Explore use of CHECK as a Meter Type option on J0483 DI-059

Date of latest update
Type
Issue
ID
I0344
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
24/08/2026 - accepted in by Code Manager
Summary
It has been suggested that CHECK meters should not be sent within industry messages so the presence of this value within the valid set may not be required. This Issue has been raised to explore whether this assumption is correct, look at the existing/historic use cases industry have used the CHECK option for, if they are no longer valid and if so why not.
Proposer
Holly Law
Impacted REC Documents
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
I0344 submission form
Company Name
-
Review status
Review required

Improved Validation for DI51599 - Electricity Smart Meter Equipment (ESME ID)

Date of latest update
Type
Issue
ID
I0341
Priority
Urgent
No
Latest Update
13/08/2026 - accepted in by Code Manager
Summary
A DNO has raised an issue with the ESME ID data stored in MPRS. Some of the ESMEs are passing MPRS basic validation but are being rejected by the proposed Metering Service preventing a change of service.
Proposer
Daniel Tadecicco
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
I0341 submission form
Company Name
-
Review status
Review required

REC Change to align with CP1633 Capture Modem Module Details Under BSCP601

Date of latest update
Type
Issue
ID
I0338
Change Category
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
06/08/2026 - Issue accepted in by the Code Manager
Summary
BSC CP1633 “Capture Modem Module Details Under BSCP601” makes amendments to BSCP601 Metering Protocol Approval and Compliance Testing. One of the amendments places obligations on MOAs where they are introducing and amending Communications Equipment. Equivalent and potentially expanded obligations need to be placed within REC Schedule 14 Metering Operations to support this.
Proposer
Lee Walker
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
I0338 submission form
Company Name
-
Review status
Review required

Post-MHHS Full Transition Complete (M15) REC updates

Date of latest update
Type
Issue
ID
I0325
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - On 21 July 2026, the REC Change Panel voted to approve the Change Report (Proposal Plan) for I0325.
Summary
The REC was updated, primarily through R0209 and R0241, to add requirements that support the transition to, and enduring operation of the MHHS arrangements. As part of the transition, each impacted Metering Point will be migrated using processes defined in Codes, including the REC. Once this migration activity is complete, the legacy and transitional arrangements will become redundant and should be removed from the REC to support its efficient operation
Proposer
Jonny Moore
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
Retention of redundant obligations within the REC would make it more complex to navigate for Market Participants and could cause confusion on the obligations that are in effect to support the efficient operation of the Great British Energy retail market. It is also worth noting that until Ofgem formally closes the MHHS Significant Code Review (SCR), this REC Issue could potentially impact that SCR.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0325 submission form
I0325 Scope list
Company Name
-
Review status
Review required

Meter Manufacturers Make and Type not Populated in SMRS

Date of latest update
Type
Issue
ID
I0297
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
An Update to Plan has been approved by the REC Technical Expert Panel on 25 June 2026.
Summary
The Meter Manufacturers Make and Type (J0410 / DI-048) was not populated as part of the MHHS Programme's data cleanse. However it is part of the SMRS maintained Meter Technical Details (MTDs) for Smart Meters which replace the DTC MTD Market Messages for Smart Meters in the MHHS environment. It is not currently possible to populate this item in the legacy arrangements.
Proposer
jonny.moore_42
Change Report - Initial Assessment and Change Plan Report
Impacted REC Services
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
Problem Statement
Following MHHS Migration, the MTDs provided by SMRS do not include the Meter Manufacturers Make and Type, as this replaces the existing D0149/D0150 Market Messages it could lead to the information being lost. This will mean Energy Suppliers and MOAs will not know the make and type of meter installed at a particular Site.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0297 submission form
I0297 Change Report (Proposal Plan) V1.0
I0297 Update to plan
I0297 Legal Drafting
Company Name
-
Review status
Review required

Registration Id Required for MHHS Appointments

Date of latest update
Type
Issue
ID
I0296
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
12/05/2026 - The Code Manager have developed a solution which has been live since 05 May 2026. More detail can be found on the REC Portal Wiki. A Closure Report has now been published, and this Issue has now been classed as resolved.
Summary
The RegistrationId (DI90043 / DI849) is required by SMRS to be included in the IF-031 'Supplier Agent Appointment Request' Market Message to allow the SMRA to process the appointment request. However not all Suppliers hold the RegistrationId for all Meter Points, in particular those that have not undergone a Registration managed by the Central Switching Service (CSS)
Proposer
jonny.moore_42
Change Report - Initial Assessment and Change Plan Report
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As part of the solution for REC Issue I0296 - Registration Id Required for MHHS Appointments the REC Code Manager have developed a process to provide Energy Suppliers the Registration Id for Metering Points that have not been through a Central Switching Service (CSS) Registration Managed Switch. This is to allow Energy Suppliers that may not hold the Registration Id for these Metering Points to populate the Market-wide Half Hourly Settlement (MHHS) Agent Appointment Messages required to initiate a MHHS Migration.
  2. More detail of the solution can be found: https://recportal.co.uk/rec-wiki-mhhs/-/knowledge_base/market-wide-half-hourly-settlement/provision-of-registration-id-required-for-mhhs-appointments?utm_source=emailoctopus&utm_medium=email&utm_campaign=Weekly%20Bulletin%20-%202026-05-01
Proposed Solution Document
Document title
I0296 Closure Report_v1.0 (12 May 2026)
Archive
Off
Problem Statement
Not all Energy Suppliers hold the RegistrationId for all Meter Points, particularly those Meter Points that have not gone through a Switch, i.e. have not undergone a Registration managed by the CSS. The RegistrationId is currently only available where a Metering Point has been through a CSS managed Registration. Without the RegistrationId available to Energy Suppliers, not all Metering Points will be able to migrate putting the MHHS Migration and Milestone M15 at risk.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0296 submission form
Company Name
-
Review status
Review required

