Review of Schedule 12 and processes to manage access to data
Preliminary Change Report issued
Start:
12 May 2023Due:
08 Sep 2023Completion:
08 Sep 2023Consultation triggered
Start:
08 Sep 2023Due:
08 Sep 2023Completion:
08 Sep 2023Consultation close
Start:
08 Sep 2023Due:
22 Sep 2023Completion:
22 Sep 2023Final Change Report issued
Start:
22 Sep 2023Due:
06 Oct 2023Completion:
06 Oct 2023Responsible Committee decision
Start:
06 Oct 2023Due:
17 Oct 2023Completion:
17 Oct 202306 December 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0106 | Performance Assurance Report Catalogue V5.1 |
- As a Consumer, I want Market Participants to have the appropriate data access so any issues affecting my energy account can be addressed easily.
- As a Consumer, I want Market Participants to have appropriate data access so that I can benefit from improved product and service offerings.
- As a Market Participant, I want the processes that grant data access to be simplified and adaptable so that valid data use cases are addressed quickly.
Frequency and content of CSS reports on switching via the DCC portal
Preliminary Change Report published
Start:
27 Apr 2023Due:
15 Dec 2023Completion:
15 Dec 2023Consultation issued
Start:
15 Dec 2023Due:
15 Dec 2023Completion:
15 Dec 2023Consultation close
Start:
15 Dec 2023Due:
19 Jan 2024Completion:
19 Jan 2024Final Change Report published
Start:
19 Jan 2024Due:
26 Jan 2024Completion:
26 Jan 2024Responsible Committee Decision
Start:
26 Jan 2024Due:
06 Feb 2024Completion:
06 Feb 2024Send to Authority for determination
Start:
06 Feb 2024Due:
07 Feb 2024Completion:
08 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want Ofgem to effectively monitor the market to ensure the right policy decisions are made.
- As Ofgem, I need accurate and timely data to ensure that I can make informed decisions on any interventions in relation to market stability.
Housekeeping amendments
Publish Housekeeping Change Report
Start:
20 Apr 2023Due:
09 May 2023Completion:
09 May 2023Responsible Committee Decision
Start:
09 May 2023Due:
16 May 2023Completion:
16 May 202330 June 2023
- As a REC Party, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Data Specification updates and clarifications
PRELIMINARY CHANGE REPORT AND CONSULTATION ISSUED
Start:
20 Apr 2023Due:
24 May 2024Completion:
24 May 2024FINAL CHANGE REPORT ISSUED
Start:
24 May 2024Due:
24 Jul 2024Completion:
19 Jul 2024RESPONSIBLE COMMITTEE DECISION
Start:
24 Jul 2024Due:
31 Jul 2024Completion:
31 Jul 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Market Participant, I need the Data Specification to be clear and correct to ensure my systems are set-up appropriately and Market Messages are correctly defined.
- As a Market Participant, I need to understand any changes to the Data Specification that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
A review of Supplier access to data on GES
Service Provider Impact Assessment Due
Start:
19 Apr 2023Due:
07 Sep 2023Completion:
07 Sep 2023Preliminary Change Report Issued
Start:
07 Sep 2023Due:
20 Sep 2023Completion:
20 Sep 2023Responsible Committee Review
Start:
20 Sep 2023Due:
27 Sep 2023Completion:
27 Sep 2023Consultation Issued
Start:
27 Sep 2023Due:
27 Sep 2023Completion:
11 Oct 2023Final Change Report Issued
Start:
27 Sep 2023Due:
18 Oct 2023Completion:
18 Oct 2023Responsible Committee Decision
Start:
18 Oct 2023Due:
25 Oct 2023Completion:
25 Oct 202303 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0104 | Clarifying requirement for continuous billing following an Erroneous Switch |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 08 Jun 2026 | ||
| 1.0 | 08 Jun 2026 |
- As a Consumer, I want my Supplier to be able to access essential information about my energy account, so that billing issues and switching problems can be addressed easily.
- As a Registered Gas Supplier, I want to be able to readily access appropriate information relating to my RMP portfolio, so that I can resolve consumer facing billing issues more easily. As the GES Provider, I want my users to be able to access information that helps them fulfil their objectives (in line with REC Data Access principles), so that the service is used as efficiently as possible.
