Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms

Date of latest update
Type
Change
ID
R0043
Change Category
Priority
Urgent
No
Latest Update
28/06/2024 - Change implemented as part of the June 2024 REC Release
Summary
This Change Proposal is to introduce new processes which will allow a Crowded Meter Room Co-ordinator (CMRC) to contract with a REC accredited Metering Equipment Manager (MEM) to act on behalf of the CMRC, so that they may resolve issues in a Crowded Meter Room (CMR) on behalf of all Registered Suppliers within that meter room. The MEMs undertaking this work on behalf of the CMRC will be referred to as the Crowded Meter Room MEM (CMRM).
Proposer
David Jones
Change Plan

Sandbox Decision

Completed

Start:

22 Apr 2022

Due:

29 Nov 2022

Completion:

29 Nov 2022

Sandbox Trial Commences

In Progress

Start:

29 Nov 2022

Due:

01 Feb 2023

Completion:

Impact Assessment Window

Completed

Start:

06 Jun 2023

Due:

09 Jun 2023

Completion:

09 Jun 2023

Present Extended Plan to Responsible Committee

Completed

Start:

01 Feb 2023

Due:

06 Jun 2023

Completion:

06 Jun 2023

Preliminary Change Report Published

Completed

Start:

09 Jun 2023

Due:

04 Aug 2023

Completion:

02 Aug 2023

Consultation Issued

Completed

Start:

04 Aug 2023

Due:

18 Aug 2023

Completion:

18 Aug 2023

Final Change Report Published

Completed

Start:

18 Aug 2023

Due:

08 Dec 2023

Completion:

10 Nov 2023

Responsible Committee Decision

Completed

Start:

08 Dec 2023

Due:

19 Dec 2023

Completion:

19 Dec 2023
Status
Implementation Date
Status Live
EMAR Version 28.06.2024_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Consumer I want to be able to have a working Smart Meter that can communicate with my Energy Supplier so that I can receive the benefits of smart metering
  2. As a property owner I want to be able to have Smart Meters installed in my properties where there are currently issues with meter room space or other technical constraints preventing installation so that my tenants can access the benefits of having a Smart Meter. As a property owner I want a co-ordinated and managed process for resolving crowded meter room issues so that I am not contacted by or dealing with multiple Suppliers or metering agents for a single property.
  3. As an Energy Supplier, I need to be able to send and receive data, from the CMRC related to interference, faults, or damage to my equipment so that I can fulfil my obligations. As an Energy Supplier I need a coordinated approach to resolving the crowded meter room to enable me to meet my regulatory obligations related to Smart Meter installations and Communications. As an Energy Supplier, I want to know of CMR works being carried out so that I am informed of relevant updates regarding RMPs that I supply. In addition, I wish to be informed if the CMRM identifies any metering issues during their initial assessment or rectification works
  4. As a Distribution Network Operator, I need to be able to send and receive data, from the CMRC related to danger, interference, or damage to my equipment so that I can fulfil my obligations.
  5. As a MEM I need a co-ordinated approach to resolving the CMR issues, to enable me to install working Smart Meters on site.
Proposed Solution Document
Document title
R0043 - Solution Overview (10.11.2023)
Archive
Off
Document title
R0043 Legal Text (10.11.2023)
Archive
Off
Document title
R0043 Data Specification (22.03.2024)
Archive
Off
Problem Statement
For many Multiple Dwelling Units (MDU), Alt HAN Co equipment is required. This needs to be installed near to the electricity Smart Meter, connected to the tails of that Smart Meter, and requires at least one further device in the Consumer premises. However, the installation of HAN equipment can be inhibited by Crowded Meter Room (CMR) for the installation of alternative HAN and smart equipment. The objective of the CMR work is to leave a meter room ready for Energy Suppliers to proceed with their installations to meet their smart metering rollout obligations. Without the ability to install the alternative HAN wired bridge device in a CMR, Energy Suppliers will ultimately be unable to establish a HAN with the associated premises in the MDU
SME
SME Role
Lead Technical Analyst
DCP400 Crowded Meter Room Data Flows.pptx
DCP 400 Introduction to CMR.pptx
R0043 - Change Proposal Plan v5.0 (Approved)
R0043 - Initial Assessment Report v1.0 (Approved)
Alt HAN Co - Target Operating Model
R0043 FAQs v1.1 (08.11.2023)
Crowded Meter Room Pilot overview 14.07.2023
Non Confidential Consolidated Party Impact Assessment Responses
Preliminary Change Report (Approved) 15.08.2023
Crowded Meter Room Webinar 10.08.2023
R0043 - Non Confidential Consultation Response
R0043 Authority Decision
R0043 Final Change Report V2.1 (Approved)
Company Name
-
Review status
Review required

