Revised Implementation Date for R0011
Party Impact Assessment Issued
Start:
25 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 2022Preliminary Change Report Issued
Start:
08 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Consultation Issued
Start:
29 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Final Change Report Issued
Start:
29 Apr 2022Due:
13 May 2022Completion:
13 May 2022Responsible Committee Decision
Start:
13 May 2022Due:
17 May 2022Completion:
17 May 202201 June 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0102 | Revision of the approved solution for R0032 |
- As a Market Participant, I need the industry Market Message/Data Specification to be implemented by all Parties at the same time so that I am able to validate EMRS invoices and credits without having to request additional supporting data or without my Market Messages failing.
- As LCCC I need to delay the implementation of R0011 so that changes to industry Market Message/Data Specification can be implemented by all Parties at the same time so that industry Market Messages don’t fail validation between Parties.
Performance Assurance Report Catalogue Changes as a consequence of REC V3.0
Impact Assessments completed
Start:
23 Mar 2022Due:
16 May 2022Completion:
16 May 2022Preliminary Change Report published
Start:
16 May 2022Due:
31 May 2022Completion:
31 May 2022Consultation started
Start:
31 May 2022Due:
31 May 2022Completion:
31 May 2022Consultation completed
Start:
31 May 2022Due:
16 Jun 2022Completion:
16 Jun 2022Final Change Report published
Start:
16 Jun 2022Due:
21 Jun 2022Completion:
21 Jun 2022Responsible Committee decision
Start:
21 Jun 2022Due:
28 Jun 2022Completion:
28 Jun 202218 July 2022
- As the Code Manager I need to receive the necessary data to complete the required Performance Assurance activities post REC V3.0
- As a REC Service Provider, I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0
- As a Supplier I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0. As a MEM I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0.
Service Provider Performance Charges (DCC)
Preliminary Change Report and Consultation Issued
Start:
04 Jan 2022Due:
15 Nov 2022Completion:
15 Nov 2022Final Change Report Issued
Start:
15 Nov 2022Due:
09 Dec 2022Completion:
09 Dec 2022Responsible Committee Decision
Start:
09 Dec 2022Due:
20 Dec 2022Completion:
20 Dec 2022Send to Authority for Decision
Start:
20 Dec 2022Due:
21 Dec 2022Completion:
21 Dec 202201 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0100 | Update to Error Handling Documents |
- As the REC Code Manager, I want to ensure that REC Service Providers achieve their Service Level Agreements (SLAs) defined in REC Service Definitions, so that impacts to the REC Code Manager, REC Parties and other Service Providers, as a consequence of Service Provider underperformance, are minimised and the change process delivers to time and cost.
- As a Service Provider, I want clarity on when and how Performance Charges will be used as part of the Performance Assurance Techniques, so that I’m clear on what service levels I need to meet and the consequences of not delivering against these.
EAC information in the EES API
Solution Development and Party Engagement
Start:
29 Aug 2022Due:
07 Sep 2022Completion:
29 Aug 2022Change Proposal Withdrawal
Start:
20 Dec 2021Due:
29 Aug 2022Completion:
29 Aug 2022- As a domestic Electricity Consumer, I want to be quoted accurately for my electricity usage based on my electricity consumption, so that I can make an informed decision to accept/reject the quotation offered.
- As an Electricity Supplier, I want to have access to the most recent Metering Point consumption data to be able to provide accurate prices/quotations to a consumer based on their Electricity usage.
- As a Third-Party Intermediary (TPI), I want to have access to the most recent Metering Point consumption data to be able to provide accurate prices/quotations to a consumer based on their Electricity usage.
