Removal of Facsimile as a Method of Code Communication
Preliminary Change Report and Consultation Issued
Start:
03 Jan 2024Due:
09 Feb 2024Completion:
09 Feb 2024Final Change Report Issued
Start:
23 Feb 2024Due:
12 Mar 2024Completion:
12 Mar 2024Responsible Committee Decision
Start:
12 Mar 2024Due:
19 Mar 2024Completion:
19 Mar 2024Appeal Window Closure
Start:
19 Mar 2024Due:
02 Apr 2024Completion:
Consultation Close
Start:
09 Feb 2024Due:
23 Feb 2024Completion:
23 Feb 202407 November 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0003 | Market-wide Half-Hourly Settlement Implementation |
- All communication methods referencing fax or facsimile will need to be removed and replaced with email
Allowing different Metering Equipment Managers (MEMs) to be appointed to Import and Export Metering Points
- As a Consumer, I want a competitive Export market so I can get the best rates for the energy I generate. I want clear metering equipment ownership so I can be confident my meter is functional and safe. I want accurate billing from my Export Supplier.
- As an Export Supplier, I want to be able to appoint the MEM that ties in with my commercial strategy.
- As a MEM, I want clear guidance on the responsibilities I have for any metering equipment I am appointed to.
Revision of the approved solution for R0032
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Service Provider Impact Assessment Complete
Start:
31 Mar 2023Due:
11 Apr 2023Completion:
11 Apr 2023Party Impact Assessment Completed
Start:
11 Apr 2023Due:
11 Apr 2023Completion:
11 Apr 2023Preliminary Change Report Published for Consultation
Start:
11 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation Start
Start:
14 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation End
Start:
14 Apr 2023Due:
21 Apr 2023Completion:
21 Apr 2023Final Change Report Published
Start:
21 Apr 2023Due:
24 Apr 2023Completion:
24 Apr 2023Responsible Committee Discussion
Start:
24 Apr 2023Due:
26 Apr 2023Completion:
Appeal Window Closure
Start:
26 Apr 2023Due:
12 May 2023Completion:
30 June 2023
- As an impacted Market Participant, I want to have clarity on version of the Market Message and the population of Data Items within the Data Specification, so that my internal systems can be correctly configured to send and receive Data Items within Market Messages.
Changes to allow DNOs to reinstate disconnected MPANs
- As a Consumer, I do not want the erroneous disconnection of my MPAN to affect the continuity of my supply contract and billing arrangements.
- As a DNO, I want to be able to reverse erroneous disconnections with no lasting effect so that I don’t need to create a new MPAN to resolve the issue, thereby avoiding DUoS payment collection issues. 2 - As a Supplier, I want to be able to reverse erroneous disconnections with no lasting effect so that I can correctly bill my consumers. 3 - As the CSS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate. 4 - As MPRS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate.
Enabling Software Product Qualification
Creating a Meter Operator Agent and MOCoP Installer
Solution analysis and development
Start:
22 Aug 2022Due:
14 Jul 2023Completion:
13 Jul 2023Service Impact assessment commenced
Start:
14 Jul 2023Due:
14 Jul 2023Completion:
14 Jul 2023Impact Assessment Period Ended
Start:
09 Oct 2023Due:
03 Nov 2023Completion:
03 Nov 2023Preliminary Change Report issued
Start:
03 Nov 2023Due:
24 Nov 2023Completion:
24 Nov 2023Consultation issued
Start:
24 Nov 2023Due:
07 Dec 2023Completion:
07 Dec 2023Final Change report issued
Start:
07 Dec 2023Due:
26 Jan 2024Completion:
26 Jan 2024REC Change Panel decision
Start:
26 Jan 2024Due:
06 Feb 2024Completion:
06 Feb 2024Appeal Window closed
Start:
06 Feb 2024Due:
20 Feb 2024Completion:
20 Feb 2024Draft Legal Text Changes (Including Legal Review)
Start:
11 Aug 2023Due:
15 Sep 2023Completion:
15 Sep 2023Service Provider Impact Assessment Completed
Start:
14 Jul 2023Due:
11 Aug 2023Completion:
11 Aug 2023Impact Assessment Period Started
Start:
15 Sep 2023Due:
09 Oct 2023Completion:
06 Oct 202328 June 2024
- As an electricity MEM, I want to be clear on the obligations I need to meet, based on the type of metering activity I complete. I want to meet my obligations efficiently and effectively and without the need to seek additional input/advice from the Code Manager.
- As the Code Manager, I want to be able to differentiate between electricity MEMs based on the type of activity they are responsible for and their interaction with central systems, so that I can engage appropriately. I need to be clear on the obligations that each MEM should be meeting and the performance reporting that should be provided.
