EES Access for Virtual Lead Parties

Date of latest update
Type
Change
ID
R0054
Change Category
Change Path
Priority
Urgent
No
Latest Update
03/04/2023 - The Data Access Matrix changes went live on 04 November 2022, the technical changes to EES were implemented alongside R0022 on 03 April 2023.
Summary
This Change Proposal seeks to allow Virtual Lead Parties (VLP) access to the Electricity Enquiry Service (EES), to allow them to efficiently register their customers for balancing services under the Balancing and Settlement Code (BSC).
Proposer
Ann Perry
Change Plan

Service Provider Impact Assessment

Completed

Start:

17 Jun 2022

Due:

22 Jul 2022

Completion:

22 Aug 2022

Preliminary Change Report Issued

Completed

Start:

22 Jul 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Issued

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Complete

Completed

Start:

02 Sep 2022

Due:

16 Sep 2022

Completion:

16 Sep 2022

Final Change Report Issued

Completed

Start:

16 Sep 2022

Due:

14 Oct 2022

Completion:

14 Oct 2022

Responsible Committee Decision

Completed

Start:

14 Oct 2022

Due:

26 Oct 2022

Completion:

26 Oct 2022
Impacted Consumers
Impacted REC Services
Status
Implementation Date
Status Live
EMAR Version 01.04.2023_live
Included changes Affected REC Items
R0100 Update to Error Handling Documents
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As an Energy Consumer, I want my VLP to have access to the data needed to correctly register me in a timely manner, so there aren’t delays in the delivery of my service.
  2. As a VLP, I want to have access to all the data I need to register my customers so I can deliver the service they have requested, without delay.
  3. As a VLP, I want to be able to use the EES to find the MPAN of a customer using their address information, to enable me to reliably gather this data to without delay or further engagement with my customer.
Proposed Solution Document
Document title
R0054 - Draft DAM Change
Archive
Off
Document title
R0054 - Draft Legal Text
Archive
Off
Problem Statement
VLPs are required to provide their customer’s MPAN as part of the registration process, as per the Balancing and Settlement Code (BSC). VLPs do not currently have access to the EES to enable an MPAN search and they have no reliable means to acquire the MPAN, other than asking their customer to provide it. This could potentially lead to delays in the registration process and may result in an increased risk of inaccurate data, detrimentally impacting the service VLPs are able to provide to their customers.
R0054 - Initial Assessment Report v1.0 (Approved)
R0054 - Change Proposal Plan v1.0 (Approved)
R0054 - Preliminary Change Report v1.0 (Published for Consultation)
R0054 - Non-Confidential Consultation Responses
R0054 - Final Change Report v2.0
Company Name
-
Review status
Review required

24/7 Emergency Metering Service

Date of latest update
Type
Change
ID
R0053
Change Category
Priority
Urgent
No
Latest Update
01/05/25 - Proposal withdrawn at proposers request.
Summary
This change has been raised to address the issue that Suppliers currently are not required to provide a 24/7 emergency metering service that enables a Consumer to speak to an agent and/or receive a visit from a field operative outside normal business hours when faced with power loss situation relating to a metering issue. This Change Proposal has been raised to assess and consider the options to address this issue.
Proposer
bryan.heap
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As an Energy Consumer, I want my metering fault to be identified and fixed as soon as possible, so that I am not left in a situation where I have no electricity for an extended period. I want to be able to contact the correct Party to fix my metering fault. I want my personal circumstances to be taken in to account when arranging for a fault to be fixed out of standard working hours.
  2. As a DNO, where there is a meter fault identified I want to be able to contact the Energy Supplier to rectify this, no matter what day or time this is identified, so that Consumers are not left without power for extended periods, during which time they may require ongoing help, support and communication. As an Energy Supplier, I want to provide my Customers with accurate and relevant Emergency contact information. As an Energy Supplier, I want to be able to respond to meter faults in a timely manner and not leave Consumers without power for an extended period.
  3. As a MEM, I want to be notified, in a timely manner, of faults that occur on Metering assets I am responsible for, so that I am able to rectify these without undue detriment being experienced by Consumers
Problem Statement
In situations where an Electricity Consumer experiences a loss of power, the DNOs who attend site to investigate and resolve the issues, are unable to do so when there is a meter issue, which is the responsibility of the Energy Supplier and it’s Appointed agents. When an issue occurs out of hours, or when an Energy Supplier does not have an out of hours metering service in operation, Consumers can be left without power for an extended period, this can create a safety or health concern, particularly for vulnerable Consumers or vulnerable members of their household.
Stages Selection
R0053 - Downloadable Change Proposal Form
R0053 - Change Proposal Plan v1.0 (pre-approval) 27/02/2023
R0053 - Initial Assessment Report v1.1 (Pre-Approval) 06.03.23
R0053 - Initial Assessment Report v2.0 (Approved) 07.03.2023
R0053 - Change Proposal Plan v2.0 (Approved) 07.03.2023
Company Name
Electricity North West Limited
Review status
Review required

