Updates to Schedule 14 Measurement Transformers Commissioning Timescales

Date of latest update
Type
Change
ID
R0284
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
12/08/2026 - the Metering Expert Panel approved the Change Report (Final Recommendation) V1.2. This Change Proposal will be implemented on 26 June 2027. If you wish to appeal this decision, this must be received by COB 28 August 2026.
Summary
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
Proposer
Caroline Freimuller
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Change Report - Draft Change Report
Impacted REC Documents
Status
Implementation Date
Status Live
EMAR Version 25.06.2027_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0284 Schedule 14 Metering Operations draft V0.2
Archive
Off
Document title
R0284 Schedule 14 Metering Operations draft V0.3
Archive
Off
Document title
R0284 Schedule 14 Metering Operations final version
Archive
Off
Problem Statement
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
I0284 submission form
I0284 Change Report (Proposal Plan) V1.0 approved 03.02.26
I0284 Change Issue Group paper v1.0
I0284 Consolidated Impact Assessment Responses PUBLIC v1.0
R0284 Change Report (For Consultation) V1.0 approved 08.04.26
R0284 Consolidated Consultation Responses PUBLIC v1.0
R0284 Change Report (Final Recommendation) V1.2 approved 12.08.26
Company Name
-
Review status
Review required

Return of Legacy Meters

Date of latest update
Type
Issue
ID
I0282
Change Path
Priority
Urgent
No
Latest Update
08/04/2026 - The Closure Report was presented to the REC Metering Expert Panel at their meeting on 08 April 2026. The Issue has now been classed as resolved.
Summary
The issue identified is that current arrangements require or assume that legacy Meter Asset Providers (MAPs) take back old, non Smart Meters once they are removed from Consumers’ Premises, even though many of these meters are obsolete, cannot be reused, and ultimately require disposal. This has resulted in large volumes of legacy meters being transported across the country between storage providers and legacy MAPs, creating unnecessary cost, administrative burden, and environmental impact. Storage providers are issuing extensive lists of Meter Serial Numbers (MSN) to try to establish meter ownership, and legacy MAPs must manually verify these details. This process has been made more difficult by historical changes in company names and ownership structures. Once ownership is confirmed, the meters are frequently transported to the legacy MAP only for them to arrange disposal, which provides no net value and simply adds further transportation and handling costs.
Proposer
bryan.heap
Change Report - Initial Assessment and Change Plan Report
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
The process for handling removed legacy non Smart Meters is inefficient and environmentally costly, with unclear ownership, unnecessary transport, and no established recycling route. A consistent, sustainable disposal solution is needed to reduce waste, simplify operations, and clarify the management of any scrap value.
I0282 submission form
I0282_Closure Report_v1.0 (26 March 2026)
Company Name
-
Review status
Review required

Extending R0067 Refresh Functionality

Date of latest update
Type
Issue
ID
I0281
Change Category
Change Path
Priority
Urgent
No
Latest Update
03/07/2026 - The Service Provider Impact Assessment is ongoing and expected to be completed by 07 August 2026.
Summary
CSS Market Messages sent by the Central Switching Service (CSS) to Switching Data Service Providers (SDSPs) are either not being received, being received after Gate Closure, or are being received out of the order that they were originally sent in. This Issue originally aimed to extend the Refresh functionality, implemented for the Gas Retail Data Agent (GRDA).to the Electricity Retail Data Agent (ERDA). Following solution development for I0281, it was agreed that the Refresh functionality would be made available for all Market Participants in receipt of the in-scope messages.
Proposer
Finn Deacon
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
CSS messages are not received by the SDSPs in the order in which they were originally sent, or after Gate Closure, so it can be difficult to detect and often requires significant manual effort to resolve. This issue can directly impact Consumer switching experiences, causing disruption and possible delays in a switch.
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0281_Change Report (Update to Plan) v1.0 (Pre-approval)
I0281_Change Report (Update to Plan) v1.0 Approved 20.05.2026
Company Name
-
Review status
Review required

