Review of Category 3 documents in the REC Baseline Statement
Preliminary Change Report Issued
Start:
07 Jan 2022Due:
04 Feb 2022Completion:
04 Feb 2022Consultation Issued
Start:
04 Feb 2022Due:
18 Feb 2022Completion:
18 Feb 2022Final Change Report Issued
Start:
18 Feb 2022Due:
25 Mar 2022Completion:
25 Mar 2022Responsible Committee Decision
Start:
25 Mar 2022Due:
05 Apr 2022Completion:
05 Apr 202214 April 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Market Participant, I need to understand any changes that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
- As the REC Code Manager, I need to ensure that proposals to amend the REC and its subsidiary documents are subject to appropriate scrutiny and impact assessment, so that impacted stakeholders can appropriately engage with the proposal and understand the impacts to their business.
Minimum identification requirements in the Meter Operation Code of Practice
- As an electricity Consumer I want to be able to verify the attending agent’s identity so I can feel safe at my Premises whilst work is completed and trust the Energy industry to care about my safety.
- As an electricity Consumer I want to be able to verify the attending agent’s identity so that work can be completed efficiently, without delay or confusion.
- As an Electricity Supplier I want my Appointed Metering Equipment Manager to be identifiable when attending Consumer Sites to retain Consumer confidence, trust and for works to be completed without delay.
- As a Metering Equipment Manager, I want clarity around the requirements regarding identity cards to be clear so that I can assure compliance and easily identify myself to consumers at site.
- As a Metering Scheme Auditor, I want clarity on appropriate identity requirements so I can confidently validate a Metering Equipment Manager’s identity during a site audit.
Whole current (WC)/Current Transformer (CT) certificates
Solution Analysis and Development Start
Start:
07 Jan 2022Due:
31 Oct 2022Completion:
Impact Assessment Period start
Start:
Due:
Completion:
Solution Development completed
Start:
Due:
Completion:
Impact Assessment period ends
Start:
Due:
Completion:
- As an Electricity Consumer I want to be confident that the Meter Operative that completes work on my Metering Equipment is competent to ensure my supply is safe, secure and uninterrupted.
- As a MEM, I want to be confident that my processes and Meter Operatives are compliant with the MOCoP, to ensure minimal disruption to my clients and the safety of my employees.
- As an Electricity Supplier, I want to be confident that my Appointed agents are compliant with the MOCoP to ensure my consumers safety.
Prepayment Unallocatable Transactions
Preliminary Change Report Issued
Start:
15 Dec 2021Due:
04 Mar 2022Completion:
04 Mar 2022Responsible Committee Decision
Start:
08 Apr 2022Due:
19 Apr 2022Completion:
19 Apr 2022Consultation Period Start
Start:
19 Apr 2022Due:
22 Apr 2022Completion:
22 Apr 2022Consultation Period End
Start:
22 Apr 2022Due:
16 May 2022Completion:
16 May 2022Final Change Report Issued
Start:
16 May 2022Due:
27 May 2022Completion:
27 May 2022Responsible Committee Decision
Start:
27 May 2022Due:
07 Jun 2022Completion:
07 Jun 2022Appeal Window Closure
Start:
07 Jun 2022Due:
22 Jun 2022Completion:
22 Jun 2022Legal Review / Preliminary Change Report Revision
Start:
04 Mar 2022Due:
15 Mar 2022Completion:
15 Mar 2022Revised Preliminary Change Report Issued
Start:
15 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 202230 June 2022
- As a PPMIP, I want to receive accurate market share data to allow me to complete the Unallocatable Prepayment Allocation Run in a timely manner.
- As an Energy Supplier, I want the calculation of Unallocatable Transactions to be carried out accurately and efficiently so that I receive payments allocated to my organisation.