Legacy Data Item API Service

Date of latest update
Type
Change
ID
R0290
Change Category
Change Path
Priority
Urgent
No
Latest Update
02/06/2026 - the REC Change Panel voted to reject the implementation of this Change Proposal, in line with the Code Manager recommendation. The appeal window closed on 17 June 2026.
Summary
MHHS removes certain Data Items (e.g. Profile Class, Measurement Class, Standard Settlement Configuration, Time Pattern Regime etc.) that are important to wider processes and products offered to consumers. This proposal is seeking a mechanism for electricity Market Participants to look up the previous entries for these legacy Data Items held before MHHS Migration begins.
Proposer
jmurphy
Impacted REC Documents
Impacted REC Services
Status
Implementation Date
Status Live
EMAR Version 26.06.2026_live
Included changes Affected REC Items
R0103 Central provision of DCC Technical Contacts for requesting test certificates
  • Schedule 25 - Central Switching Service
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0290 New Schedule Legacy Data Item API V0.4
Archive
Off
Document title
R0290 Schedule 1 Defined Terms V0.2
Archive
Off
Document title
R0290 Schedule 9 Qualification and Maintenance v0.1
Archive
Off
Problem Statement
The risk of loss of certain Data Items for MHHS Migrated Metering Points may impact Parties in their ability to carry out and support industry processes, or in what products they are able to offer Consumers, in both the MHHS Market and following a Reverse Migration.
Stages Selection
SME
SME Role
Lead Technical Analyst
I0290 submission form
I0290 Change Report (Proposal Plan) V1.0
I0290 Extension to Plan V1.0 approved 27.03.26
I0290 Extension to Plan V2.0 approved 27.04.26
R0290 Change Report (For Consultation) v1.0
R0290 Consolidated Consultation Responses V1.0
Energy Consultants Association - letter on Change Report (Final Recommendation)
R0290 Change Report (Final Recommendation) v1.1 post vote 02.06.2026
Company Name
-
Review status
Review required

MHHS Related Metering Points across Market Segments

Date of latest update
Type
Issue
ID
I0275
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
06/11/2025 - Following discussions at the Change Issues Group on 06 November, a REC guidance will be developed to support the resolution of this Issue after which it will be classed as resolved.
Summary
It has been identified by the MHHS Data Cleanse Working Group (DCWG) that around 9,000 existing Metering Point Relationships include Metering Points that would migrate into different Market-wide Half Hourly Settlement (MHHS) Market Segments. The majority of these are where one Metering Point has a Traditional meter installed (Smart Segment) and a Related Metering Point has an Advanced meter (Advanced Segment). This situation is currently valid but in MHHS would cause two problems. - SMRS would not be able to align the agent appointments, leaving secondary MPANs without agents and MHHS Migrations unable to fully complete.
Proposer
jonny.moore_42
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
Without considering this Issue, there will be a risk to the MHHS migration. Indeed, a Metering Point installed which does not match its Related Metering Point (for example a Relationship between a Traditional meter with an Advanced Meter) will not be able to fully migrate to MHHS arrangements.
I0275 submission form
Company Name
-
Review status
Review required

Sharing of SSC and TPR Information for MHHS Smart and Advanced Meters

Date of latest update
Type
Issue
ID
I0273
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
23/06/2026 - The Code Manager has published an Interim Guidance Document for I0273.
Summary
In the MHHS design the Standard Settlement Configuration (SSC) is a non-mandatory data item for Smart and Advanced metering points, in addition the register level TPR information is not shared in the MTD flows for these meters (IF-006 for Smart and D0268 for Advanced). It was identified through BSC Issue I118 that there is a requirement for the SSC to be set for Domestic / Microbusiness Advanced Metering Points making use of the HH data opt out and there may be other areas where the SSC is required.
Proposer
jonny.moore_42
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
James Hardy
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0273 - Interim Guidance Document V1.1
Archive
Off
Problem Statement
The MHHS design does not mandate the use of SSC or support register-level TPR data for Smart and Advanced Meters, creating gaps in data availability for certain Settlement scenarios.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0273 Submission Form
I0273 - Update to Plan V2.0 (Pre-Approval) 06.05.2026
Company Name
-
Review status
Review required