Switch Request Objections (Change of Occupier)

Date of latest update
Type
Change
ID
R0051
Change Category
Change Path
Priority
Urgent
No
Latest Update
26/01/2024 - Withdrawn following adoption window closure.
Summary
This Change Proposal looks to clarity obligations regarding the losing suppliers' rights to object and the circumstances surrounding registrations by gaining suppliers, following the migration from the MRA to the REC.
Proposer
admin
Impacted Consumers
Impacted REC Services
Status
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Stages Selection
R0051 - Downloadable CP form
Company Name
Business Energy Direct
Review status
Review required

Intellectual Property Rights and Services Data Main Body changes

Date of latest update
Type
Change
ID
R0049
Change Category
Change Path
Priority
Urgent
No
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Summary
The Central Registration Services (CRS) intellectual property rights (IPR) provisions in the Code were drafted before designation of v1.0 of the Code and primarily seek to deal with the CRS Services IPR as if it were IPR developed and owned by the CRS Provider or its contractors. In reality, much of the solution is built upon third party-owned software or platforms/services that are available to the market. Notwithstanding certain concessions were drafted in Clause 13.5 of the Code at designation, the scope of CRS Service IPR refers to some now obsolete terms and concepts and ought to be amended to clarify what the CRS Provider actually owns or is responsible for, to alleviate the existing ambiguity. Potential to amend Clause 13 of the Code as proposed in the attached mark-up, with consequential amendments to the associated definitions in Schedule 1 (Interpretation and Definitions). The definition “User” should be deleted from the Code and the defined terms “CSS User” or “REC Service User” (as applicable) used in substitution.
Proposer
Cordelia Grey
Change Plan

Party Impact Assessment Published

Completed

Start:

20 May 2022

Due:

04 Jul 2024

Completion:

04 Jul 2024

Preliminary Change Report & Consultation Published

Completed

Start:

04 Jul 2024

Due:

08 Aug 2024

Completion:

08 Aug 2024

Consultation Closes

Completed

Start:

08 Aug 2024

Due:

30 Aug 2024

Completion:

30 Aug 2024

Final Change Report Issued

Completed

Start:

30 Aug 2024

Due:

10 Sep 2024

Completion:

10 Sep 2024

Responsible Committee Decision

Completed

Start:

10 Sep 2024

Due:

17 Sep 2024

Completion:

17 Sep 2024

Appeal Window Closure

Not Started

Start:

17 Sep 2024

Due:

01 Oct 2024

Completion:

Impacted Consumers
Status
Implementation Date
Status Live
EMAR Version 08.11.2024_live
Included changes Affected REC Items
R0105 Review of ONAGE SLAs
  • Schedule 14 - Metering Operations
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. N/A – No tangible Consumer impact identified.
  2. As a REC Participant (Service Provider/User), I want the Code to clearly stipulate IPR requirements, so that CRS provisions and arrangements are readily identifiable.
Proposed Solution Document
Document title
R0049-Draft REC Main Body Changes V1.0 04.07.24
Archive
Off
Problem Statement
There is uncertainty as to the scope of the various classes of Intellectual Property Rights (IPR) covered in Clause 13 of the REC Main Body (including the extent to which any IPR may exist in certain data, and the use of obsolete terms and concepts). As a result, there is a risk that the relevant industry stakeholders referred to in Clause 13 are unable to grant the licences and indemnities as described in that Clause. The current wording of Clause 5.3 of the REC Main Body requires amendments to ensure it correctly reflects the relationship between CRS Provider and RECCo, the services being provided and the entitlement to input VAT as a recipient of the CRS.
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
SME Role
Lead Assurance Analyst
R0049 - Change Proposal Form
R0049 - Main Body amendments proposed by DCC
R0049 Change Proposal Plan (Approved) V1.0 03.07.24
R0049 Initial Assessment Report (Approved) V1.0 03.07.24
R0049 - Consolidated IA Responses V1.0 08.08.24
R0049 Change Report (Published for Consultation) V1.0 08.08.24
R0049 Consolidated Consultation Responses V1.0 02.09.24
R0049 Final Change Report (Approved) V2.0 17.09.24
Company Name
-
Review status
Review required

MHHS Programme Changes required to Central Switching Service

Date of latest update
Type
Change
ID
R0044
Change Category
Urgent
Yes
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
This change has been raised by the Market-wide Half-Hourly Settlement (MHHS) Programme to implement the necessary Retail Energy Code (REC) changes in relation to a new Data Communications Company User Role for the Meter Data Retrieval service (MDR). The new role required by the MHHS Target Operating Model will be established by the Smart Energy Code Modification Proposal, SEC MP162. This REC change will provide the new system interfaces required for sharing the MDR’s Registration Data.
Proposer
Jason Brogden
Change Plan

Analysis and Requirements Gathering started

Completed

Start:

29 Apr 2022

Due:

05 May 2022

Completion:

05 May 2022

Present Updated Change Proposal Plan to REC Change Panel

Completed

Start:

05 May 2022

Due:

21 Jun 2022

Completion:

21 Jun 2022

Service Provider Impact Assessment initiated

Completed

Start:

21 Jun 2022

Due:

11 Jul 2022

Completion:

05 Jul 2022

Service Provider Impact Assessment completed

Completed

Start:

11 Jul 2022

Due:

15 Aug 2022

Completion:

10 Aug 2022

Present extended Change Proposal Plan to Change Panel

Completed

Start:

15 Aug 2022

Due:

06 Sep 2022

Completion:

06 Sep 2022

Requirement refinement and validation of Detailed Impact Assessment

Completed

Start:

06 Sep 2022

Due:

27 Sep 2022

Completion:

27 Sep 2022

Provide extended Change Proposal Plan to Change Panel

Completed

Start:

28 Oct 2022

Due:

31 Oct 2022

Completion:

25 Oct 2022

Preliminary Change Report Issued

Completed

Start:

27 Sep 2022

Due:

28 Oct 2022

Completion:

27 Oct 2022

Responsible Committee Review of the Preliminary Change Report

Completed

Start:

31 Oct 2022

Due:

01 Nov 2022

Completion:

01 Nov 2022

Consultation started

Completed

Start:

01 Nov 2022

Due:

04 Nov 2022

Completion:

03 Nov 2022

Consultation ended

Completed

Start:

04 Nov 2022

Due:

25 Nov 2022

Completion:

25 Nov 2022

Final Change Report issued

Completed

Start:

25 Nov 2022

Due:

09 Dec 2022

Completion:

09 Dec 2022

Responsible Committee ex-committee decision

Completed

Start:

09 Dec 2022

Due:

13 Dec 2022

Completion:

13 Dec 2022

Authority Determination

Completed

Start:

13 Dec 2022

Due:

02 Feb 2023

Completion:

02 Feb 2023
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version _live
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Harriet Truss
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As the SMDSP, I want to be able to validate that an SMDR is registered so that I can provide them with access to the Metering Points to which they are registered.
  2. As a SMDR, I want to be able to access the Metering Points I am registered to so that I can collect settlement data from those meters
  3. As the CSS Provider, I want the CSS to be able to receive notifications from the Registration Service on the appointment/de-appointment of an SMDR so that I can send the appointment data to the SMDSP. As the CSS Provider, I want the CSS to be able to provide SMDR appointment data to the SMDSP.
Proposed Solution Document
Document title
R0044 - Draft Legal Text
Archive
Off
Document title
R0044 Final Legal Text (Post Consultation)
Archive
Off
Document title
Consultation page
Archive
Off
Document title
Link to EMAR Change Set
Archive
Off
Problem Statement
The MHHS Target Operating Model requires that the appointment data of the Smart Meter Data Retriever (SMDR) is available to the Smart Meter Data Service Provider (SMDSP), so that the SMDSP can provide SMDRs with access to the Smart Meters at Metering Points they are registered to. Currently the new SMDR role and appointment data do not exist in, nor can they be made available from, CSS as this is a new industry operating model.
SME
SME Role
Lead Technical Analyst
R0044 - Change Proposal form v1.0
MHHSP-BP003A-CSSandDCC Update - v3.0
R0044 Change Proposal Plan v5.0 (Approved)
R0044 Initial Assessment Report v1.0 (Approved)
R0044 - Preliminary Change Report v1.0 (Approved)
R0044 - Consolidated Consultation Responses v1.0
R0044 - Final Change Report v2.0 (Post-Vote)
R0044 - Ofgem Decision
Company Name
MHHS Programme
Review status
Review required

REC V3.0

Date of latest update
Type
Change
ID
R0041
Change Category
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Alasdair MacMillan
Change Plan

Legal text baselined

Completed

Start:

10 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Final Change Report Issued

Completed

Start:

13 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Responsible Committee Decision

Completed

Start:

20 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Authority Determination (Original)

Completed

Start:

07 Jun 2022

Due:

20 Jun 2022

Completion:

17 Jun 2022

Authority Determination (revoked and re-issued)

Completed

Start:

20 Jun 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 18.07.2022_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
  3. As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
  4. As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.
Proposed Solution Document
Document title
REC V3.0 Baselined documents
Archive
Off
Document title
REC v3.0 Baselined documents (REC Portal)
Archive
Off
Problem Statement
Changes are required to the REC, to ensure the appropriate obligations, processes and provisions are defined within the REC at CSS go-live, enabling successful transition to enduring governance and operational arrangements developed as part of Ofgem’s Switching Programme.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0041 - Change Proposal Form
Letter from the Authority to the REC Code Manager - REC V3.0 Authority Change Proposal
R0041 - Change Proposal Plan v1.0 (Approved)
R0041 - Initial Assessment Report v2.0 (Approved)
R0041 - Final Change Report v3.0 (Post-Vote)
R0041 Authority Decision
Company Name
Ofgem
Review status
Review required

Prepayment Credit Balance Transfer Process

Date of latest update
Type
Change
ID
R0037
Change Category
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
04/08/2026 - On 04 August 2026, the REC Change Panel approved this Proposal Plan.
Summary
This Change Proposal seeks to develop an agile, efficient, Consumer-centric solution for the transfer of credit balance as part of a smart prepayment Switch.
Proposer
Simon Bevis
Change Plan

Initial Analysis

Completed

Start:

10 Mar 2022

Due:

30 Jun 2022

Completion:

Present updated Change Proposal Plan to Change Panel

Completed

Start:

30 Jun 2022

Due:

19 Jul 2022

Completion:

Solution Development Complete

Completed

Start:

30 Jan 2023

Due:

29 Feb 2024

Completion:

29 Feb 2024

Present Updated Change Proposal Plan to Change Panel

Completed

Start:

19 Jul 2022

Due:

08 Nov 2022

Completion:

Present Updated Plan to Change Panel

Completed

Start:

08 Nov 2022

Due:

17 Jan 2023

Completion:

17 Jan 2023

Service Provider Impact Assessment

Completed

Start:

17 Jan 2023

Due:

30 Jan 2023

Completion:

30 Jan 2023
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
florentina.monea
Date of Update to Priority
Solution Development
Proposed Solution Document
Document title
R0037 - Draft Legal Text v1.0
Archive
Off
Document title
R0037 - Solution Document v2.0
Archive
Off
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
R0037 - CP Form (Downloadable version)
R0037 Consolidated Party IA Responses PUBLIC v1.0
R0037 - Change Proposal Plan V6.0 (Approved) 05.03.24
R0037 - Initial Assessment Report v1.0 (Approved) 06.04.22
R0037 Consolidated RFI Responses PUBLIC v1.0
R0037 Change Report (Proposal Plan) Approved
Company Name
Utilita Energy Limited
Review status
Review required

Market Stabilisation Charge – Administration

Date of latest update
Type
Change
ID
R0035
Change Category
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Jon Dixon
Change Plan

Party Impact Assessment initiated

Completed

Start:

22 Feb 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Party Impact Assessment completed

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Preliminary Change Report issued

Completed

Start:

29 Apr 2022

Due:

06 May 2022

Completion:

06 May 2022

Issued to Responsible Committee for review (ex-Committee)

Completed

Start:

06 May 2022

Due:

10 May 2022

Completion:

10 May 2022

Consultation initiated

Completed

Start:

10 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Consultation completed

Completed

Start:

13 May 2022

Due:

01 Jun 2022

Completion:

01 Jun 2022

Final Change Report issued

Completed

Start:

01 Jun 2022

Due:

10 Jun 2022

Completion:

10 Jun 2022

Responsible Committee Decision (ex-Committee)

Completed

Start:

10 Jun 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Authority Determination

Completed

Start:

14 Jun 2022

Due:

24 Jun 2022

Completion:

27 Jun 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 30.06.2022_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Domestic Consumer, I want to be able to choose my Energy Supplier and a tariff from a range of competitive options, so that I can take advantage of cheaper deals as they become available.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
  3. As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
  4. As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send my invoices/credit notes, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I make to RECCo or at an appropriate time for my organisation. As a Domestic Supplier, I want to understand how I could dispute an invoice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly
Proposed Solution Document
Document title
Legal Text (tracked changes)
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A and introduced into the REC by Change Proposal R0034. A change is needed to the REC to set out the charging and payment mechanism, and to introduce the necessary governance arrangements to allow these MSC payments to be administered by RECCo.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0035 - CP Form (Downloadable version)
Ofgem Decision document - Short Term Interventions
MSC calculation guidance
Gas SLC Modified Decision Notice
Elec SLC Modified Decision Notice
R0035 - High level Solution Overview v1.0
R0035 - Change Proposal Plan v2.0 (Approved)
R0035 - Initial Assessment Report v2.0 (Approved)
R0035 - Consolidated IA responses v1.0
R0035 - Proposed Solution v2.0
R0035 - Preliminary Change Report v2.0 (Approved)
R0035 - Consolidated consultation responses v1.0
R0035 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0035
Company Name
RECCo
Review status
Review required

Erroneous Transfer Cancellations

Date of latest update
Type
Change
ID
R0030
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Summary
Erroneous Switches (ESs) are currently being cancelled without a defined process or full audit trail. This Change Proposal seeks to introduce a defined process for Energy Suppliers to be able to cancel an ES in specific scenarios.
Proposer
Lorna Mallon
Change Plan