ETTOS Report Dissemination
Initial Assessment Report published
Start:
29 Nov 2021Due:
03 Dec 2021Completion:
03 Dec 2021Change Panel review
Start:
03 Dec 2021Due:
07 Dec 2021Completion:
07 Dec 2021Preliminary Change Report issued
Start:
07 Dec 2021Due:
13 Dec 2021Completion:
13 Dec 2021Change Panel review
Start:
13 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 2021Consultation starts
Start:
21 Dec 2021Due:
22 Dec 2021Completion:
21 Dec 2021Consultation ends
Start:
22 Dec 2021Due:
12 Jan 2022Completion:
12 Jan 2022Final Change Report issued
Start:
12 Jan 2022Due:
14 Jan 2022Completion:
14 Jan 2022Change Panel decision
Start:
14 Jan 2022Due:
18 Jan 2022Completion:
18 Jan 202231 January 2022
- As a Consumer, I want my Energy Supplier to receive and act upon energy theft tip-offs, to ensure the safety and security of my energy supply.
- As an ETTOS Recipient, I need to be aware of changes to the way I will receive and send tip-off information, so I can engage in the process and plan any required changes to my processes.
- As an ETTOS Recipient, I need to receive my ETTOS Service Data in a timely manner, so that I am able to act on tip-offs, to reduce risks for consumers and my business.
Consequential REC changes for BSC CP1532
Initial Assessment Report and Change Proposal Plan approved
Start:
26 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Preliminary Change Report issued
Start:
21 Dec 2021Due:
28 Jan 2022Completion:
28 Jan 2022Preliminary Change Report approval
Start:
28 Jan 2022Due:
09 Feb 2022Completion:
09 Feb 2022Consultation starts
Start:
09 Feb 2022Due:
14 Feb 2022Completion:
11 Feb 2022Consultation ends
Start:
14 Feb 2022Due:
04 Mar 2022Completion:
04 Mar 2022Final Change Report Issued
Start:
04 Mar 2022Due:
11 Mar 2022Completion:
11 Mar 2022Responsible Committee decision (ex-Committee)
Start:
11 Mar 2022Due:
23 Mar 2022Completion:
22 Mar 202230 June 2022
- As an electricity Consumer I want my new Energy Supplier to set up my account and appoint their agents appropriately, so I receive timely and accurate bills.
- As a Market Participant, I need to understand any changes to Market Messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
- As an Energy Supplier, I want to be able to Appoint and De-appoint Agents more quickly, to minimise risks to my settlement performance and ability to produce accurate and timely consumer bills when the new switching arrangements go-live.
Complex Sites process improvements
Party Impact Assessment Issued
Start:
25 Nov 2021Due:
20 Jan 2022Completion:
10 Feb 2022Preliminary Change Report Issued
Start:
20 Jan 2022Due:
21 Feb 2022Completion:
18 Feb 2022Responsible Committee Decision – Ex-Committee
Start:
21 Feb 2022Due:
03 Mar 2022Completion:
03 Mar 2022Consultation Started
Start:
03 Mar 2022Due:
07 Mar 2022Completion:
07 Mar 2022Consultation End
Start:
07 Mar 2022Due:
01 Apr 2022Completion:
01 Apr 2022Final Change Report Issued
Start:
01 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Responsible Committee Decision
Start:
29 Apr 2022Due:
11 May 2022Completion:
11 May 2022Appeal Window Open
Start:
11 May 2022Due:
13 May 2022Completion:
13 May 2022Appeal Window Closed
Start:
13 May 2022Due:
27 May 2022Completion:
27 May 202204 November 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0002 | Review of Data Specification Category in REC Baseline Statement |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.3 | 29 May 2026 | ||
| 1.3 | 29 May 2026 |
- As an electricity Consumer, I want my metering data to be accurate, to ensure my account is set up correctly and I receive accurate and timely invoices.
- As a Metering Equipment Manager, I want to have clarity on my obligations to provide data - specifically what data I need to send, who the recipients are and when I need to send it to ensure I provide accurate data to other Market Participants. As an Electricity Supplier and as an Electricity Distribution Network Operator (DNO), I want to receive accurate and complete Meter Technical Details (MTD) to enable me to take appropriate action following a change of metering equipment, a switch, a change of HHDC, a new connection a meter configuration or MEM.
- As a Half Hourly Data Collector, I want to receive accurate and complete Meter Technical Details to enable me to take appropriate action following a change of metering equipment, change of supplier, change of HHDC, new connections, meter configuration or MEM.
