Resolution of Bilateral Erroneous Transfers
Solution Analysis
Start:
18 Nov 2021Due:
21 Mar 2023Completion:
Proposed Approach Presented To Change Panel
Start:
21 Mar 2023Due:
18 Apr 2023Completion:
- As a Consumer, I want issues affecting me or my energy account to be resolved at the earliest opportunity, to minimise impacts to my energy switch or accurate and timely billing.
- As a Consumer, I want industry parties to share my personal data securely so that my data is protected.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I can bill my Consumers accurately and timely.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I supply Consumers with whom I have a valid contract.
Cable Colour Identification
Initial Assessment Report published
Start:
01 Nov 2021Due:
26 Nov 2021Completion:
26 Nov 2021Change Panel review
Start:
26 Nov 2021Due:
07 Dec 2021Completion:
07 Dec 2021Preliminary Change Report issued
Start:
07 Dec 2021Due:
04 Jan 2022Completion:
31 Dec 2021Metering Expert Panel review
Start:
04 Jan 2022Due:
12 Jan 2022Completion:
12 Jan 2022Consultation starts
Start:
12 Jan 2022Due:
17 Jan 2022Completion:
25 Jan 2022Consultation ends
Start:
17 Jan 2022Due:
15 Feb 2022Completion:
15 Feb 2022Final Change Report issued
Start:
15 Feb 2022Due:
25 Feb 2022Completion:
25 Feb 2022Metering Expert Panel decision
Start:
25 Feb 2022Due:
09 Mar 2022Completion:
09 Mar 202230 June 2022
- As an electricity Consumer, I want requested meter work to take place safely and efficiently at the time and date agreed, so that I have a safe and working meter.
- As a MEM or a DNO I want clarity on how to deal with cable labelling during periods of coloured cable supply chain shortages, so that I can continue to install or maintain consumer metering.
- As a Metering Scheme Auditor, I want there to be clarity on the permitted labelling of non-standard colour coded cables used when connecting meters, so that audits can be appropriately completed.
Electricity Enquiry Service API Service Status
Initial Assessment Report published
Start:
11 Oct 2021Due:
05 Nov 2021Completion:
05 Nov 2021Analysis and Solution development activity
Start:
05 Nov 2021Due:
13 Jan 2022Completion:
Service Provider Impact Assessment completion
Start:
13 Jan 2022Due:
15 Feb 2022Completion:
REC Party Impact Assessment completion
Start:
15 Feb 2022Due:
23 Mar 2022Completion:
Preliminary Change Report issued
Start:
23 Mar 2022Due:
20 Apr 2022Completion:
Technical Expert Panel review
Start:
20 Apr 2022Due:
27 Apr 2022Completion:
Consultation starts
Start:
27 Apr 2022Due:
05 May 2022Completion:
Consultation ends
Start:
05 May 2022Due:
26 May 2022Completion:
Final Change Report issued
Start:
26 May 2022Due:
21 Jun 2022Completion:
Technical Expert Panel decision
Start:
21 Jun 2022Due:
29 Jun 2022Completion:
- As an EES User (organisation), I want a method of integrating the service status of the EES API with my systems, so that in the event of EES API outage or disruption I do not trigger unnecessary internal diagnostic activity of my IT systems and processes, and I can initiate appropriate mitigation activity to reduce impacts to my systems and/or the services I provide.
Reporting of Additional EMR Backing Data to Suppliers
Initial Assessment Report published
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
12 Nov 2021Completion:
12 Nov 2021Technical Expert Panel review
Start:
12 Nov 2021Due:
24 Nov 2021Completion:
24 Nov 2021Consultation starts
Start:
24 Nov 2021Due:
30 Nov 2021Completion:
29 Nov 2021Consultation ends
Start:
30 Nov 2021Due:
21 Dec 2021Completion:
21 Jan 2022Final Change Report issued
Start:
21 Dec 2021Due:
14 Jan 2022Completion:
14 Jan 2022Technical Expert Panel decision
Start:
14 Jan 2022Due:
26 Jan 2022Completion:
26 Jan 202230 June 2023
- As a Market Participant, I need to be able to validate EMRS invoices and credits without having to request additional supporting data.
- As EMR Settlement Ltd, I need to have an efficient mechanism in place that enables me to provide Market Participants with all the relevant data that they need to validate their invoices and credit notes, to reduce/remove the need for Market Participants to contact the service desk for additional information.
