Search GES API using Meter Serial Number
Service Provider Impact Assessment start
Start:
18 May 2023Due:
04 Apr 2024Completion:
04 Apr 2024Service Provider Impact Assessment close
Start:
04 Apr 2024Due:
21 Jun 2024Completion:
18 Jun 2024Party Impact Assessment start
Start:
21 Jun 2024Due:
28 Jun 2024Completion:
28 Jun 2024Party Impact Assessment close
Start:
28 Jun 2024Due:
19 Jul 2024Completion:
19 Jul 2024Preliminary Change Report and Consultation published
Start:
19 Jul 2024Due:
26 Jul 2024Completion:
26 Jul 2024Consultation close
Start:
26 Jul 2024Due:
16 Aug 2024Completion:
16 Aug 2024Final Change Report published
Start:
16 Aug 2024Due:
20 Aug 2024Completion:
20 Aug 2024Responsible Committee Decision
Start:
20 Aug 2024Due:
28 Aug 2024Completion:
28 Aug 202428 February 2025
Annulment Definition
Preliminary Change Report and Consultation Issued
Start:
17 May 2023Due:
31 May 2024Completion:
31 May 2024Final Change Report Issued
Start:
31 May 2024Due:
05 Jul 2024Completion:
05 Jul 2024Responsible Committee Decision
Start:
05 Jul 2024Due:
16 Jul 2024Completion:
Authority Determination Requested
Start:
16 Jul 2024Due:
17 Jul 2024Completion:
08 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
TPI access to the Meter Asset Manager data via the GES
Housekeeping amendments
Publish Housekeeping Change Report
Start:
20 Apr 2023Due:
09 May 2023Completion:
09 May 2023Responsible Committee Decision
Start:
09 May 2023Due:
16 May 2023Completion:
16 May 202330 June 2023
- As a REC Party, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Supplier compensation for Network Party driven MPXN or GSP Group changes
Provision of Grid Supply Point Group ID from a Postcode search in EES
A review of Supplier access to data on GES
Service Provider Impact Assessment Due
Start:
19 Apr 2023Due:
07 Sep 2023Completion:
07 Sep 2023Preliminary Change Report Issued
Start:
07 Sep 2023Due:
20 Sep 2023Completion:
20 Sep 2023Responsible Committee Review
Start:
20 Sep 2023Due:
27 Sep 2023Completion:
27 Sep 2023Consultation Issued
Start:
27 Sep 2023Due:
27 Sep 2023Completion:
11 Oct 2023Final Change Report Issued
Start:
27 Sep 2023Due:
18 Oct 2023Completion:
18 Oct 2023Responsible Committee Decision
Start:
18 Oct 2023Due:
25 Oct 2023Completion:
25 Oct 202303 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0104 | Clarifying requirement for continuous billing following an Erroneous Switch |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 08 Jun 2026 | ||
| 1.0 | 08 Jun 2026 |
- As a Consumer, I want my Supplier to be able to access essential information about my energy account, so that billing issues and switching problems can be addressed easily.
- As a Registered Gas Supplier, I want to be able to readily access appropriate information relating to my RMP portfolio, so that I can resolve consumer facing billing issues more easily. As the GES Provider, I want my users to be able to access information that helps them fulfil their objectives (in line with REC Data Access principles), so that the service is used as efficiently as possible.
Enabling Electricity Enquiry Service searches using a Unique Property Reference Number
Service Provider Impact Assessment window start
Start:
19 Apr 2023Due:
02 Oct 2023Completion:
02 Oct 2023Service Provider Impact Assessment window close
Start:
02 Oct 2023Due:
18 Dec 2023Completion:
18 Dec 2023Party Impact Assessment start
Start:
18 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As I Consumer, I want to be able to quote or switch my electricity as part of a packaged search.
- As a Supplier, I want Consumers to be able to search for quotes and switch efficiently.
- As an organisation providing multi-channel switching services, I want Consumers to be able to use one set of data when requesting quotes.
CSS Message Time Stamping
Test
Start:
14 Apr 2023Due:
19 Mar 2026Completion:
19 Mar 2026Revision of the Implementation Date and approved solution for R0021
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Responsible Committee Review Completed
Start:
31 Mar 2023Due:
27 Apr 2023Completion:
27 Apr 2023Consultation Started
Start:
27 Apr 2023Due:
28 Apr 2023Completion:
28 Apr 2023Consultation Ended
Start:
28 Apr 2023Due:
16 May 2023Completion:
16 May 2023Final Change Report Issued
Start:
16 May 2023Due:
19 May 2023Completion:
19 May 2023Responsible Committee Recommendation
Start:
19 May 2023Due:
26 May 2023Completion:
26 May 202330 June 2023
- As a premise owner I want to be able to contract with a Safe Isolator Provider (SIP), and for the SIP to be able to provide the service in a fully compliant manner.
- As a REC MEM who wants to operate as SIP, I need clarity on the solution and Market Message requirements when I provide Safe Isolation Works to Premise Owners. As a Registered Supplier, I need clarity on the solution and Market Message requirements when my consumers have Safe Isolation Works completed at their Premise Owners by SIPs.
- As a Distribution Network Operator, I need clarity on the solution and Market Message requirements when my connected parties have Safe Isolation Works completed at their Premise Owners by SIPs.