Establishing the Safe Isolation Provider (SIP) as a Standalone REC Party

Date of latest update
Type
Issue
ID
I0278
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - An Update to Plan has been approved by the Change Panel on 21 July 2026.
Summary
This proposal recommends the formal recognition of the Safe Isolation Provider (SIP) as a standalone Party under the Retail Energy Code (REC). This aligns with the direction set out in Ofgem’s recently published Strategic Direction Statement (SDS), which explicitly calls for the establishment of SIPs as a standalone Party role. The aim is to address the growing scale of unregulated SIP activity, mitigate associated consumer safety risks, and ensure the metering industry is equipped to support the UK’s Net Zero ambitions. By enabling easier access to certified SIPs, this change will enhance consumer protection, accelerate low-carbon technology deployment, and improve operational efficiency across the energy sector.
Proposer
Rebecca Griffiths
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
The current SIP framework poses several risks: - Consumers, MEMs and unaccredited practitioners’ safety. Unaccredited and unregulated isolation work increases the risk of unsafe installations and potential harm to Consumers. NAPIT highlighted to RECCo and DESNZ that 17 and 13 unregulated practitioners respectively died in 2023 and in 2024 due to unsafe isolation. With the right Party undertaking this work, there would also be less safety issues for the Consumer at their premises; - Inequity. Independent Installers face longer wait times compared to supplier-led installations, creating a two-tier system; - Low competitive market. Currently prospective Parties can be put off from applying to be a SIP as it appears they would need full MEM Accreditation which is often too far outside their current business operating model. Providing SIPs with their own pathway and requirements could result in more Parties becoming SIPs and therefore giving Consumers more choice in their provider; and - Decarbonisation delays. The inability to scale SIP capacity undermines the timely deployment of LZCTs, threatening Net Zero targets.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0278 submission form
I0278 Change Report (Proposal Plan) V1.0 (Pre-Approval) 09.10.2025
I0278_Change Report (Extension to Plan) v1.0 (Pre-Approval) 12.01.2026
I0278_Change Report (Extension to Plan) v2.0 (Pre-Approval) 13.07.2026
I0278_Change Report (Extension to Plan) v2.1 (Approved) 21.07.26
I0278_Consolidated Information Request DNO Responses
I0278_Consolidated Information Request MEM-SIP Responses PUBLIC
I0278_Consolidated Information Request RPA Responses
Company Name
-
Review status
Review required

MHHS Related Metering Points across Market Segments

Date of latest update
Type
Issue
ID
I0275
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
06/11/2025 - Following discussions at the Change Issues Group on 06 November, a REC guidance will be developed to support the resolution of this Issue after which it will be classed as resolved.
Summary
It has been identified by the MHHS Data Cleanse Working Group (DCWG) that around 9,000 existing Metering Point Relationships include Metering Points that would migrate into different Market-wide Half Hourly Settlement (MHHS) Market Segments. The majority of these are where one Metering Point has a Traditional meter installed (Smart Segment) and a Related Metering Point has an Advanced meter (Advanced Segment). This situation is currently valid but in MHHS would cause two problems. - SMRS would not be able to align the agent appointments, leaving secondary MPANs without agents and MHHS Migrations unable to fully complete.
Proposer
jonny.moore_42
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
Without considering this Issue, there will be a risk to the MHHS migration. Indeed, a Metering Point installed which does not match its Related Metering Point (for example a Relationship between a Traditional meter with an Advanced Meter) will not be able to fully migrate to MHHS arrangements.
I0275 submission form
Company Name
-
Review status
Review required

Gas Pressure and Capacity Information Transparency

Date of latest update
Type
Issue
ID
I0274
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - Change Report (Proposal Re-Plan) approved at Change Panel
Summary
As per Section 13.4.18 of CoMCoP, retrieving gas pressure and capacity information from Transporters via the GT1 process can be time consuming for Energy Suppliers/MAMs and/or Consumers. The process of retrieving this information is inconsistent and service timescales are varied between transporters. Gas pressure and capacity information should be readily available through the Gas Enquiry Service to enable timely processing of site work and requests to enable MAM’s and Suppliers to appropriately service their customers.
Proposer
Carl Whitehouse
Impacted REC Services
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Problem Statement
For some Energy Suppliers, MAMs and consumers, retrieving pressure and capacity information via the GT1 process can be time consuming. This is due to elements like response timescales and methods (batch responses vs individual responses) being varied among GTs. This ultimately has a negative impact on customers waiting on site work, such as a new connection, for example.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0274 submission form
I0274 Change Report (Proposal Plan) V1.0 approved 18.11.25
IG174 Change Proposal Re-Plan v2.0 approved 21.07.2026
Company Name
-
Review status
Review required

Sharing of SSC and TPR Information for MHHS Smart and Advanced Meters

Date of latest update
Type
Issue
ID
I0273
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
23/06/2026 - The Code Manager has published an Interim Guidance Document for I0273.
Summary
In the MHHS design the Standard Settlement Configuration (SSC) is a non-mandatory data item for Smart and Advanced metering points, in addition the register level TPR information is not shared in the MTD flows for these meters (IF-006 for Smart and D0268 for Advanced). It was identified through BSC Issue I118 that there is a requirement for the SSC to be set for Domestic / Microbusiness Advanced Metering Points making use of the HH data opt out and there may be other areas where the SSC is required.
Proposer
jonny.moore_42
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
James Hardy
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0273 - Interim Guidance Document V1.1
Archive
Off
Problem Statement
The MHHS design does not mandate the use of SSC or support register-level TPR data for Smart and Advanced Meters, creating gaps in data availability for certain Settlement scenarios.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0273 Submission Form
I0273 - Update to Plan V2.0 (Pre-Approval) 06.05.2026
Company Name
-
Review status
Review required