New Meter Types for Auxiliary Proportional Controllers (APCs)
Change Panel review
Start:
08 Sep 2021Due:
19 Oct 2021Completion:
19 Oct 2021Analysis and Solution development activity
Start:
19 Oct 2021Due:
30 Dec 2021Completion:
30 Dec 2021Alternative Change Proposal decision point
Start:
30 Dec 2021Due:
31 Dec 2021Completion:
31 Dec 2021Service Provider Impact Assessment completion
Start:
31 Dec 2021Due:
21 Apr 2022Completion:
21 Apr 2022REC Party Impact Assessment completion
Start:
21 Apr 2022Due:
23 May 2022Completion:
28 Mar 2022Preliminary Change Report issued
Start:
23 May 2022Due:
27 Jun 2022Completion:
27 Jun 2022Technical Expert Panel review
Start:
27 Jun 2022Due:
05 Jul 2022Completion:
30 Jun 2022Consultation starts
Start:
05 Jul 2022Due:
12 Jul 2022Completion:
01 Jul 2022Consultation ends
Start:
12 Jul 2022Due:
26 Jul 2022Completion:
22 Jul 2022Final Change Report issued
Start:
26 Jul 2022Due:
22 Aug 2022Completion:
19 Aug 2022Technical Expert Panel decision
Start:
22 Aug 2022Due:
31 Aug 2022Completion:
31 Aug 202230 June 2023
- As an Energy Consumer, I want to be quoted the correct rates as part of my contract conversation when switching supplier. I want my meter set-up correctly to be able to utilise secondary electricity loads at specific times for specific purposes. (e.g., overnight Electric Vehicle (EV) charging, Heat/Hot Water, Boost, etc.). I want to be assured that I will have access to electricity when I need it. I want to switch to my chosen Supplier without any delays or issues.
- As an Energy Supplier, I need to identify meter types with Auxiliary Proportional Controllers (APCs) at a property, so that I can offer my customer the correct tariff and configure their meter correctly.
- As a Meter Equipment Manager (MEM), I need to identify meter types that incorporate Auxiliary Proportional Controllers (APCs) are present at a property, so that any necessary maintenance/repair work can be carried out appropriately.
Introduction of SDEP and EES User Maintenance API
Initial Assessment Report published
Start:
08 Sep 2021Due:
25 Oct 2021Completion:
25 Oct 2021Analysis and Solution Development activity
Start:
25 Oct 2021Due:
15 Feb 2022Completion:
15 Feb 2022Service Provider Impact Assessment completion
Start:
15 Feb 2022Due:
04 Apr 2022Completion:
04 Apr 2022Preliminary Change Report issued
Start:
13 May 2022Due:
16 Dec 2022Completion:
16 Dec 2022Technical Expert Panel review
Start:
16 Dec 2022Due:
21 Dec 2022Completion:
21 Dec 2022Consultation Starts
Start:
21 Dec 2022Due:
23 Dec 2022Completion:
23 Dec 2022Consultation Ends
Start:
23 Dec 2022Due:
27 Jan 2023Completion:
27 Jan 2023Final Change Report issued
Start:
27 Jan 2023Due:
10 Feb 2023Completion:
10 Feb 2023Appeal Window Closure
Start:
22 Feb 2023Due:
15 Mar 2023Completion:
15 Mar 2023Party Impact Assessment Issued
Start:
04 Apr 2022Due:
13 May 2022Completion:
13 May 2022Technical Expert Panel review
Start:
10 Feb 2023Due:
22 Feb 2023Completion:
22 Feb 2023- As a consumer, I want to ensure the data held by my supplier and other industry parties is correct so that I receive accurate and timely bills so that I understand what I need to pay and by when with no surprises.
- As a consumer, I want to be able to switch my energy supply without experiencing significant delays whilst my new and old supplier resolve any issues. So that I can see the benefits of switching at the earliest opportunity.
- As an SDEP User, I want to be able to automate processes that use the SDEP, so I can meet my obligations as efficiently and effectively as possible. As an EES or SDES User, I want to be able to automate certain user maintenance requests, so I can manage user maintenance activities as efficiently as possible.
Changes to message ownership in SDEP
Initial Assessment Report published
Start:
08 Sep 2021Due:
25 Oct 2021Completion:
25 Oct 2021Change Panel review
Start:
25 Oct 2021Due:
02 Nov 2021Completion:
02 Nov 2021Analysis and Solution Development activity
Start:
02 Nov 2021Due:
21 Dec 2021Completion:
Service Provider Impact Assessment completion
Start:
21 Dec 2021Due:
02 Feb 2022Completion:
REC Party Impact Assessment completion
Start:
02 Feb 2022Due:
18 Mar 2022Completion:
Preliminary Change Report issued
Start:
18 Mar 2022Due:
16 May 2022Completion:
Technical Expert Panel review
Start:
15 Jul 2022Due:
27 Jul 2022Completion:
Consultation Starts
Start:
16 May 2022Due:
26 May 2022Completion:
Consultation ends
Start:
26 May 2022Due:
20 Jun 2022Completion:
Final Change Report issued
Start:
20 Jun 2022Due:
15 Jul 2022Completion:
Technical Expert Panel decision
Start:
27 Jul 2022Due:
27 Jul 2022Completion:
Appeal Window Closure
Start:
27 Jul 2022Due:
17 Aug 2022Completion:
- As a consumer, I want issues affecting me or my energy account to be resolved at the earliest opportunity, to minimise impacts to my energy switch or accurate and timely billing.