Performance Assurance Board Terms of Reference

Date of latest update
Type
Change
ID
R0042
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
_
Summary
-
Proposer
Performance Assurance
Change Plan

Solution Walkthrough

Completed

Start:

14 Apr 2022

Due:

17 May 2022

Completion:

17 May 2022

Change Proposal Plan Approval

Completed

Start:

17 May 2022

Due:

17 May 2022

Completion:

17 May 2022

Preliminary Change Report Published

Completed

Start:

17 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Consultation Start

Completed

Start:

20 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Consultation End

Completed

Start:

20 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Responsible Committee Decision

Completed

Start:

07 Jun 2022

Due:

05 Jul 2022

Completion:

05 Jul 2022

Appeals Window Closes

Not Started

Start:

05 Jul 2022

Due:

19 Jul 2022

Completion:

Status
Implementation Date
Status Live
EMAR Version 18.07.2022_live
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Jonathan Holland
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a REC Service Provider, I need the REC PAB to be able to make decisions on emergency operational change appeals and derogation requests in a timely manner, to ensure the Switching Service remains operational and effective.
  2. As a REC PAB member, I need to be able to make decisions on emergency operational change appeals and derogation requests in a timely manner, to ensure the Switching Service remains operational and effective.
  3. As a member of the Switching CAB, I need the REC PAB to make decisions on emergency operational change appeals and derogation requests in a timely manner, to ensure the Switching Service remains operational and effective. As a REC PAB Member, I need the quoracy requirements to be effective, so that meetings can go ahead and make decisions without the need to support additional ex-committee processes.
Proposed Solution Document
Document title
REC PAB - ToR - REC v3.0 Draft
Archive
Off
Problem Statement
Following the implementation of REC V3.0, the current REC PAB ToR will not support extraordinary meetings and quoracy arrangements driven by the Switching CAB or the appeals route from the Switching CAB to the REC PAB. This change seeks to update the REC PAB ToR to fully represent the changes being implemented as part of REC V3.0, and to also address lessons learnt during the REC PAB’s first year of operation.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
R0042 - CP Form (Downloadable version)
R0042 - Change Proposal Plan v1.0 (Approved)
R0042 - Preliminary Change Report v1.0 (Approved)
R0042 - Initial Assessment Report v1.0 (Approved)
R0042 - Final Change Report v2.0 (Approved)
R0042 - Consolidated Consultation Responses
Company Name
REC Code Manager - Performance Assurance
Review status
Review required

REC V3.0

Date of latest update
Type
Change
ID
R0041
Change Category
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Alasdair MacMillan
Change Plan

Legal text baselined

Completed

Start:

10 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Final Change Report Issued

Completed

Start:

13 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Responsible Committee Decision

Completed

Start:

20 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Authority Determination (Original)

Completed

Start:

07 Jun 2022

Due:

20 Jun 2022

Completion:

17 Jun 2022

Authority Determination (revoked and re-issued)

Completed

Start:

20 Jun 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 18.07.2022_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
  3. As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
  4. As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.
Proposed Solution Document
Document title
REC V3.0 Baselined documents
Archive
Off
Document title
REC v3.0 Baselined documents (REC Portal)
Archive
Off
Problem Statement
Changes are required to the REC, to ensure the appropriate obligations, processes and provisions are defined within the REC at CSS go-live, enabling successful transition to enduring governance and operational arrangements developed as part of Ofgem’s Switching Programme.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0041 - Change Proposal Form
Letter from the Authority to the REC Code Manager - REC V3.0 Authority Change Proposal
R0041 - Change Proposal Plan v1.0 (Approved)
R0041 - Initial Assessment Report v2.0 (Approved)
R0041 - Final Change Report v3.0 (Post-Vote)
R0041 Authority Decision
Company Name
Ofgem
Review status
Review required

