Smart Meter Communication Licence Code Changes

Date of latest update
Type
Change
ID
R0333
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
28/08/2026 - The consultation has closed - The Code Manager now present this Change Proposal for a final vote at the REC Change Panel on 15 September 2026.
Summary
Ofgem has awarded the Smart Meter Communications Licence 2 (SMCL2) to DCC2 Limited, a subsidiary of Smart Energy Code Company Limited (SECCo). To enable a smooth transition and ensure continuity of service, changes to both the Smart Energy Code (SEC) and the Retail Energy Code (REC) will be required.
Proposer
Holly Law
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0333 - Legal Text V1.1 28.08.26
Archive
Off
SME
SME Role
Lead Assurance Analyst
I0333 Submission Form (PDF)
R0333 Change Report (Consultation) (Approved) 04.08.26
Company Name
-
Review status
Review required

Amend the REC to permit RECCo to undertake additional code manager activities

Date of latest update
Type
Change
ID
R0332
Change Category
Urgent
Yes
Latest Update
26/08/2026 On 25 August 2026, the Change Panel voted, in line with the Code Manager's recommendation, to recommend to the Authority to approve the proposed solution, the implementation approach and the implementation date. This Change Proposal has now been issued to the Authority for decision.
Summary
The REC currently frames RECCo's objective and permissible activities by reference to the REC only. This creates a vires issue where RECCo needs to undertake activities connected with an Energy Code other than the REC, whether directly, through a subsidiary or in partnership with another organisation.
Proposer
Elizabeth Lawlor
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0332 - Draft Main Body
Archive
Off
Document title
R0332 - Draft Schedule 1 - Interpretations and Definitions
Archive
Off
Document title
R0332 - Draft Schedule 4 - Company Governance
Archive
Off
Problem Statement
The REC currently frames RECCo's objective and permissible activities by reference to the REC only. This creates a vires issue where RECCo needs to undertake activities connected with an Energy Code other than the REC, whether directly, through a subsidiary or in partnership with another organisation.
R0332 submission form
REC Change Proposal R0332 - FAQs
R0332 Change Report (Proposal Plan and Consultation) v1.1 Approved 27.07.2026
R0332 Consolidated Consultation Responses v1.0
R0332 Change Report (Final Recommendation) v1.1 Approved 25.08.26
Company Name
-
Review status
Review required

Change of Market Segment – MHHS Guidance

Date of latest update
Type
Change
ID
C3-0161
Urgent
No
Latest Update
-
Summary
Following approval by the REC Metering Expert Panel, this change is being raised on their behalf for implementation. An update to the Change of Market Segment document is proposed to align to the current technical arrangements in relation to the receipt of the IF-035 ‘SMRS Appointment Status Notification’ and subsequent sending of the D0268 ‘Advanced Meter Technical Details’ by a Losing MOA (Advanced). The change provides clarification on expectations in this Advanced to Smart Change of Market Segment scenario.
Proposer
Harriet Truss
Status
Implementation Status
Date Raised
Date of Update to Priority
Company Name
Code Manager (RPS)
Review status
Review required

Regulatory Alliance Creation Rejections

Date of latest update
Type
Issue
ID
I0331
Change Category
Change Path
Priority
Urgent
No
Latest Update
19/08/2026 - the Change Report (Proposal Plan) was approved by Change Panel. The Change Team and Performance Assurance team are working together to determine if there are performance assurance requirements for this change.
Summary
An incident where Network Parties did not submit Regulatory Alliances on time to the Central Switching Service (CSS) Provider, or did submit the Regulatory Alliances but did not action rejections from the CSS Provider in a timely manner, led to over 200 Consumers being delayed in Switching to their chosen Energy Supplier. This Change Proposal has been raised to review this process.
Proposer
abedapatel
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0331 Schedule 24 Switching Data Management
Archive
Off
Problem Statement
The lack of Service Level Agreements (SLAs) on Network Parties to submit Regulatory Alliances to the CSS Provider or to work any rejections received from the CSS Provider can lead to delays in Consumers being able to Switch to their chosen Energy Supplier.
SME
SME Role
Lead Assurance Analyst
I0331 submission form
I0331 Change Report (Proposal Plan) V1.0 approved 18.08.26
Company Name
-
Review status
Review required

Test Sagar

Type
Change
ID
CP6169172797
Urgent
No
Latest Update
Assessment done
Summary
Empty
Proposer
Sagar Agrawal
Impacted REC Documents
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
Stages Selection
Company Name
-
Review status
Review required