Solution Development

Completed

Start:

13 Jan 2022

Due:

22 Apr 2022

Completion:

22 Apr 2022

Party Impact Assessment Issued

Completed

Start:

22 Apr 2022

Due:

06 May 2022

Completion:

06 May 2022

Preliminary Change Report Issued

Completed

Start:

06 May 2022

Due:

08 Jul 2022

Completion:

08 Jul 2022

Responsible Committee Review

Completed

Start:

08 Jul 2022

Due:

19 Jul 2022

Completion:

19 Jul 2022

Consultation Issued

Completed

Start:

19 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 30.06.2023_live
Implementation Status
Date Raised
Fuel
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Consumer I want to receive my bills when expected, from the Supplier of my choice without delays caused by being switched incorrectly and not being resolved in a timely manner. As a Consumer, in the event that my Supplier has exited the market and my supply cannot be returned to my original Supplier, I want the Gaining ET Supplier to have the ability to terminate any ET process that has already been initiated so that I am able to choose my preferred Supplier and switch without delay or penalty.
  2. As a Consumer, if Energy Suppliers need to share my data to resolve a switching issue, I want Suppliers to share my personal data securely so that my data is protected.
  3. As an Energy Supplier, where appropriate, I need to be able to cancel an ET effectively and efficiently, so that I can bill my Consumers accurately and timely. As an Energy Supplier, where appropriate, I need to be able to cancel an ET so that I supply Consumers with whom I have a valid contract.
  4. As The Code Manager I need to be able to identify when an ET has been cancelled so that I have a clear audit trail and can monitor performance effectively.
Proposed Solution Document
Document title
R0030 Pre Consultation Solution Documents
Archive
Off
Document title
R0030 - Final Solution Documents
Archive
Off
Document title
R0030 - EMAR Change Set (Final)
Archive
Off
Problem Statement
Erroneous Transfers are being cancelled by Suppliers, which is currently not permitted under the REC. There is no consistent defined process or audit trail. In the event of a Supplier of Last Resort (SoLR) being appointed, or on a Change of Occupier at a premise, the Gaining Supplier currently has no way to formally cancel an ET after it has been initiated. This can cause Switching and/or Billing delays for Consumers whilst Energy Suppliers attempt to resolve an outstanding or open ET. For Energy Suppliers this can mean they are supplying Consumers with whom they have no Valid Contract, resulting in additional Guaranteed Standards of Performance (GSOP) Payments and increased Consumer dissatisfaction. The Performance Assurance Board (PAB) has no way to identify the difference between the process legitimately closing without resolution, and an Energy Supplier not meeting their obligations in the code to properly resolve an ET. As a result, the PAB are unable to differentiate the performance of Energy Suppliers between those that are closed down legitimately or those being closed inappropriately.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
Erroneous Transfer Cancellations - Change Proposal Form
R0030 - Consolidated Impact Assessment Responses
R0030 Change Proposal Plan v1.0 (Approved)
R0030 - Initial Assessment Report v1.0 (Approved)
R0030 - Preliminary Change Report v2.0 (Approved)
Non Confidential Consultation Responses
R0030 Final Change Report v2.0 (Post-Vote)
Company Name
Scottish Power
Review status
Review required

Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier

Date of latest update
Type
Change
ID
R0021
Change Category
Priority
Urgent
No
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Summary
Currently only the Registered Supplier can instruct a Metering Equipment Manager (MEM) to work on their metering asset. There is no ability to request that a single MEM completes work on multiple properties that may have different Electricity Suppliers. This creates barriers to developing solutions for local authorities, private and social housing landlords who are refurbishing premises or to help any premise owner (whether domestic or non-domestic) install new equipment to facilitate Low & Zero Carbon Technology (LZCT) installation such as the retro-fit of Electric Vehicle Charging (EVC) Points to homes and business premises. This Change Proposal will introduce a new role for existing accredited MEMs that will enable them to accept instructions to undertake a limited set of activities at the request of the premise owners without the need to use the Registered Suppliers’ MEMs.
Proposer
Colette Baldwin
Change Plan