Revised Implementation Date for R0011

Date of latest update
Type
Change
ID
R0039
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
patrick.bibby
Change Plan

Party Impact Assessment Issued

Completed

Start:

25 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Preliminary Change Report Issued

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Consultation Issued

Completed

Start:

29 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Final Change Report Issued

Completed

Start:

29 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Responsible Committee Decision

Completed

Start:

13 May 2022

Due:

17 May 2022

Completion:

17 May 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 01.06.2022_live
Included changes Affected REC Items
R0102 Revision of the approved solution for R0032
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Market Participant, I need the industry Market Message/Data Specification to be implemented by all Parties at the same time so that I am able to validate EMRS invoices and credits without having to request additional supporting data or without my Market Messages failing.
  2. As LCCC I need to delay the implementation of R0011 so that changes to industry Market Message/Data Specification can be implemented by all Parties at the same time so that industry Market Messages don’t fail validation between Parties.
Problem Statement
Following a review of its delivery pipeline, the LCCC has determined it is unable to deploy the changes required in time for the current approved implementation date of 04 November 2022. In order to communicate a revised date and to limit the impacts to industry parties and delivery partners, this change needs to be assessed as a matter of urgency.
R0039 Change Proposal Form
R0039 - Change Proposal Plan v1.0 (Approved)
R0039 Initial Assessment Report v1.0
R0039 Preliminary Change Report v1.0
R0039 - Final Change Report v2.0
Company Name
Low Carbon Contracts Company
Review status
Review required

Performance Assurance Report Catalogue Changes as a consequence of REC V3.0

Date of latest update
Type
Change
ID
R0038
Change Category
Change Path
Priority
Urgent
No
Latest Update
_
Summary
_
Proposer
Performance Assurance
Change Plan

Impact Assessments completed

Completed

Start:

23 Mar 2022

Due:

16 May 2022

Completion:

16 May 2022

Preliminary Change Report published

Completed

Start:

16 May 2022

Due:

31 May 2022

Completion:

31 May 2022

Consultation started

Completed

Start:

31 May 2022

Due:

31 May 2022

Completion:

31 May 2022

Consultation completed

Completed

Start:

31 May 2022

Due:

16 Jun 2022

Completion:

16 Jun 2022

Final Change Report published

Completed

Start:

16 Jun 2022

Due:

21 Jun 2022

Completion:

21 Jun 2022

Responsible Committee decision

Completed

Start:

21 Jun 2022

Due:

28 Jun 2022

Completion:

28 Jun 2022
Status
Implementation Date
Status Live
EMAR Version 18.07.2022_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As the Code Manager I need to receive the necessary data to complete the required Performance Assurance activities post REC V3.0
  2. As a REC Service Provider, I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0
  3. As a Supplier I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0. As a MEM I need to understand all the data that I am required to share and from when, with the Code Manager required for Performance Assurance activities post REC V3.0.
Proposed Solution Document
Document title
Updated Proposed changes required to the PARC
Archive
Off
Problem Statement
Following the implementation of REC V3.0, the Code Manager (Performance Assurance) will need to receive the data necessary for them to complete their Performance Assurance activities post REC V3.0 The Performance Assurance Report Catalogue requires a change to include the new and updated Data Items. These are required to support the monitoring of Retail Risks included in the revised Performance Assurance Risk Register and give REC Parties clarity on the data they are required to provide.
Change Proposal Form
R0038 Change Proposal Plan v2.0 (Approved)
R0038 Initial Assessment Report
R0038 - Consolidated Impact Assessment Responses
R0038 Preliminary Assessment Report
R0038 - Consolidated Consultation Responses
R0038 - Final Change Report V2.0
Company Name
-
Review status
Review required