Its very hard to get to grip with XXX

Type
Change
ID
CP6166285305
Urgent
No
Latest Update
Empty
Summary
Empty
Proposer
t.tester
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
supporting_documentation_attachment (1).docx
Company Name
-
Review status
Review required

This an issue or a change request submission

Type
Change
ID
I6166214792
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
THIS IS AN UPDATE AND, ANOTHER...
Summary
THIS IS A SUMMARY OF THE CHANGE
Proposer
alex sansom
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Change Report - Draft Change Report

Comments deadline
Change report - Final Change Report

Comments deadline
Change Plan

understand the system

This an issue or a change request submission > Change Plan

Start:

01 Jan 2026

Due:

01 Jan 2026

Completion:

complete tasks x, y and z

This an issue or a change request submission > Change Plan

Start:

Due:

Completion:

27 Jan 2026

finsh remaining task z

This an issue or a change request submission > Change Plan

Start:

06 Jan 2026

Due:

29 Jan 2026

Completion:

22 May 2026

cvbxcvb

This an issue or a change request submission > Change Plan

Start:

01 Jan 2026

Due:

06 Jan 2026

Completion:

my first milestone

This an issue or a change request submission > Change Plan

Start:

29 Jan 2026

Due:

31 Mar 2026

Completion:

my first milestone

This an issue or a change request submission > Change Plan

Start:

31 Mar 2026

Due:

31 Mar 2026

Completion:

aerawertewrtewrt

This an issue or a change request submission > Change Plan

Start:

Due:

Completion:

milestone aaaa

This an issue or a change request submission > Change Plan

Start:

31 Mar 2026

Due:

29 Apr 2026

Completion:

Status
Implementation Status
Date Raised
Lead Analyst
Harriet Truss
Date of Update to Priority
Solution Development
Proposed solution summary
this is the first requirement this is the second requirement this is the third requi... this is the fourth re... this is the fifth re...
Proposed Solution Document
Document title
I chose a document and gave it this title
Archive
Off
Document title
222 another odcument i selected
Archive
Off
Document title
What is this link related to?
Archive
Off
Document title
Another link
Archive
Off
Document title
supporting_documentation_attachment (1).docx
Archive
Off
Document title
Example link
Archive
Off
Problem Statement
this is a statement.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
ATTACHED DOC 1
ANTOHER attached DOC
Company Name
-
Review status
Review required

A review of the Misdirected Payments and Debt Assignment Processes

Date of latest update
Type
Issue
ID
I0329
Change Category
Change Path
Priority
Urgent
No
Latest Update
04/08/2026 - On 04 August 2026, the REC Change Panel approved this Proposal Plan.
Summary
This Issue seeks to assess and identify any gaps, inconsistencies or process improvements opportunities for the Misdirected Payments and Debt Assignment processes.
Proposer
florentina.monea_zDlzC
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0329 Submission Form
I0329 Change Report (Proposal Plan) V1.1 Approved
Company Name
-
Review status
Review required

Provision of Standard industrial Classification (SIC) Code to REC Parties

Date of latest update
Type
Issue
ID
I0327
Priority
Urgent
No
Latest Update
22/05/2026 - Issue accepted in by Code Manager
Summary
As part of the planning required to deliver Net Zero, Gas Distribution Networks (GDNs) are obligated to plan Industrial and Commercial (I&C) gas demand at a more granular, site-specific level. To meet this obligation, access to Standard Industrial Classification (SIC) Code data, matched to both Gas and Electricity Meter Point Reference Numbers, would provide a significantly improved understanding of I&C customers.
Proposer
Sally Hardman
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
I0327 submission form
Company Name
-
Review status
Review required

Erroneous Switch Review: Assurance Reporting Update

Date of latest update
Type
Issue
ID
I0326
Change Path
Priority
Urgent
No
Latest Update
07/07/2025 - Change Report (Proposal Plan) has been approved by the REC Change Panel.
Summary
There is gap in the Erroneous Switch (ES) Performance Assurance reporting as the DTN does not provide MPXN level data up front. It requires individual ES permission before MPXNs are provided. However, CSS reporting does provide monthly MPXN level report. As such end-to-end monitoring of the ES process cannot be carried out at a MPXN level.
Proposer
Joy Nnamani
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
I0326 submission form
I0326 Change Report (Proposal Plan) (Approved) v1.1 07.07.26
Company Name
-
Review status
Review required