Changes to Terms of reference following acceptance of R0167
Date of latest update
Type
Change
ID
R0188
Change Path
Urgent
No
Latest Update
20/08/2024 - Approved for implementation on 06/09/2024.
Summary
This Housekeeping Change Proposal seeks to update the Terms of Reference of the REC Change Panel and the Performance Assurance Board, following the acceptance of R0167, to reflect Issues.
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
06 September 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0003 | Market-wide Half-Hourly Settlement Implementation |
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
REC Change Panel - Terms of Reference
Archive
Off
Document title
REC Performance Assurance Board (PAB) - Terms of Reference
Archive
Off
Problem Statement
This Housekeeping Change Proposal seeks to update the Change Panel and Performance Assurance Board, Terms of Reference to reflect that these Committees consider change Issues as well as Change Proposals.
Stages Selection
R0188 - Change Proposal Form
R0188 - Housekeeping Change Report (Post Approval)
Company Name
Rec Manager
Review status
Review required
Removal of the Green Deal Panel
Date of latest update
Type
Change
ID
R0166
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
This Change Proposal seeks to remove the Green Deal Panel Terms of Reference from the REC Baseline Statement and product set, and to amend the Change Panel Terms of Reference to incorporate consideration of Green Deal business.
Change Plan
Preliminary Change Report Published
Completed
Start:
22 Apr 2024Due:
09 May 2024Completion:
09 May 2024Consultation Issued
Completed
Start:
09 May 2024Due:
09 May 2024Completion:
09 May 2024Final Change Report Issued
Completed
Start:
09 May 2024Due:
07 Jun 2024Completion:
07 Jun 2024Responsible Committee Decision
Completed
Start:
07 Jun 2024Due:
18 Jun 2024Completion:
18 Jun 2024Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
23 August 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0103 | Central provision of DCC Technical Contacts for requesting test certificates |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
- As a party I want Green Deal matters, should they arise to be dealt with in a timely fashion. This could be difficult under the current arrangements where it is not possible to get a quorate panel to make decisions.
Proposed Solution Document
Document title
REC Change Panel - Terms of Reference - Red-lined
Archive
Off
Problem Statement
Since the REC was established, no business has been raised that would require the Green Deal Panel to meet and therefore the group has not yet convened. As well as being an unnecessary administrative consideration, it is a challenge to keep the Members and Chair abreast of the wider REC Change Process, and the Green Deal Panel may therefore find it more challenging to discharge its functions in the event that it needs to be convened.
Stages Selection
Change Proposal Form
R0166 - Change Proposal Plan v1.0 (Approved)
R0166 - Initial Assessment Report (Approved)
R0166 - Preliminary Change Report V1.0
R0166 Final Change Report v1.0
Company Name
REC Code Manager
Review status
Review required
Clarifying Event of Default requirements
Date of latest update
Type
Change
ID
R0129
Priority
Urgent
No
Latest Update
04/10/2023 - Following the approval of R0138, this change has been withdrawn.
Summary
Following several recent events of non-payment for services and REC defaults it is clear that the event of default provisions in the Code are unclear. This change seeks to introduce clarity to the REC Main Body.
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
Stages Selection
R0129 - Change Proposal form (downloadable version) 16.06.2023
Company Name
REC Code Manager
Review status