Amendment to REC Data Access Matrix
Solution Development
Start:
15 Dec 2021Due:
28 Mar 2022Completion:
28 Mar 2022Party Impact Assessment Issued
Start:
28 Mar 2022Due:
01 Apr 2022Completion:
01 Apr 2022Service Provider Impact Assessment Issued
Start:
01 Apr 2022Due:
12 May 2022Completion:
12 May 2022Service Provider Preliminary Impact Assessment Complete
Start:
12 May 2022Due:
31 May 2022Completion:
31 May 2022Service Provider Detailed Impact Assessment initiated
Start:
31 May 2022Due:
27 Jun 2022Completion:
01 Jul 2022Technical Expert Panel solution review
Start:
27 Jun 2022Due:
29 Jun 2022Completion:
29 Jun 2022Preliminary Change Report published
Start:
29 Jun 2022Due:
08 Jul 2022Completion:
07 Jul 2022Service Provider Detailed Impact Assessment completed
Start:
08 Jul 2022Due:
18 Jul 2022Completion:
22 Jul 2022Consultation 1 initiated
Start:
18 Jul 2022Due:
22 Jul 2022Completion:
21 Jul 2022Consultation 1 completed
Start:
22 Jul 2022Due:
12 Aug 2022Completion:
12 Aug 2022Change Panel review of updated Preliminary Change Report
Start:
12 Aug 2022Due:
16 Aug 2022Completion:
16 Aug 2022Consultation 2 initiated
Start:
16 Aug 2022Due:
18 Aug 2022Completion:
18 Aug 2022Consultation 2 completed
Start:
18 Aug 2022Due:
02 Sep 2022Completion:
02 Sep 2022Final Change Report published
Start:
02 Sep 2022Due:
23 Sep 2022Completion:
23 Sep 2022Change Panel decision
Start:
23 Sep 2022Due:
04 Oct 2022Completion:
04 Oct 202204 November 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0002 | Review of Data Specification Category in REC Baseline Statement |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.3 | 29 May 2026 | ||
| 1.3 | 29 May 2026 |
- As an Electricity Consumer, I want data associated with my electricity supply to be made consistently available to Market Participants relevant organisations, so that they have equal access to the data they use to supply my electricity or look after my meter.
- As an EES User, I want to have access to all the data items appropriate to my EES User Category so that I can operate processes without disruption, to provide a good service to my customers and meet my performance targets. As the EES Provider I want to have clarity on the data items that I should provide to EES Users appropriate to their role. As the Code Manager I want Market Participants to have access to appropriate data in EES so they can complete business processes and meet performance targets, while ensuring access to data is subject to appropriate security and controls.
Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier
Solution Development
Start:
09 Dec 2021Due:
03 Feb 2022Completion:
19 Apr 2022Party Impact Assessment Issued
Start:
03 Feb 2022Due:
22 Apr 2022Completion:
22 Apr 2022Deadline for Alternative Change Proposal Submission
Start:
22 Apr 2022Due:
27 May 2022Completion:
27 May 2022Preliminary Change Report Issued Interim
Start:
27 May 2022Due:
27 May 2022Completion:
27 May 2022Consultation Issued
Start:
27 May 2022Due:
12 Jul 2022Completion:
12 Jul 2022Final Change Report Issued
Start:
16 Aug 2022Due:
26 Aug 2022Completion:
26 Aug 2022Responsible Committee Decision
Start:
26 Aug 2022Due:
14 Sep 2022Completion:
14 Sep 2022Preliminary Change Report (Updated) Issued
Start:
12 Jul 2022Due:
12 Jul 2022Completion:
12 Jul 2022Consultation closure (extended deadline)
Start:
12 Jul 2022Due:
16 Aug 2022Completion:
16 Aug 202230 June 2023
- As a property owner or occupier I want to be to arrange for the installation of equipment for the use of the occupier, such as fitting an isolator, installing on-site generation equipment or electric vehicle charging points. I want the installer to use a Safe Isolator Provider (SIP) who is authorised to undertake the work at my instruction rather than arrange for this work to be completed through the premises’ Registered Suppliers.
- As a REC Accredited Metering Equipment Manager, I want to be able to work as a SIP and de-energise and re-energise a site on the instruction of the homeowner/landlord, so that equipment – such as an isolator, on-site generation or electric vehicle charging points can be fitted without the need to co-ordinate the work with the Registered Suppliers’ MEMs. As a Distribution Network Operator, I want to be assured that the work is only completed by a SIP that has the necessary skills and REC accreditation and has the appropriate permissions to de-energise and re-energise the supply and doesn’t introduce any additional risk to the Distribution Network.
- As the Registered Supplier, I want to know what steps the SIP who attends the site and finds the site in an unsafe situation to re-energise, will take so that my customer is not left off-supply unnecessarily. As the Registered Supplier, I want to be alerted if the SIP finds any evidence of meter tampering at the premises.
Invalid Requests for Site Technical Details
03 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0104 | Clarifying requirement for continuous billing following an Erroneous Switch |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 08 Jun 2026 | ||
| 1.0 | 08 Jun 2026 |
- As a Consumer I want my existing or new meter to be read regularly to ensure I receive accurate bills.