Solution Development

Completed

Start:

09 Dec 2021

Due:

03 Feb 2022

Completion:

19 Apr 2022

Party Impact Assessment Issued

Completed

Start:

03 Feb 2022

Due:

22 Apr 2022

Completion:

22 Apr 2022

Deadline for Alternative Change Proposal Submission

Completed

Start:

22 Apr 2022

Due:

27 May 2022

Completion:

27 May 2022

Preliminary Change Report Issued Interim

Completed

Start:

27 May 2022

Due:

27 May 2022

Completion:

27 May 2022

Consultation Issued

Completed

Start:

27 May 2022

Due:

12 Jul 2022

Completion:

12 Jul 2022

Final Change Report Issued

Completed

Start:

16 Aug 2022

Due:

26 Aug 2022

Completion:

26 Aug 2022

Responsible Committee Decision

Completed

Start:

26 Aug 2022

Due:

14 Sep 2022

Completion:

14 Sep 2022

Preliminary Change Report (Updated) Issued

Completed

Start:

12 Jul 2022

Due:

12 Jul 2022

Completion:

12 Jul 2022

Consultation closure (extended deadline)

Completed

Start:

12 Jul 2022

Due:

16 Aug 2022

Completion:

16 Aug 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 30.06.2023_live
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
colette.baldwin
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a property owner or occupier I want to be to arrange for the installation of equipment for the use of the occupier, such as fitting an isolator, installing on-site generation equipment or electric vehicle charging points. I want the installer to use a Safe Isolator Provider (SIP) who is authorised to undertake the work at my instruction rather than arrange for this work to be completed through the premises’ Registered Suppliers.
  2. As a REC Accredited Metering Equipment Manager, I want to be able to work as a SIP and de-energise and re-energise a site on the instruction of the homeowner/landlord, so that equipment – such as an isolator, on-site generation or electric vehicle charging points can be fitted without the need to co-ordinate the work with the Registered Suppliers’ MEMs. As a Distribution Network Operator, I want to be assured that the work is only completed by a SIP that has the necessary skills and REC accreditation and has the appropriate permissions to de-energise and re-energise the supply and doesn’t introduce any additional risk to the Distribution Network.
  3. As the Registered Supplier, I want to know what steps the SIP who attends the site and finds the site in an unsafe situation to re-energise, will take so that my customer is not left off-supply unnecessarily. As the Registered Supplier, I want to be alerted if the SIP finds any evidence of meter tampering at the premises.
Proposed Solution Document
Document title
R0021 - Final Approved legal text
Archive
Off
Document title
R0021 - Proposed new Market Message v1.0
Archive
Off
Document title
R0021 - Draft Legal Text
Archive
Off
Document title
R0021 - Webinar 2 March 2023 - Draft Q & A Responses v0.3
Archive
Off
Problem Statement
It is difficult for landlords of local authority, social housing developments or private landlords of homes and businesses to co-ordinate the refurbishment of properties where they need the electricity supply to be de-energised to allow work being completed and the supply re-energised. Currently the landlord needs to liaise with the Electricity Supplier of each premise independently to arrange for the appointed MEM to attend and de-energise each supply point and then re-energise the site when the work is completed, as currently only the Registered Supplier’s appointed MEM or the DNO is permitted to undertake the work.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0021 - Change Proposal Plan v2.0 (Approved)
R0021 - Party IA Consolidated Responses
R0021 - Initial Assessment Report v1.0 (Approved)
R0021 - FAQs following Impact Assessment
R0021 - Preliminary Change Report v2.0 (Approved)
NAPIT Survey Results
R0021 - Consultation Non-confidential Consolidated Responses
R0021 - Final Change Report (Post-Vote)
R0021 Authority Decision
Company Name
-
Review status
Review required