Extensive Housekeeping Amendments

Date of latest update
Type
Change
ID
R0036
Change Category
Change Path
Priority
Urgent
No
Latest Update
_
Summary
_
Proposer
Ann Perry
Change Plan

Legal review of draft legal text

Completed

Start:

04 Mar 2022

Due:

19 Aug 2022

Completion:

19 Aug 2022

Creation of legal text in the EMAR

Completed

Start:

19 Aug 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Deadline for alternative change proposal submission

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Preliminary Change Report issued

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Start

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Ends

Completed

Start:

02 Sep 2022

Due:

26 Sep 2022

Completion:

26 Sep 2022

Final Change Report issued

Completed

Start:

26 Sep 2022

Due:

07 Oct 2022

Completion:

07 Oct 2022

Appeal window closure

Not Started

Start:

18 Oct 2022

Due:

01 Nov 2022

Completion:

Responsible Committee Decision

Completed

Start:

07 Oct 2022

Due:

18 Oct 2022

Completion:

18 Oct 2022
Status
Implementation Date
Status Live
EMAR Version 04.11.2022_live
Included changes Affected REC Items
R0002 Review of Data Specification Category in REC Baseline Statement

Documents

Name Version Last updated Actions
241.04 KB
Version 1.3 - 29 May 2026 XLSX - 241.04 KB
1.3 29 May 2026
455.42 KB
Version 1.3 - 29 May 2026 XLSX - 455.42 KB
1.3 29 May 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Jonathan Holland
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a REC Party, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Proposed Solution Document
Document title
R0036 - proposed changes v2.0
Archive
Off
Document title
Variants ONJOB Flows - Market Participant Mandatory v1.0
Archive
Off
Document title
EMAR Link 1
Archive
Off
Document title
EMAR Link 2
Archive
Off
Problem Statement
REC Parties and Service Providers rely on the REC to provide a consistent baseline to ensure the industry operates effectively and to give certainty to Parties obligations. There are currently inconsistencies between the drafting of the REC, and the processes operated by REC Parties and Service Providers. This could cause issues in the effective operation and assurance of the retail energy market.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0036 - proposed changes v1.0
R0036 - Change Proposal Plan v2.0 (Approved)
R0036 - Initial Assessment Report v1.0 (Approved)
R0036 - CP Form (Downloadable version)
R0036 - Consolidated consultation responses
Re-Baselined Change Proposal Plan for R0036
R0036 - Preliminary Change Report v1.0
R0036 - Final Change Report v2.0 (Post-Vote)
Company Name
-
Review status
Review required

Market Stabilisation Charge – Administration

Date of latest update
Type
Change
ID
R0035
Change Category
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Jon Dixon
Change Plan

Party Impact Assessment initiated

Completed

Start:

22 Feb 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Party Impact Assessment completed

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Preliminary Change Report issued

Completed

Start:

29 Apr 2022

Due:

06 May 2022

Completion:

06 May 2022

Issued to Responsible Committee for review (ex-Committee)

Completed

Start:

06 May 2022

Due:

10 May 2022

Completion:

10 May 2022

Consultation initiated

Completed

Start:

10 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Consultation completed

Completed

Start:

13 May 2022

Due:

01 Jun 2022

Completion:

01 Jun 2022

Final Change Report issued

Completed

Start:

01 Jun 2022

Due:

10 Jun 2022

Completion:

10 Jun 2022

Responsible Committee Decision (ex-Committee)

Completed

Start:

10 Jun 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Authority Determination

Completed

Start:

14 Jun 2022

Due:

24 Jun 2022

Completion:

27 Jun 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 30.06.2022_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Domestic Consumer, I want to be able to choose my Energy Supplier and a tariff from a range of competitive options, so that I can take advantage of cheaper deals as they become available.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
  3. As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
  4. As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send my invoices/credit notes, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I make to RECCo or at an appropriate time for my organisation. As a Domestic Supplier, I want to understand how I could dispute an invoice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly
Proposed Solution Document
Document title
Legal Text (tracked changes)
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A and introduced into the REC by Change Proposal R0034. A change is needed to the REC to set out the charging and payment mechanism, and to introduce the necessary governance arrangements to allow these MSC payments to be administered by RECCo.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0035 - CP Form (Downloadable version)
Ofgem Decision document - Short Term Interventions
MSC calculation guidance
Gas SLC Modified Decision Notice
Elec SLC Modified Decision Notice
R0035 - High level Solution Overview v1.0
R0035 - Change Proposal Plan v2.0 (Approved)
R0035 - Initial Assessment Report v2.0 (Approved)
R0035 - Consolidated IA responses v1.0
R0035 - Proposed Solution v2.0
R0035 - Preliminary Change Report v2.0 (Approved)
R0035 - Consolidated consultation responses v1.0
R0035 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0035
Company Name
RECCo
Review status
Review required

Market Stabilisation Charge

Date of latest update
Type
Change
ID
R0034
Change Category
Priority
Urgent
Yes
Latest Update
_
Summary
_
Proposer
Henry Kemp
Change Plan

Preliminary Change Report issued

Completed

Start:

21 Feb 2022

Due:

04 Mar 2022

Completion:

04 Mar 2022

Consultation issued (5 WD)

Completed

Start:

04 Mar 2022

Due:

04 Mar 2022

Completion:

04 Mar 2022

Final Change Report issued

Completed

Start:

04 Mar 2022

Due:

18 Mar 2022

Completion:

18 Mar 2022

Responsible Committee decision (ex-Committee)

Completed

Start:

18 Mar 2022

Due:

23 Mar 2022

Completion:

23 Mar 2022

Authority determination

Completed

Start:

23 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 14.04.2022_live
Included changes Affected REC Items
R0105 Review of ONAGE SLAs
  • Schedule 14 - Metering Operations
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
Proposed Solution Document
Document title
Legal Text
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A. A change is needed to the REC to give effect to the Market Stabilisation Charge from 14 April 2022.
Ofgem Decision Document - Short Term Interventions
R0034 - CP Form (Downloadable version)
R0034 - Change Proposal Plan v1.0 (Approved)
R0034 - Initial Assessment Report v1.0 (Approved)
R0034 - Preliminary Change Report v1.0 (Published for Consultation)
R0034 - Consolidated consultation responses v1.0
R0034 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0034 - Market Stabilisation Charge
Company Name
-
Review status
Review required

Micro-business Smart Meter Installation Reports

Date of latest update
Type
Change
ID
R0033
Change Category
Change Path
Priority
Urgent
No
Latest Update
_
Summary
_
Proposer
Kelly Austin
Change Plan

Legal text drafting initiated

Completed

Start:

07 Feb 2022

Due:

02 May 2022

Completion:

02 May 2022

Legal text drafting completed

Completed

Start:

02 May 2022

Due:

16 May 2022

Completion:

16 May 2022

Service Provider IA completed

Completed

Start:

16 May 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Preliminary Change Report issued

Completed

Start:

14 Jun 2022

Due:

01 Jul 2022

Completion:

01 Jul 2022

Consultation completed

Completed

Start:

01 Jul 2022

Due:

22 Jul 2022

Completion:

22 Jul 2022

Final Change Report issued

Completed

Start:

22 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022

Responsible Committee Decision

Completed

Start:

05 Aug 2022

Due:

16 Aug 2022

Completion:

16 Aug 2022
Status
Implementation Date
Status Live
EMAR Version 04.11.2022_live
Included changes Affected REC Items
R0002 Review of Data Specification Category in REC Baseline Statement