Enabling Electricity Enquiry Service searches using a Unique Property Reference Number
Service Provider Impact Assessment window start
Start:
19 Apr 2023Due:
02 Oct 2023Completion:
02 Oct 2023Service Provider Impact Assessment window close
Start:
02 Oct 2023Due:
18 Dec 2023Completion:
18 Dec 2023Party Impact Assessment start
Start:
18 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As I Consumer, I want to be able to quote or switch my electricity as part of a packaged search.
- As a Supplier, I want Consumers to be able to search for quotes and switch efficiently.
- As an organisation providing multi-channel switching services, I want Consumers to be able to use one set of data when requesting quotes.
Central provision of DCC Technical Contacts for requesting test certificates
Impact Assessment period - start date
Start:
23 Mar 2023Due:
19 May 2023Completion:
19 May 2023Impact Assessment period - end date
Start:
19 May 2023Due:
28 Jul 2023Completion:
28 Jul 2023Preliminary Change Report issued and consultation started
Start:
28 Jul 2023Due:
11 Aug 2023Completion:
11 Aug 2023Consultation end date
Start:
11 Aug 2023Due:
04 Sep 2023Completion:
04 Sep 2023Final Change Report issued
Start:
04 Sep 2023Due:
15 Sep 2023Completion:
08 Sep 2023Responsible Committee decision
Start:
15 Sep 2023Due:
22 Sep 2023Completion:
19 Sep 202323 February 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As the SO, I want sufficient simulators to be available in the test environments, so that I can test changes to CSS systems for all necessary scenarios
- As a CSS User, I want changes to the CSS systems to be robustly tested, so that implemented changes align to their design and deliver the planned benefits
- As a CSS User, I want to be able to manage my Technical Contacts, so that I am in control of my responsibilities under the REC
Revision of the approved solution for R0032
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Service Provider Impact Assessment Complete
Start:
31 Mar 2023Due:
11 Apr 2023Completion:
11 Apr 2023Party Impact Assessment Completed
Start:
11 Apr 2023Due:
11 Apr 2023Completion:
11 Apr 2023Preliminary Change Report Published for Consultation
Start:
11 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation Start
Start:
14 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation End
Start:
14 Apr 2023Due:
21 Apr 2023Completion:
21 Apr 2023Final Change Report Published
Start:
21 Apr 2023Due:
24 Apr 2023Completion:
24 Apr 2023Responsible Committee Discussion
Start:
24 Apr 2023Due:
26 Apr 2023Completion:
Appeal Window Closure
Start:
26 Apr 2023Due:
12 May 2023Completion:
30 June 2023
- As an impacted Market Participant, I want to have clarity on version of the Market Message and the population of Data Items within the Data Specification, so that my internal systems can be correctly configured to send and receive Data Items within Market Messages.
Revision of the Implementation Date and approved solution for R0021
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Responsible Committee Review Completed
Start:
31 Mar 2023Due:
27 Apr 2023Completion:
27 Apr 2023Consultation Started
Start:
27 Apr 2023Due:
28 Apr 2023Completion:
28 Apr 2023Consultation Ended
Start:
28 Apr 2023Due:
16 May 2023Completion:
16 May 2023Final Change Report Issued
Start:
16 May 2023Due:
19 May 2023Completion:
19 May 2023Responsible Committee Recommendation
Start:
19 May 2023Due:
26 May 2023Completion:
26 May 202330 June 2023
- As a premise owner I want to be able to contract with a Safe Isolator Provider (SIP), and for the SIP to be able to provide the service in a fully compliant manner.
- As a REC MEM who wants to operate as SIP, I need clarity on the solution and Market Message requirements when I provide Safe Isolation Works to Premise Owners. As a Registered Supplier, I need clarity on the solution and Market Message requirements when my consumers have Safe Isolation Works completed at their Premise Owners by SIPs.
- As a Distribution Network Operator, I need clarity on the solution and Market Message requirements when my connected parties have Safe Isolation Works completed at their Premise Owners by SIPs.
Optional fuzzy searching in EES
Service Provider Impact Assessment window start
Start:
07 Mar 2023Due:
09 Oct 2023Completion:
09 Oct 2023Service Provider Impact Assessment window close
Start:
09 Oct 2023Due:
27 Dec 2023Completion:
24 Nov 2024Party Impact Assessment start
Start:
27 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As an organisation providing switching services, I want Consumers to be able to search addresses efficiently.