Enabling transparency of the CRS Provider’s REC service level performance

Date of latest update
Type
Change
ID
R0272
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
RECCo regularly reports on the performance of REC Service Providers in relation to their activities under the REC. However, there is currently no formal agreement to permit the publication of CRS performance measures between the CRS Provider and RECCo. Due to the multi-Party agreement, the REC does not specifically address the publication of this performance data. Instead, RECCo are operating under an informal understanding with the CRS Provider, which means there is a possibility that publication may be delayed or not agreed to in a given month. RECCo is dependent on the CRS Provider’s approval for each publication, which can cause delays. This approval could also be withheld at any point.
Proposer
Jenny Bridges
Change Report - Initial Assessment and Change Plan Report
Change report - Final Change Report

Comments deadline
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Live
EMAR Version 27.02.2026_live
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. An update to the REC Schedule 6 – Performance Assurance.
Proposed Solution Document
Document title
R0272 Approved legal text (26.01.2026)
Archive
Off
Problem Statement
Unlike REC Service Providers, there is currently no formal agreement in place between the CRS Provider and RECCo to publish details about the CRS Provider’s performance. RECCo is therefore dependent on the CRS Provider’s approval for each publication. Not only could there be delays in RECCo’s reporting, but the approval could also be withheld at any point, preventing RECCo’s reporting.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0272 Change Proposal Form
R0272 Consolidated Consultation responses V1.0
Company Name
-
Review status
Review required

Clarification of SIP Qualification Requirements

Date of latest update
Type
Change
ID
R0270
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
REC Schedules 1, 14, and 15 all note that in order to Qualify as a Safe Isolation Provider (SIP), the Party needs to be a Qualified Meter Operator Agent (MOA). It has since been determined that Qualified Electricity Metering Operatives (EMOs) should also be able to Qualify as SIPs.
Proposer
Daniel Rodgers
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Live
EMAR Version 27.02.2026_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0270 draft legal text
Archive
Off
Problem Statement
Requiring SIPs to be fully Qualified MOAs may be hindering smaller Parties who wish to be SIPs from Qualifying under the REC. This in turn may be reducing the number of Qualified SIPs in the market for Consumers to choose from or causing Consumers inadvertently to contract with people who are not Qualified SIPs to carry out SIP Works.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0270 Submission Form
I0270 Change Report (Proposal Plan) V1.0 approved 18.11.25
R0270 Change Report (For Consultation) V1.1 approved 10.12.25
R0270 Consolidated Consultation Responses V1.0
R0270 Change Report (Final Recommendation) V1.0 approved 11.02.26
Company Name
-
Review status
Review required

Smart Meter Installation Surveys - Microbusiness requirements

Date of latest update
Type
Change
ID
R0267
Change Category
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
There is no requirement for energy suppliers planning fewer than 5000 Smart meter installations at domestic premises, within a calendar year, to survey Consumers for REC compliance purposes. Conversely, there is no minimum threshold in place for microbusiness installations, meaning that non-domestic suppliers are required to procure a suitably qualified, independent Smart Meter Installation Survey Organisation, at considerable cost, to survey what might be a very small number of customers.
Proposer
june.mallett
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

19 Aug 2025
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Live
EMAR Version 26.06.2026_live
Included changes Affected REC Items
R0103 Central provision of DCC Technical Contacts for requesting test certificates
  • Schedule 25 - Central Switching Service
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
I0267 CoMCoP Appendix 20 draft V0.1
Archive
Off
Document title
R0267 CoMCoP Appendix 20 draft V0.2
Archive
Off
Problem Statement
Non-Domestic Energy Suppliers are having to procure an independent Smart Meter Installation Survey Organisation, at considerable cost, to survey what might be a very small number of Consumers to be compliant with their REC obligations.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0267 Submission form
I0267 Change Report (Proposal Plan) V1.1
I0267 Extension to Plan V1.0
I0267 Consolidated Impact Assessment Responses PUBLIC v1.0
R0267 Change Report (For Consultation) V1.0
R0267 Consolidated Consultation Responses PUBLIC v1.0
R0267 Change Report (Final Recommendation) V1.0 approved 07.04.26
R0267 Decision Document
Company Name
-
Review status
Review required