Resolution of Bilateral Erroneous Transfers
Solution Analysis
Start:
18 Nov 2021Due:
21 Mar 2023Completion:
Proposed Approach Presented To Change Panel
Start:
21 Mar 2023Due:
18 Apr 2023Completion:
- As a Consumer, I want issues affecting me or my energy account to be resolved at the earliest opportunity, to minimise impacts to my energy switch or accurate and timely billing.
- As a Consumer, I want industry parties to share my personal data securely so that my data is protected.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I can bill my Consumers accurately and timely.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I supply Consumers with whom I have a valid contract.
Remote communication obligations for electricity Advanced Meters
Initial Assessment Report published
Start:
17 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Analysis and Solution development activity
Start:
21 Dec 2021Due:
27 Feb 2022Completion:
25 Feb 2022Party Impact Assessment completion
Start:
27 Feb 2022Due:
21 Mar 2022Completion:
21 Mar 2022Preliminary Change Report issued
Start:
07 Apr 2022Due:
27 May 2022Completion:
27 May 2022Consultation starts
Start:
27 May 2022Due:
10 Jun 2022Completion:
10 Jun 2022Consultation ends
Start:
10 Jun 2022Due:
01 Jul 2022Completion:
01 Jul 2022Final Change Report issued
Start:
01 Jul 2022Due:
29 Jul 2022Completion:
28 Jul 2022Metering Expert Panel decision
Start:
29 Jul 2022Due:
10 Aug 2022Completion:
10 Aug 2022Service Provider Impact Assessment issued
Start:
21 Mar 2022Due:
07 Apr 2022Completion:
07 Apr 2022Send back solution refinement completed
Start:
10 Aug 2022Due:
13 Jan 2023Completion:
13 Jan 2023Consultation issued
Start:
13 Jan 2023Due:
20 Jan 2023Completion:
20 Jan 2023Update provided to Change Panel
Start:
20 Jan 2023Due:
07 Feb 2023Completion:
07 Feb 2023Final Change Report issued
Start:
07 Feb 2023Due:
14 Feb 2023Completion:
14 Feb 2023Responsible Committee decision
Start:
14 Feb 2023Due:
21 Feb 2023Completion:
21 Feb 2023Authority Determination requested
Start:
21 Feb 2023Due:
28 Feb 2023Completion:
24 Mar 202330 June 2023
- As an electricity consumer with an Advanced Meter, I want my usage data to be accessed remotely from my meter, to reduce the need for on-site visits and ensure that I receive timely and accurate bills.
- As the Market-wide Half Hourly Settlement (MHHS) Programme I want to see an effective, early migration of NHH settled Advanced Meters to HH settled, to reduce the risk of missed migration deadlines and ensuring sufficient time to resolve ‘problem’ sites ahead of the MHHS migration deadline.
- As an Energy Supplier I want to obtain usage remotely, reducing the need for on-site metering reading activity, enabling me to settle and bill accurately. As a Metering Equipment Manager (MEM), I need to understand any changes to obligations that may impact my business, so I can engage in the change process and plan any required changes to my systems, processes and organisation.
Housekeeping amendments to REC V2
Initial Assessment Report published
Start:
04 Oct 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
22 Oct 2021Completion:
22 Oct 2021Change Panel review
Start:
22 Oct 2021Due:
16 Nov 2021Completion:
16 Nov 2021Consultation starts
Start:
16 Nov 2021Due:
17 Nov 2021Completion:
17 Nov 2021Consultation ends
Start:
17 Nov 2021Due:
08 Dec 2021Completion:
08 Dec 2021Final Change Report issued
Start:
08 Dec 2021Due:
10 Dec 2021Completion:
10 Dec 2021Change Panel decision
Start:
10 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 202131 January 2022
- As an Energy Consumer, I need Energy Companies to operate consistent processes, to ensure my energy supply is managed efficiently and to retain my trust in the functioning of the energy market.
- As a REC Party, I need the REC to provide a consistent baseline, so I can operate in an interoperable way with other Market Participants.