Schedule 27 - RMP Lifecycle 1.1
– Implemented on
Loading...
CSS Message Time Stamping
Date of latest update
Type
Change
ID
R0107
Urgent
No
Latest Update
11/08/2023 - This Change Proposal has been withdrawn. During the progression of the Preliminary Impact Assessment work, it was found that an existing data item ‘EventDate’ could be leveraged to address the issue stated in the Change Proposal. R107 will be open for adoption until 25/08/2023.
Summary
Empty
Change Plan
Test
In Progress
Start:
14 Apr 2023Due:
19 Mar 2026Completion:
19 Mar 2026Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Date of Update to Priority
Solution Development
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
R0107 - Change Proposal Form
Company Name
DCC
Review status
Review required
Changes to allow DNOs to reinstate disconnected MPANs
Date of latest update
Type
Change
ID
R0095
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
10/04/2026 - Change has been taken of hold. This change will be triggered for a reassessment for Code Manager Impact on 14/04/2026.
Summary
When Meter Point Administration Numbers (MPANs) are erroneously disconnected, they cannot be reinstated. As a result, Consumers suffer billing issues and Registered Suppliers cannot settle against the disconnected MPAN. This change seeks to introduce a mechanism to restore erroneously disconnected MPANs.
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
- As a Consumer, I do not want the erroneous disconnection of my MPAN to affect the continuity of my supply contract and billing arrangements.
- As a DNO, I want to be able to reverse erroneous disconnections with no lasting effect so that I don’t need to create a new MPAN to resolve the issue, thereby avoiding DUoS payment collection issues. 2 - As a Supplier, I want to be able to reverse erroneous disconnections with no lasting effect so that I can correctly bill my consumers. 3 - As the CSS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate. 4 - As MPRS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate.
Problem Statement
When MPANs are incorrectly identified and targeted for disconnection, the RMP will be erroneously terminated following receipt of Termination Market Messages by the CSS. This process is irreversible once triggered, meaning that there is no mechanism to restore the MPAN as it was previously. This results in a poor Consumer experience, and settlement misbalancing for Registered Suppliers. Currently, there is no mechanism to mitigate the negative impact on Registered Suppliers/DNO and Consumers.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0095 - Change Proposal form downloadable version 17.02.2023
R0095 Change Proposal Plan v1.0 (Approved) - 20.09.23
R0095 Initial Assessment Report v1.0 (Approved) - 20.09.2023
R0095 - Change Proposal Re-Plan (Approved) v1.0-13.12.23
Company Name
-
Review status
Review required
REC V3.0
Date of latest update
Type
Change
ID
R0041
Change Category
Urgent
Yes
Latest Update
_
Summary
_
Change Plan
Legal text baselined
Completed
Start:
10 Apr 2022Due:
13 May 2022Completion:
13 May 2022Final Change Report Issued
Completed
Start:
13 May 2022Due:
20 May 2022Completion:
20 May 2022Responsible Committee Decision
Completed
Start:
20 May 2022Due:
07 Jun 2022Completion:
07 Jun 2022Authority Determination (Original)
Completed
Start:
07 Jun 2022Due:
20 Jun 2022Completion:
17 Jun 2022Authority Determination (revoked and re-issued)
Completed
Start:
20 Jun 2022Due:
29 Jun 2022Completion:
29 Jun 2022Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
18 July 2022
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
- As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
- As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
- As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
- As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.
Proposed Solution Document
Document title
REC V3.0 Baselined documents
Archive
Off
Document title
REC v3.0 Baselined documents (REC Portal)
Archive
Off
Problem Statement
Changes are required to the REC, to ensure the appropriate obligations, processes and provisions are defined within the REC at CSS go-live, enabling successful transition to enduring governance and operational arrangements developed as part of Ofgem’s Switching Programme.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0041 - Change Proposal Form
Letter from the Authority to the REC Code Manager - REC V3.0 Authority Change Proposal
R0041 - Change Proposal Plan v1.0 (Approved)
R0041 - Initial Assessment Report v2.0 (Approved)
R0041 - Final Change Report v3.0 (Post-Vote)
R0041 Authority Decision
Company Name
Ofgem
Review status
Review required