284 Schedule 14 Metering Operations draft V0.3
Archive
Off
Document title
R0284 Schedule 14 Metering Operations final version
Archive
Off
Problem Statement
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
I0284 submission form
I0284 Change Report (Proposal Plan) V1.0 approved 03.02.26
I0284 Change Issue Group paper v1.0
I0284 Consolidated Impact Assessment Responses PUBLIC v1.0
R0284 Change Report (For Consultation) V1.0 approved 08.04.26
R0284 Consolidated Consultation Responses PUBLIC v1.0
R0284 Change Report (Final Recommendation) V1.2 approved 12.08.26
Company Name
-
Review status
Review required

Establishing the Safe Isolation Provider (SIP) as a Standalone REC Party

Date of latest update
Type
Issue
ID
I0278
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - An Update to Plan has been approved by the Change Panel on 21 July 2026.
Summary
This proposal recommends the formal recognition of the Safe Isolation Provider (SIP) as a standalone Party under the Retail Energy Code (REC). This aligns with the direction set out in Ofgem’s recently published Strategic Direction Statement (SDS), which explicitly calls for the establishment of SIPs as a standalone Party role. The aim is to address the growing scale of unregulated SIP activity, mitigate associated consumer safety risks, and ensure the metering industry is equipped to support the UK’s Net Zero ambitions. By enabling easier access to certified SIPs, this change will enhance consumer protection, accelerate low-carbon technology deployment, and improve operational efficiency across the energy sector.
Proposer
Rebecca Griffiths
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
The current SIP framework poses several risks: - Consumers, MEMs and unaccredited practitioners’ safety. Unaccredited and unregulated isolation work increases the risk of unsafe installations and potential harm to Consumers. NAPIT highlighted to RECCo and DESNZ that 17 and 13 unregulated practitioners respectively died in 2023 and in 2024 due to unsafe isolation. With the right Party undertaking this work, there would also be less safety issues for the Consumer at their premises; - Inequity. Independent Installers face longer wait times compared to supplier-led installations, creating a two-tier system; - Low competitive market. Currently prospective Parties can be put off from applying to be a SIP as it appears they would need full MEM Accreditation which is often too far outside their current business operating model. Providing SIPs with their own pathway and requirements could result in more Parties becoming SIPs and therefore giving Consumers more choice in their provider; and - Decarbonisation delays. The inability to scale SIP capacity undermines the timely deployment of LZCTs, threatening Net Zero targets.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0278 submission form
I0278 Change Report (Proposal Plan) V1.0 (Pre-Approval) 09.10.2025
I0278_Change Report (Extension to Plan) v1.0 (Pre-Approval) 12.01.2026
I0278_Change Report (Extension to Plan) v2.0 (Pre-Approval) 13.07.2026
I0278_Change Report (Extension to Plan) v2.1 (Approved) 21.07.26
I0278_Consolidated Information Request DNO Responses
I0278_Consolidated Information Request MEM-SIP Responses PUBLIC
I0278_Consolidated Information Request RPA Responses
Company Name
-
Review status
Review required

Clarification of SIP Qualification Requirements

Date of latest update
Type
Change
ID
R0270
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
REC Schedules 1, 14, and 15 all note that in order to Qualify as a Safe Isolation Provider (SIP), the Party needs to be a Qualified Meter Operator Agent (MOA). It has since been determined that Qualified Electricity Metering Operatives (EMOs) should also be able to Qualify as SIPs.
Proposer
Daniel Rodgers
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Live
EMAR Version 27.02.2026_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0270 draft legal text
Archive
Off
Problem Statement
Requiring SIPs to be fully Qualified MOAs may be hindering smaller Parties who wish to be SIPs from Qualifying under the REC. This in turn may be reducing the number of Qualified SIPs in the market for Consumers to choose from or causing Consumers inadvertently to contract with people who are not Qualified SIPs to carry out SIP Works.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0270 Submission Form
I0270 Change Report (Proposal Plan) V1.0 approved 18.11.25
R0270 Change Report (For Consultation) V1.1 approved 10.12.25
R0270 Consolidated Consultation Responses V1.0
R0270 Change Report (Final Recommendation) V1.0 approved 11.02.26
Company Name
-
Review status
Review required

Effective Dates in EES

Date of latest update
Type
Issue
ID
I0247
Other Industry Codes impacted
Urgent
No
Latest Update
12/08/2026 - the Proposer has chosen to withdraw this Issue as MHHS means many of the effective dates are being updated as per the original business case so the change is no longer required.
Summary
On a switch many of the effective dates within EES default to the switch date. This includes energisation status. It means EES users that don't have access to the meter technical details do not know the actual date the status changed.
Proposer
Lorna Mallon
Impacted REC Documents
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
Stages Selection
Stages Selection
Proposal Form
Company Name
-
Review status
Review required