- As a Distribution Network Operator I want to receive appropriate Requests for Site Technical Details. As a Distribution Network Operator I want the difference between my obligations and best practice to be clear in relation to provision of Site Technical Details for sites with and without Measurement Transformers.
- As a Metering Equipment Manager I want to be provided with Site Technical Details for all relevant sites so I can correctly install, commission and maintain the Metering Equipment.
Cable Colour Identification
Initial Assessment Report published
Start:
01 Nov 2021Due:
26 Nov 2021Completion:
26 Nov 2021Change Panel review
Start:
26 Nov 2021Due:
07 Dec 2021Completion:
07 Dec 2021Preliminary Change Report issued
Start:
07 Dec 2021Due:
04 Jan 2022Completion:
31 Dec 2021Metering Expert Panel review
Start:
04 Jan 2022Due:
12 Jan 2022Completion:
12 Jan 2022Consultation starts
Start:
12 Jan 2022Due:
17 Jan 2022Completion:
25 Jan 2022Consultation ends
Start:
17 Jan 2022Due:
15 Feb 2022Completion:
15 Feb 2022Final Change Report issued
Start:
15 Feb 2022Due:
25 Feb 2022Completion:
25 Feb 2022Metering Expert Panel decision
Start:
25 Feb 2022Due:
09 Mar 2022Completion:
09 Mar 202230 June 2022
- As an electricity Consumer, I want requested meter work to take place safely and efficiently at the time and date agreed, so that I have a safe and working meter.
- As a MEM or a DNO I want clarity on how to deal with cable labelling during periods of coloured cable supply chain shortages, so that I can continue to install or maintain consumer metering.
- As a Metering Scheme Auditor, I want there to be clarity on the permitted labelling of non-standard colour coded cables used when connecting meters, so that audits can be appropriately completed.
Electricity Enquiry Service API Service Status
Initial Assessment Report published
Start:
11 Oct 2021Due:
05 Nov 2021Completion:
05 Nov 2021Analysis and Solution development activity
Start:
05 Nov 2021Due:
13 Jan 2022Completion:
Service Provider Impact Assessment completion
Start:
13 Jan 2022Due:
15 Feb 2022Completion:
REC Party Impact Assessment completion
Start:
15 Feb 2022Due:
23 Mar 2022Completion:
Preliminary Change Report issued
Start:
23 Mar 2022Due:
20 Apr 2022Completion:
Technical Expert Panel review
Start:
20 Apr 2022Due:
27 Apr 2022Completion:
Consultation starts
Start:
27 Apr 2022Due:
05 May 2022Completion:
Consultation ends
Start:
05 May 2022Due:
26 May 2022Completion:
Final Change Report issued
Start:
26 May 2022Due:
21 Jun 2022Completion:
Technical Expert Panel decision
Start:
21 Jun 2022Due:
29 Jun 2022Completion:
- As an EES User (organisation), I want a method of integrating the service status of the EES API with my systems, so that in the event of EES API outage or disruption I do not trigger unnecessary internal diagnostic activity of my IT systems and processes, and I can initiate appropriate mitigation activity to reduce impacts to my systems and/or the services I provide.
Reporting of Additional EMR Backing Data to Suppliers
Initial Assessment Report published
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
12 Nov 2021Completion:
12 Nov 2021Technical Expert Panel review
Start:
12 Nov 2021Due:
24 Nov 2021Completion:
24 Nov 2021Consultation starts
Start:
24 Nov 2021Due:
30 Nov 2021Completion:
29 Nov 2021Consultation ends
Start:
30 Nov 2021Due:
21 Dec 2021Completion:
21 Jan 2022Final Change Report issued
Start:
21 Dec 2021Due:
14 Jan 2022Completion:
14 Jan 2022Technical Expert Panel decision
Start:
14 Jan 2022Due:
26 Jan 2022Completion:
26 Jan 202230 June 2023
- As a Market Participant, I need to be able to validate EMRS invoices and credits without having to request additional supporting data.
- As EMR Settlement Ltd, I need to have an efficient mechanism in place that enables me to provide Market Participants with all the relevant data that they need to validate their invoices and credit notes, to reduce/remove the need for Market Participants to contact the service desk for additional information.