CSS Message Regeneration Functionality
Update to Plan approved at Change Panel
Start:
Due:
Completion:
21 Oct 202505 November 2027
DCC Service Level Agreements for the Switching Incentive Regime
Solution Development
Start:
01 Feb 2023Due:
05 Oct 2023Completion:
05 Oct 2023Service Provider Impact Assessment
Start:
05 Oct 2023Due:
20 Nov 2023Completion:
13 Nov 2023Party Impact Assessment
Start:
20 Nov 2023Due:
03 Jan 2024Completion:
10 Nov 2023Preliminary Change Report issued
Start:
03 Jan 2024Due:
20 Feb 2024Completion:
16 Feb 2024Preliminary Change Report - Committee Review
Start:
20 Feb 2024Due:
27 Feb 2024Completion:
27 Feb 2024Consultation close
Start:
01 Mar 2024Due:
04 Apr 2024Completion:
04 Apr 2024Final Change Report issued
Start:
04 Apr 2024Due:
23 Apr 2024Completion:
19 Apr 2024Responsible Committee Decision
Start:
23 Apr 2024Due:
30 Apr 2024Completion:
30 Apr 2024Sent to Authority for Determination
Start:
30 Apr 2024Due:
01 May 2024Completion:
Consultation published
Start:
27 Feb 2024Due:
01 Mar 2024Completion:
01 Mar 2024- As a Consumer, I want the CRS Provider to provide an effective service so that my Switch is not delayed.
- As the REC Code Manager, I want to ensure the CRS Provider has appropriate SLAs set, which incentivises the effective functioning of the Switching Service.
- As the CRS Provider, I want to ensure that the appropriate SLAs are in place to incentivise the effective functioning of the Switching Service and if these SLAs are not met by the CRS Provider, the commercial impact is proportionate to the detriment experienced by CSS Users and Consumers.
Clarifications to the Theft Detection Incentive Scheme
Initial Assessment Report Issued
Start:
23 Jan 2023Due:
27 Jan 2023Completion:
27 Jan 2023Change Proposal Plan Issued
Start:
27 Jan 2023Due:
27 Jan 2023Completion:
27 Jan 2023Preliminary Change Report Issued
Start:
07 Feb 2023Due:
17 Feb 2023Completion:
17 Feb 2023Consultation Issued
Start:
17 Feb 2023Due:
17 Feb 2023Completion:
17 Feb 2023Responsible Committee Decision
Start:
17 Feb 2023Due:
24 Mar 2023Completion:
24 Mar 2023IAR and CPP Approval
Start:
27 Jan 2023Due:
07 Feb 2023Completion:
07 Feb 202301 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As an Energy Supplier, I need my TDIS obligations to be clear to ensure I can meet the requirements appropriately.
- As the Code Manager, I want all Suppliers to be clear on the required Energy Theft reporting so that the scheme can be effectively administered.
- As RECCo, I want to ensure that all Suppliers have clear obligations to ensure the effective administration of TDIS to support the Theft Reduction Strategy.
Housekeeping changes to the approved legal text for R0047
Preliminary Change Report published and issued for Consultation
Start:
16 Dec 2022Due:
24 Feb 2023Completion:
24 Feb 2023Consultation ends
Start:
24 Feb 2023Due:
10 Mar 2023Completion:
10 Mar 2023Final Change Report published
Start:
10 Mar 2023Due:
21 Mar 2023Completion:
21 Mar 2023Responsible Committee decision (Ex-Committee)
Start:
21 Mar 2023Due:
24 Mar 2023Completion:
24 Mar 2023Appeal window closure
Start:
24 Mar 2023Due:
07 Apr 2023Completion:
01 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As a DNO, MEM, AMI, ASP or MI, I want all Code of Practice obligations to be clear and transparent, to ensure all obligations placed upon my organisation and operatives are understood and can be met in the most efficient way.
- As an Energy Supplier, I want to be confident that my Appointed agents are compliant with all relevant CoP obligations to ensure the safety of my Consumers.
- As RECCo, I want the Metering Scheme obligations to be clear and transparent, to ensure the arrangements deliver against the RECCo strategic aims.
- As the Metering Scheme Auditor, I want the Metering Scheme obligations to be clear and transparent, to ensure the arrangements deliver against the RECCo strategic aims.
CSS Market Message Retry Strategy
Improvements to ‘Failed to Deliver’ CSS Messages
Service Provider Impact Assessment close
Start:
09 Nov 2022Due:
25 Jan 2024Completion:
25 Jan 2024Party Impact Assessment trigger
Start:
25 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Party Impact Assessment close
Start:
02 Feb 2024Due:
23 Feb 2024Completion:
23 Feb 2024Preliminary Change Report and Consultation issued
Start:
23 Feb 2024Due:
10 May 2024Completion:
10 May 2024Consultation close
Start:
10 May 2024Due:
03 Jun 2024Completion:
03 Jun 2024Responsible Committee Decision
Start:
24 Jul 2024Due:
31 Jul 2024Completion:
31 Jul 2024Final Change Report Issued
Start:
03 Jun 2024Due:
24 Jul 2024Completion:
19 Jul 202427 June 2025
- As a Consumer, I want the Switching process to work successfully, so that I can switch Energy Supplier without delays or issues.
- As the CSS Provider I want the messages I send to CSS Users to be received and processed successfully, so that there is no interruption to the Switching process or the Consumers’ Switching experience.