- As a SDEP Authorised Person with the responsibility for message allocation, I want to efficiently assign multiple messages in one transaction to an Authorised Person, to remove the need to manual assign them one by one.
- As a SDEP Authorised Person with the responsibility for message allocation, I want to be able to filter messages to identify messages requiring action. This will ensure messages are picked up promptly and resolved within the agreed Service Level Agreement (SLA).
Missing Meter Technical Details
Initial Assessment Report published
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Updated Change Proposal Plan presented to Change Panel
Start:
19 Oct 2021Due:
04 Oct 2022Completion:
04 Oct 2022Solution Development
Start:
04 Oct 2022Due:
05 Oct 2022Completion:
08 Jan 2023Updated plan Presented to Change Panel
Start:
05 Oct 2022Due:
06 Dec 2022Completion:
06 Dec 2022Service Provider Impact Assessment
Start:
06 Dec 2022Due:
09 Jan 2023Completion:
Party Impact Assessment
Start:
09 Jan 2023Due:
03 Feb 2023Completion:
24 Feb 2023Preliminary Change Report Issued
Start:
03 Feb 2023Due:
28 Apr 2023Completion:
Responsible Committee Review
Start:
28 Apr 2023Due:
10 May 2023Completion:
Consultation Issued
Start:
10 May 2023Due:
12 May 2023Completion:
Final Change Report Issued
Start:
12 May 2023Due:
30 Jun 2023Completion:
Responsible Committee Decision
Start:
30 Jun 2023Due:
12 Jul 2023Completion:
- As a Consumer: I want my new Supplier to set up my account in a timely manner, ensuring that I receive timely and accurate bills. I want to my meter to be read regularly to ensure I receive accurate bills I want to receive my final invoice from my old Supplier in a timely manner
- As a Losing Supplier I want to agree a closing meter reading to allow me to produce a final invoice and collect any outstanding payments
- As a Gaining Supplier I want to set up the energy account correctly for the consumer, receive an opening reading and produce a timely first invoice As a Gaining Supplier’s MEM I want to receive the MTD to enable me to update my data and trigger the necessary Market Messages to the new Supplier, new DC and DNO As a new Data Collector I want to receive the MTD to enable me to set up the correct meter reading schedule and collect meter readings.
Electricity Enquiry Service (EES) Master Administration User (MAU) Access
Initial Assessment Report published
Start:
03 Sep 2021Due:
21 Oct 2021Completion:
21 Oct 2021Change Panel review
Start:
21 Oct 2021Due:
02 Nov 2021Completion:
02 Nov 2021Analysis and Solution development activity
Start:
02 Nov 2021Due:
13 Jan 2022Completion:
Service Provider Impact Assessment completion
Start:
29 Mar 2022Due:
31 Mar 2022Completion:
REC Party Impact Assessment completion
Start:
13 Jan 2022Due:
29 Mar 2022Completion:
Preliminary Change Report issued
Start:
31 Mar 2022Due:
20 Apr 2022Completion:
Technical Expert Panel review
Start:
20 Apr 2022Due:
27 Apr 2022Completion:
Consultation starts
Start:
27 Apr 2022Due:
05 May 2022Completion:
Consultation ends
Start:
05 May 2022Due:
26 May 2022Completion:
Final Change Report issued
Start:
29 Jun 2022Due:
21 Sep 2022Completion:
Technical Expert Panel decision
Start:
26 May 2022Due:
29 Jun 2022Completion:
- As a consumer, I want to my queries to be resolved in a timely manner by advisers with access to relevant information, so that I receive accurate and timely bills.
- As an EES User (an organisation): I want to receive reports of Meter Point Limit Breaches in the absence of the MAU, to enable the analysis of EES usage and to enable limit breaches to be identified and responded to. I also want all approved people to have access to the EES in a timely manner following the introduction of a new email domain, so that the EES can be used to support with issue and query resolution.
- As an MAU, I want email domain changes to be validated in my absence, to avoid delays to new users being set up with EES access.