Resolution of invalid CSS data by Data Owners
Solution Analysis and Development
Start:
22 Aug 2022Due:
15 Aug 2023Completion:
15 Aug 2023Service Provider Impact Assessment Due
Start:
15 Aug 2023Due:
19 Oct 2023Completion:
19 Oct 2023- As a Consumer, I want data relating to my energy supply to be accurate, so that I can have a consistent and faultless switching experience. As a Consumer, I want any data issues related to my switch to be resolved quickly and by the party responsible, to ensure a fast and efficient switching experience.
- As a DNO, I want my service level requirements to be reflective of my data ownership responsibilities, so that data queries can be resolved more efficiently. As the CSS Service Desk provider, I want my tickets to be allocated to the most appropriate party able to resolve them.
MHHS Programme Changes required to Central Switching Service
Analysis and Requirements Gathering started
Start:
29 Apr 2022Due:
05 May 2022Completion:
05 May 2022Present Updated Change Proposal Plan to REC Change Panel
Start:
05 May 2022Due:
21 Jun 2022Completion:
21 Jun 2022Service Provider Impact Assessment initiated
Start:
21 Jun 2022Due:
11 Jul 2022Completion:
05 Jul 2022Service Provider Impact Assessment completed
Start:
11 Jul 2022Due:
15 Aug 2022Completion:
10 Aug 2022Present extended Change Proposal Plan to Change Panel
Start:
15 Aug 2022Due:
06 Sep 2022Completion:
06 Sep 2022Requirement refinement and validation of Detailed Impact Assessment
Start:
06 Sep 2022Due:
27 Sep 2022Completion:
27 Sep 2022Provide extended Change Proposal Plan to Change Panel
Start:
28 Oct 2022Due:
31 Oct 2022Completion:
25 Oct 2022Preliminary Change Report Issued
Start:
27 Sep 2022Due:
28 Oct 2022Completion:
27 Oct 2022Responsible Committee Review of the Preliminary Change Report
Start:
31 Oct 2022Due:
01 Nov 2022Completion:
01 Nov 2022Consultation started
Start:
01 Nov 2022Due:
04 Nov 2022Completion:
03 Nov 2022Consultation ended
Start:
04 Nov 2022Due:
25 Nov 2022Completion:
25 Nov 2022Final Change Report issued
Start:
25 Nov 2022Due:
09 Dec 2022Completion:
09 Dec 2022Responsible Committee ex-committee decision
Start:
09 Dec 2022Due:
13 Dec 2022Completion:
13 Dec 2022Authority Determination
Start:
13 Dec 2022Due:
02 Feb 2023Completion:
02 Feb 2023MHHS Programme Milestone M8 (Code changes delivered)
- As the SMDSP, I want to be able to validate that an SMDR is registered so that I can provide them with access to the Metering Points to which they are registered.
- As a SMDR, I want to be able to access the Metering Points I am registered to so that I can collect settlement data from those meters
- As the CSS Provider, I want the CSS to be able to receive notifications from the Registration Service on the appointment/de-appointment of an SMDR so that I can send the appointment data to the SMDSP. As the CSS Provider, I want the CSS to be able to provide SMDR appointment data to the SMDSP.
Revised Implementation Date for R0011
Party Impact Assessment Issued
Start:
25 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 2022Preliminary Change Report Issued
Start:
08 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Consultation Issued
Start:
29 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Final Change Report Issued
Start:
29 Apr 2022Due:
13 May 2022Completion:
13 May 2022Responsible Committee Decision
Start:
13 May 2022Due:
17 May 2022Completion:
17 May 202201 June 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0102 | Revision of the approved solution for R0032 |
- As a Market Participant, I need the industry Market Message/Data Specification to be implemented by all Parties at the same time so that I am able to validate EMRS invoices and credits without having to request additional supporting data or without my Market Messages failing.
- As LCCC I need to delay the implementation of R0011 so that changes to industry Market Message/Data Specification can be implemented by all Parties at the same time so that industry Market Messages don’t fail validation between Parties.
Invalid Requests for Site Technical Details
03 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0104 | Clarifying requirement for continuous billing following an Erroneous Switch |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 08 Jun 2026 | ||
| 1.0 | 08 Jun 2026 |
- As a Consumer I want my existing or new meter to be read regularly to ensure I receive accurate bills.
- As a Distribution Network Operator I want to receive appropriate Requests for Site Technical Details. As a Distribution Network Operator I want the difference between my obligations and best practice to be clear in relation to provision of Site Technical Details for sites with and without Measurement Transformers.
- As a Metering Equipment Manager I want to be provided with Site Technical Details for all relevant sites so I can correctly install, commission and maintain the Metering Equipment.