- As the CSS User I want to receive CSS messages in a timely manner following any outage of my own gateway or systems, so that there is no interruption to the Switching process or the Consumers’ Switching experience.
DCC access to EES and GES
Service Provider Impact Assessment Due
Start:
25 Sep 2022Due:
21 Sep 2023Completion:
Preliminary Change Report Issued
Start:
21 Sep 2023Due:
06 Oct 2023Completion:
Responsible Committee Review
Start:
06 Oct 2023Due:
17 Oct 2023Completion:
17 Oct 2023Consultation Issued
Start:
17 Oct 2023Due:
20 Oct 2023Completion:
20 Oct 2023Final Change Report Issued
Start:
20 Oct 2023Due:
10 Nov 2023Completion:
10 Nov 2023Responsible Committee Decision
Start:
10 Nov 2023Due:
21 Nov 2023Completion:
21 Nov 202323 February 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As a Consumer, I want data relating to my energy supply to be handled appropriately, so that I can have a consistent and faultless switching experience.
- As the Switching Service Desk, I want to be able to access market data that lets me resolve tickets first time, so that I can provide a more efficient service to users. As the GES Provider, I want my users to be able to access information that helps them fulfil their objectives, so that the service is used as efficiently as possible. As the EES Provider, I want my users to be able to access information that helps them fulfil their objectives, so that the service is used as efficiently as possible.
Introduction of CSS refresh functionality
Solution Analysis and Development
Start:
29 Aug 2022Due:
19 Oct 2022Completion:
19 Oct 2022Service Provider Impact Assessment
Start:
19 Oct 2022Due:
29 Mar 2023Completion:
29 Mar 2023Consultation
Start:
11 Apr 2023Due:
09 May 2023Completion:
28 Apr 2023Preliminary Change Report Issued
Start:
29 Mar 2023Due:
11 Apr 2023Completion:
05 Apr 2023Final Change Report Issued
Start:
Due:
Completion:
21 Jun 2023Responsible Committee Decision
Start:
09 May 2023Due:
28 Jun 2023Completion:
28 Jul 202306 December 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0106 | Performance Assurance Report Catalogue V5.1 |
- As a Consumer, I want the Switching process to work successfully, so that I can switch Energy Supplier without delays or issues.
- As the CSS Provider I want the messages I send to SDSPs to be received and processed successfully, so that there is no interruption to the Switching process or the Consumers’ Switching experience. As the CSS Provider, I want the functionality to be available for SDSPs to automatically resolve issues when messages are not received in the correct order or are received after Gate Closure, so that this work does not have to be done manually.
- As an SDSP, I want to be able to detect when I have not received the expected CSS messages, so that I am able to request that the missing messages are sent to me to process. As an SDSP I want to be able to request a refresh of CSS messages when they are not received in the correct order or they are received after Gate Closure, so that I am able to maintain an accurate reflection of the current Switch status and minimise impacts on CSS Users and Consumers.
Addition of key information to all Service Now tickets
Solution Analysis and Development
Start:
22 Aug 2022Due:
07 Feb 2023Completion:
07 Feb 2023Service Provider Impact Assessment - Preliminary
Start:
07 Feb 2023Due:
20 Mar 2023Completion:
20 Mar 2023Service Provider Detailed Impact Assessments
Start:
20 Mar 2023Due:
10 Jul 2023Completion:
27 Jun 2023Preliminary Change Report issued
Start:
10 Jul 2023Due:
14 Jul 2023Completion:
14 Jul 2023Responsible Committee review
Start:
14 Jul 2023Due:
26 Jul 2023Completion:
26 Jul 2023Consultation trigger
Start:
26 Jul 2023Due:
28 Jul 2023Completion:
28 Jul 2023Consultation close
Start:
28 Jul 2023Due:
18 Aug 2023Completion:
18 Aug 2023Final Change Report issued
Start:
18 Aug 2023Due:
15 Sep 2023Completion:
14 Sep 2023Responsible Committee decision
Start:
15 Sep 2023Due:
27 Sep 2023Completion:
27 Sep 202312 April 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0105 | Review of ONAGE SLAs |
|
- As a Consumer I want the Switch process to work efficiently and effectively, so that I can switch Energy Supplier without unnecessary delay or issues.
- As an ERDS and GRDS, I want to receive SNOW tickets that contain all of the relevant data to enable me to triage and resolve issues efficiently, so that Consumers do not experience unnecessary switching delays and I am able to meet my service level obligations.
- As the CSS Provider, I want the ERDS related SNOW tickets to contain all of the relevant data to enable the efficient resolution of issues without the need for a manual workaround to be utilised, so that Consumers do not experience unnecessary switching delays.
Clarification of Supplier of Last Resort Obligations under the REC
- As a Consumer when my Energy Supplier goes out of business and I am transferred to a Replacement Supplier, I want my supply transfer to be handled quickly and have confidence that my new Supplier has all the necessary data to set up my account and bill me correctly from the transfer date, and if the Replacement Supplier fails to provide the expected level of service they will be appropriately held accountable.
- As a Replacement Supplier, I want the limitations affecting my ability to meet my REC obligations to be understood by the REC Code Manager and the Performance Assurance Board, so that any breaches of obligations are considered fairly and any limitations are taken into consideration.
- As the Code Manager I want to apply appropriate and proportionate Performance Assurance Techniques, taking in to account the ability of a Replacement Supplier to meet their obligations under the REC.