Documents

Name Version Last updated Actions
241.04 KB
Version 1.3 - 29 May 2026 XLSX - 241.04 KB
1.3 29 May 2026
455.42 KB
Version 1.3 - 29 May 2026 XLSX - 455.42 KB
1.3 29 May 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
colette.baldwin
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As a Micro-Business Consumer, I want my Energy Supplier to complete my Smart Meter installation in line with, or above, the standards of service provided by other Energy Suppliers, so that the installation of the Smart Meter has minimal disruption to my business.
  2. As an Energy Supplier to Micro-Business Consumers, I want access to Consumer feedback from across the industry, to enable me to assess my performance relative to other Micro-Business Energy Suppliers and identify areas of under or over performance, enabling me to take appropriate actions to increase or maintain my performance.
Proposed Solution Document
Document title
Proposed Draft Legal Text
Archive
Off
Document title
Final Change Report (Approved)
Archive
Off
Problem Statement
Energy Suppliers do not currently have the ability to assess their Micro-Business Smart Meter installation performance relative to other Energy Suppliers through Consumer Survey Reports, therefore may not take any appropriate action to address any areas of underperformance or respond to trends in Consumer feedback, wider than their own Consumer base. This could affect the Smart Meter installation service received by Micro-Business Consumers.
Micro Business Customer Survey Report Q2 2021
R0033 - CP Form (Downloadable version)
R0033 - Change Proposal Plan v1.0 (Approved)
R0033 - Initial Assessment Report v1.0 (Approved)
Consolidated Impact Assessment Responses
R0033 - Preliminary Change Report v1.0 (Published for Consultation)
R0033 -. Final Change Report (Post Vote)
Company Name
-
Review status
Review required

New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)

Date of latest update
Type
Change
ID
R0032
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Summary
This change seeks to deliver a recommendation from the Market-Wide Half Hourly Settlement Programme’s (MHHSP’s) Code Change and Development Group (CCDG), to introduce Registration Service Data Items that will be needed for MHHS, into the existing Supplier Meter Registration Service (SMRS) systems, before MHHS migration commences in October 2024.
Proposer
Colette Baldwin
Change Plan

Solution Analysis and Development

Completed

Start:

03 Feb 2022

Due:

09 May 2022

Completion:

09 May 2022

Service Provider Impact Assessment Issued

Completed

Start:

09 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Party Impact Assessment Issued

Completed

Start:

13 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Preliminary Change Report Issued

Completed

Start:

29 Jun 2022

Due:

29 Jul 2022

Completion:

29 Jul 2022

Consultation Issued

Completed

Start:

29 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022

Final Change Report Issued

Completed

Start:

05 Aug 2022

Due:

08 Nov 2022

Completion:

08 Nov 2022

Additional Impact Assessment Issued

Completed

Start:

13 May 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022

Responsible Committee Decision (Deferred from 20/09/22)

Completed

Start:

08 Nov 2022

Due:

15 Nov 2022

Completion:

15 Nov 2022
Status
Implementation Date
Status Live
EMAR Version 30.06.2023_live
Implementation Status
Date Raised
REC Decision Maker
Date of Update to Priority
Solution Development
Proposed solution summary
  1. As an impacted Market Participant, I want to ensure good quality underlying data is available to support the transition to HH Settlements to avoid additional time and effort being spent fixing data quality issues during the migration period.
  2. As the MHHS Programme, I want Registration Data Items to be available ahead of the MHHS migration to enable data cleanse activity to be completed to address data quality issues.
Proposed Solution Document
Document title
R0032 Final Solution Documents
Archive
Off
Problem Statement
There are Registration Service Data Items that are critical to the MHHS rules and processes. The MHHS Programme is concerned that starting migration in October 2024 with poor underlying data quality would lead to avoidable time and effort being spent fixing issues during the 12-month migration period. To facilitate MHHS Programme data cleanse activity, prior to the transition to Half Hourly Settlement, Registration Service Data Items need to be introduced into the existing Supplier Meter Registration Service (SMRS) system and displayed in EES.
SME
SME Role
Lead Technical Analyst
CCDG_Transition_Consultation_v1.0-1.pdf
Proposed D0312 data flow with new data items.pdf (03.02.2022)
R0032 - CP form (Downloadable version)
R0032 - Change Proposal Plan v2.0 (Approved)
R0032 Initial Assessment Report v1.0 (Approved)
R0032 Consolidated First Impact Assessment Responses
R0032 Consolidated Second Impact Assessment Responses
R0032 - Preliminary Change Report V1.0 (Approved)
R0032 - Consolidated Consultation Responses
R0032 - Final Change Report v3.0 (Post-Vote)
Company Name
-
Review status
Review required