Removal of CSS Business Rule 1177 to reflect OFAF optionality
Preliminary Change Report and Consultation Issued
Start:
16 Jun 2023Due:
28 Jul 2023Completion:
27 Jul 2023Consultation Closed
Start:
28 Jul 2023Due:
18 Aug 2023Completion:
18 Aug 2023Final Change Report published
Start:
18 Aug 2023Due:
08 Sep 2023Completion:
08 Sep 2023Responsible Committee Decision
Start:
08 Sep 2023Due:
27 Sep 2023Completion:
15 Sep 2023Appeal Window Closed
Start:
27 Sep 2023Due:
02 Oct 2023Completion:
02 Oct 202306 December 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0106 | Performance Assurance Report Catalogue V5.1 |
- As the Code Manager, I want the REC to reflect the intended design and align to the CSS functionality so that I do not need to operate a workaround As the Switching Operator, I want the REC Data Specification to reflect the functionality as designed so that my obligations are clear
- As an Energy Supplier, I want the SOD, relating to my Market Participant Identifier/s (MPIDs), to accurately record my OFAF reference so that my OFAF qualification status is clearly understood
Search GES API using Meter Serial Number
Service Provider Impact Assessment start
Start:
18 May 2023Due:
04 Apr 2024Completion:
04 Apr 2024Service Provider Impact Assessment close
Start:
04 Apr 2024Due:
21 Jun 2024Completion:
18 Jun 2024Party Impact Assessment start
Start:
21 Jun 2024Due:
28 Jun 2024Completion:
28 Jun 2024Party Impact Assessment close
Start:
28 Jun 2024Due:
19 Jul 2024Completion:
19 Jul 2024Preliminary Change Report and Consultation published
Start:
19 Jul 2024Due:
26 Jul 2024Completion:
26 Jul 2024Consultation close
Start:
26 Jul 2024Due:
16 Aug 2024Completion:
16 Aug 2024Final Change Report published
Start:
16 Aug 2024Due:
20 Aug 2024Completion:
20 Aug 2024Responsible Committee Decision
Start:
20 Aug 2024Due:
28 Aug 2024Completion:
28 Aug 202428 February 2025
Annulment Definition
Preliminary Change Report and Consultation Issued
Start:
17 May 2023Due:
31 May 2024Completion:
31 May 2024Final Change Report Issued
Start:
31 May 2024Due:
05 Jul 2024Completion:
05 Jul 2024Responsible Committee Decision
Start:
05 Jul 2024Due:
16 Jul 2024Completion:
Authority Determination Requested
Start:
16 Jul 2024Due:
17 Jul 2024Completion:
08 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
TPI access to the Meter Asset Manager data via the GES
Housekeeping amendments
Publish Housekeeping Change Report
Start:
20 Apr 2023Due:
09 May 2023Completion:
09 May 2023Responsible Committee Decision
Start:
09 May 2023Due:
16 May 2023Completion:
16 May 202330 June 2023
- As a REC Party, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Supplier compensation for Network Party driven MPXN or GSP Group changes
A review of Supplier access to data on GES
Service Provider Impact Assessment Due
Start:
19 Apr 2023Due:
07 Sep 2023Completion:
07 Sep 2023Preliminary Change Report Issued
Start:
07 Sep 2023Due:
20 Sep 2023Completion:
20 Sep 2023Responsible Committee Review
Start:
20 Sep 2023Due:
27 Sep 2023Completion:
27 Sep 2023Consultation Issued
Start:
27 Sep 2023Due:
27 Sep 2023Completion:
11 Oct 2023Final Change Report Issued
Start:
27 Sep 2023Due:
18 Oct 2023Completion:
18 Oct 2023Responsible Committee Decision
Start:
18 Oct 2023Due:
25 Oct 2023Completion:
25 Oct 202303 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0104 | Clarifying requirement for continuous billing following an Erroneous Switch |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 08 Jun 2026 | ||
| 1.0 | 08 Jun 2026 |
- As a Consumer, I want my Supplier to be able to access essential information about my energy account, so that billing issues and switching problems can be addressed easily.
- As a Registered Gas Supplier, I want to be able to readily access appropriate information relating to my RMP portfolio, so that I can resolve consumer facing billing issues more easily. As the GES Provider, I want my users to be able to access information that helps them fulfil their objectives (in line with REC Data Access principles), so that the service is used as efficiently as possible.
Enabling Electricity Enquiry Service searches using a Unique Property Reference Number
Service Provider Impact Assessment window start
Start:
19 Apr 2023Due:
02 Oct 2023Completion:
02 Oct 2023Service Provider Impact Assessment window close
Start:
02 Oct 2023Due:
18 Dec 2023Completion:
18 Dec 2023Party Impact Assessment start
Start:
18 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As I Consumer, I want to be able to quote or switch my electricity as part of a packaged search.
- As a Supplier, I want Consumers to be able to search for quotes and switch efficiently.
- As an organisation providing multi-channel switching services, I want Consumers to be able to use one set of data when requesting quotes.
CSS Message Time Stamping
Test
Start:
14 Apr 2023Due:
19 Mar 2026Completion:
19 Mar 2026Review of ONAGE SLAs
Solution Development Closes
Start:
06 Apr 2023Due:
31 May 2024Completion:
31 May 2024Party Impact Assessment Published
Start:
31 May 2024Due:
04 Jul 2024Completion:
04 Jul 2024Preliminary Change Report & Consultation Published
Start:
04 Jul 2024Due:
08 Aug 2024Completion:
08 Aug 2024Final Change Report Published
Start:
08 Aug 2024Due:
04 Sep 2024Completion:
Responsible Committee Decision
Start:
04 Sep 2024Due:
11 Sep 2024Completion:
Appeal Window Closure
Start:
11 Sep 2024Due:
25 Sep 2024Completion:
- As a Consumer, I want to have continual Meter Equipment Manager coverage, so that I am confident that work on my Metering Asset can be conducted even during a Switch.
- As a MEM, I want my obligations relating to appointment and de-appointment to be considered and practicable, so that my operational processes are not unduly onerous. 2 - As a Gas Supplier, I want to be able to reliably and predictably appoint and de-appoint MEMs during a Switch, so that I am confident that my Consumers are not left without a MEM at any stage. 3 - As the Code Manager, I want REC processes to operate within SLAs that are reflective of both the realistic operational capacities of REC Parties, and also of the needs of the broader market, so that the end Consumer has the best possible Switching experience.